Confirms Commitments/Clarifications Made in 820305 Telcon Re SER Suppl 1 Outstanding Issues Concerning Pool Dynamic Loads,Equipment Dynamic Qualification,Ie Bulletin 79-27, Pumpback Sys,Mgt Organization & Scram Sys Piping
ML20049J334
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 03/10/1982
From: Grunseich R
LONG ISLAND LIGHTING CO.
To: Joshua Wilson
Office of Nuclear Reactor Regulation
References
IEB-79-27, NUDOCS 8203150091
Download: ML20049J334 (2)


Text

l 4

LONG ISLAND LIGHTING COM PANY SHOREHAM NUCLEAR POWER STATION

, P.O. DOX 610, NORTH COUNTRY ROAD e WAL NO RIVER, N.Y. p b

March 10, 1982 O hECiWjpg 1 2- -

A,RR1 5199g ,_ -

Mr. Jerry Wilson Division of Licensing ,Naugrg

\ yp D .

U.S. Nuclear Regulatory Commission Washington, DC 20555 t

=

SER Supplement No. 1 - Outstanding Issues Shoreham Nuclear Power Station - Unit 1

Dear Mr. Wilson:

Based on the telephone conversation between yourself and Mr.

J. L. Smith and Mr. R. Grunseich of LTLCO on March 5, 1982, tr a below listed commitments / clarifications were made relative to SER Supplement No. 1 Outstanding Issues:

1. Pool Dynamic Loads (O.I. #1) - LILCO to check and confirm that commitment made in ACRS letter of October 19, 1981 has been met.
2. Equipment Dyrc.mic Qualification - (O.I. #8) - Meeting on certain items addressed in February 26, 1982 NRC letter will be arranged, if necessary, tentatively for the week of March 22, 1982.
3. Equipment Environmental Qualification (O.I. #9) -

Meeting to discuss this item to be tentatively arranged in conjunction with No. 2 above.

4. Preservice Inspection (O.I. #19) - LILCO will provide schedule for submittal of confirmatory information necessary to completely resolve issue.
5. Suppression Pool Bypass (O.I. #26) - Telephone conference call to be arranged with Mel Fields of NRR regarding requirements for low pressure test of suppression pool bypass.
6. Pumpback System (O.I. #39) - LILCO will provide schedule for preparation of the alarm response procedure.
7. I&E Bulletin 79-27 (O.I. #46) - LILCO will provide a schedule for submittal of confirmatory information on this issue.

0k 9

8203150091 820310 PDR ADOCK 05000322 6s 0 E PDR

March 10, 1982 Mr. Jerry Wilson Page 2

8. Management Organization (O.I. #52) - Telephone cail and/or meeting to be arranged with G. Rivenbark of NRR on this issue.
9. Post Accident Sampling (O.I. II.B.3) - Telephone call and/or meeting to be arranged with J. Wing of NRR on this issue.
10. Emergency Response Facilities (O.I. III.A.l.2) -

Verbal approval has been indicated by the NRC for our plans relative to possible use of the security building as a " fallback" TSC as outlined in letter SNRC-613.

11. Scram System Piping (O.I. #61) - NRC will provide schedule on their review of this item, which is also being tricked as an NRC Generic Letter. LILCO is in the process of developing further information on this matter which they could present to the staff at a future date.

Should you have any comments, please contact this office.

l Very truly yours,

$W -/h w R. W. Grunseich Senior Licensing Engineer Shoreham Nuclear Power Station RWG:mp cc: Mr. Robert Gilbert - NRC J. L. Smith M. II . Milligan