g Comm:nw:cith Edison O / one First National Plaza. Chicago, lihnois i
C/
Address Reply to: Post Office Box 767 Chicago, Illinois 60690 March 25, 1982 Mr. James G. Keppler, Regional Administrator Directorate of Inspection and Enforcement - Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137
Subject:
LaSalle County Station Units 1 and 2 Motor Terminal Block Voltage Rating in Limitorque Valve Controls ps, j ' h' 10 CFR 50.55(e) #81-01 Final Report NRC Docket Nos. 50-373 and 50-374 p
MEC:
9 References (a):
L.
DelGeorge to J.
G. Keppler 2D s
dated February 20, 1981.
Same k-APRJ Subject, 30 Day Report.
3 Ugrgt.
2 'I (b):
L. DelGeorge to J.
G.
Keppler
- N '
//
dated July 15, 1981.
Same qp c(\\
Subject, Interim Report.
I.T ' M (c):
C.
Sargent letter to J.
G. Keppler dated Septembe r 15, 1981.
Same Subject, Interim Report.
(d):
C.
Sargent letter to J.
G.
Keppler dated October 29, 1981.
Same Subject, Interim Report.
(e):
C.
Sargent letter to J.
G. Keppler dated-Decembe r 15, 1981.
Same Subject, In terim Report.
Dear Mr. Keppler:
The purpose o f this letter is to submit the Final Report
- 81-01 regarding the subject Motor Terminal Block Modification.
This incident was initially reported to your o f fice on January 21, 1981, a 30-day report was made (Reference (a)), and several interim reports have been submitted (References (b),(c),(d), and (e)).
d}h s204o20260 e20223 PDR ADDCK 05000373 S
% 20 PDR
=
i J. G. Keppler March 25, 1982 J
The Unit 1 status is as follows:
1.
All Unit 1 limitorques have been inspected.
2.
All Unit 1 limitorques that are fed by Safety-Related cables have had the motor terminal blocks removed and a lug to-lug connection installed.
+
2 3.
Unit 1 limitorques that are fed by Non-Safety-Related cables will have the motor terminal blocks removed and j
a lug to lug connection installed prior to Unit 1 criticality.
(Note:
Limitorque operators type SMC-04 s
and type PB do not contain a motor terminal block l
because the motor leads are terminated on the control terminal block.
These limitorques were inspected and i
found to have the correct size control terminal block and the correct cable terminations.
In addition, these types of limitorque operators are only fed by non-safety-related cables at LaSalle County Station).
The Unit 2 status is as follows:
Unit 2 limitorques will be inspected and reworked prior to Unit 2 fuel load.
Limitorque operators type SMC-04 and type PB will be inspected for correct size control terminal I
block and for the correct cable terminations, q
If there are any further questions in this matter, please contact this o f fice.
I Very truly yours, i
@W 3hs/82.
C.
W. Schroeder Nuclear Licensing Administrator 1m i