ML20050B582

From kanterella
Jump to navigation Jump to search
Forwards Commitment to Confirm Presence of Strong Absorber in Facility Spent Fuel Racks by Performing Verification Tests at Manufacturer or Plant Site to Show Sufficient Amount of Neutron Absorber in Racks
ML20050B582
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 03/31/1982
From: Rausch T
COMMONWEALTH EDISON CO.
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
NUDOCS 8204060087
Download: ML20050B582 (2)


Text

-

' [N) one Fast NItsonst Ptalh Chicsgo, flhnois

~

Commonwealth Edison O

~Addr:ss R: ply to: Post Offics Box 767 Chicago, I!!inois 60690 March 31, 1982 Mr. Darrell G. Eisenhut, Director Division of Licensing U.S. Nuclear Regulatory Commission Washington, DC 20555

Subject:

Quad Cities Units 1 and 2 s/,,

High Density Fuel Rack N,

Modification - Neutron Y

s Attenuation Testing f

NCM 2 'h NRC Docket Nos. 50.254/265

]

.g.,

Reference (a):

B. Grimes letter to All Power E

nypyf[f((1 Reactor Licensees dated April 1 Tu^

/,x 1978.

g

?

27Tru

Dear Mr. Eisenhut:

Commonwealth Edison has recently reviewed the Reference (a)

"0T Position for Review and Acceptance of Spent Fuel Storage and Handling Application" requirement to confirm the presence of strong absorber material in new high density storage racks (refer to page III-3 o f Re ference (a)).

For the high density racks intended to be used at Quad Cities Station Units 1 aid 2, we have determined that this verification test may be more efficiently performed at the manufacturer than at the site.

Specifically, (1) this alternative would have less impact upon refueling outage preparations because fuel handling personnel and the reactor building crane will not need to be employed for this testing, and (2) this approach would result in a net reduction in personnel radiation exposures because work will be performed in lower background areas and with less interruption.

Considering the above, Commonwealth Edison intends to confirm the presence of strong absorber in the new Quad Cities spent fuel racks by performing verification tests at the manufacturer or at the Quad Cities site that will show within 95 percent confidence limits that there is a sufficient amount of neutron absorber in the racks to maintain the neutron multiplication factor at or below

[y/

0.95.

This apnroach has been discussed with the NRC Quad Cities

/1 f

Project Manager and we understand that there should be no concerns with your staf f.

f o kh 0

P

r s'

N,

^

z

.D.

G. Eisenhut=

2'-

March 31, 1982

.Please address any. questions you may have concerning this matter to this office.

One-(1) signed original and thirty-nine (39) copies of this transmittal have been.provided for'your use.

Very truly yours,

^=[

Thoma s J.

Rausch Nuclear Licensing Administrator.

Im j

cc:

Region III Inspector - Quad Cities 3767N i

i l

r l

l l

l L

- _. _. _ - _ _ _. _....... - _ _. _. _ _. _.. _ _., _