Revised Part 21 Rept Re Crosby SRV Solenoid Valves.Unit 1 Automatic Depressurization Sys SRV Solenoids Have Been Installed W/Qualified Collar/Yoke Assemblies
ML20050A889
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 03/24/1982
From: Schrader C
COMMONWEALTH EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
REF-PT21-82-600-000, RTR-NUREG-588 10CFR-50.55E, 3710N, PT21-82-600, PT21-82-600-000, NUDOCS 8204020368
Download: ML20050A889 (2)


Text

.' .

y Commonw2lth Edison One First National Plaza, Chicago. Illinois C Address Reply to: Post Office Box 767 Chicago, Ilhnois 60690 March 24, 1982 l

Mr. James G. Keppler, Regional Administrator Directorate o f Inspection and Enforcemen t - Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137

Subject:

LaSalle County Station Units 1 and 2 Crosby SRV Solenoid Valves 10 CFR s *js 50.55(e) Revised Final Report #81-06 @ N NRC Docke t Nos. 50-373 and 50-374 ',

S Reference (a): C. E. Sargent letter to J. G, ,

SMO h Keppler dated December 15, 1981. L p Appy 7gg {3 L

(b): C. E. Sargent letter to J. G. ~ En:antmmy7

mar n -e s Keppler dated November 19, 1981. T, W U/

\

(c): C. E. Sa rgent letter to J. G. 'b  ;

Keppler dated February 9, 1982.

Dea r Mr. Keppler:

The purpose of this letter is to provide a revised status o f the Crosby SRV Solenoid Valve 10 CFR 50.55(e) report as committed to in Reference (a) .

As described in Re ference (b), the final resolution to the Crosby Solenoid Valve qualification problem was pursued in parallel paths; one included modification of the collet / yoke assembly and the other was to provide a qualified Crosby Solenoid. The qualification of the Crosby Solenoid has not been completed nor has the material been delivered to the job site. Since this is considered to be the long term solution, the following installation schedule has been established:

Unit 1 - ADS-SRV's - Interim fix in accordance with Reference (a) has been completed Unit 1 - Remaining SRV's - Testing to assure acceptance criteria is met has been completed Unit 1 - All SRV's - Long term fix (installation o f qualified Crosby Solenoid) prior to startup following first refuel outage Unit 2 - All SRV's - Long term fix prior to heatup.

nr2 S

woe 9N! ma I

O J. G. Keppler March 24, 1982 All Unit 1 ADS SRV Solenoids have had the qualified collet /

yoke assembly installed in them. This modification and the manufac-turer's testing to 1EE 323 (1971) standards qualifies these valves for plant operation until further testing to NUREG 0588 requirements is completed under Commonwealth Edison Company's Equipment Qualifi-cation program.

If there are any further questions in this regard, please contact this office.

Very truly yours,

/

3/2.99' C.W. Schroeder Nuclea r Licensing Administrato r 1m cc: Director o f Inspection and Enforcemen t - Washington , D .C.

Hegion III Inspector - LSCS 3710N