Text
.
PHILAD ELPHIA ELECTRIC COM PANY 4-2301 M ARKET STREET
(
'q P.O. BOX 8699 d
)
g-[
PHILADELPHI A. PA.19101 i
,,j q
v SHIELDS L DALTROFF e4 g j$
e u crme m oouctio
<1 A
/
s s-April 5,
198 G>
iild '
Docket Nos. 50-277 50-278 Mr. John F.
Stolz, Chief U. S.
Nuclear Regulatory Commission Operating Reactors Branch #4 Division of Licensing Washington, DC 20555
Dear Mr. Stol z :
Your letter of March 5, 1982 requested additional information on the Peach Bottom Inservice Inspection Program.
Due to the significant amount of research required to address the subject with a complete and satisfactory response, we must request an extension for its submittal.
Peach Bottom Unit 2 is presently undergoing an extended refueling and modifications outage which requires significant attention by the same staffs-involved in preparing our response to your request.
A telephone conversation with the NRC Peach Bottom Project Manager on March-29, 1982, described the subject and an extension to June 8, 1982, was mutually determined to be appropriate.
If you have any further questions or require additional information, please do not hesitate to contact us.
Very truly yours,
]
Y Jef /
bg
/
/O 8204000247 8204U5 PDR ADOCK 05000277 O