Suppls 810324 Response to NRC Re Violation Noted in IE Insp Rept 50-293/81-01.Extension of Final Implementation Date Until 820415 Requested Due to Delay in Procuring Environmentally Qualified Components
ML20049H656
Person / Time
Site: Pilgrim
Issue date: 01/13/1982
From: Morisi A
BOSTON EDISON CO.
To: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML20049H651 List:
References
82-7, NUDOCS 8203030415
Download: ML20049H656 (1)


Text

'

BOSTON EO SON COMPANY DENERAL OFFICES 800 00VLETON STREET GO STO N. M ASSACMum ETTs 0219 9 A. V. MO R15 0 MANAGER NUCLEAR OPERATION 5 SUPPORT DEPARTMENT January 13,1982 BECo. Ltr. #82-7 Mr. Eldon J. Brunner, Chief Reactor Operations and Nuclear Support Branch Office of Inspection and Enforcement Region I U.S. Nuclear Regulatory Comission 631 Fark Avenue King of Prussia, PA.

19406 License No. DPR-35 Docket No. 50-293 Fire Protection Deluge System for the Standby Gas Treatment System

References:

(a) BECo Letter #81-65, dated 3/24/81 A. V. Morisi to Eldon J. Brunner (b)

IE Inspection #81-01, dated 2/19/81

Dear Sir:

In Reference (a), as part of Boston Edison's response to Violation A of Reference (b) concerning the Standby Gas Treatment System (SBGTS) at Pilgrim Nuclear Power Station, Boston Edison stated that modification of the Deluge System was scheduled to be completed during our next refueling outage. We are herein requesting that the date for final implementation be extended to April 15,1982.

We believe this request to be justified by the extensive delays Boston Edison has experienced in procuring environmentally qualified components (79-01B).

We have now procured the majority of these components, though they are many weeks behind schedule. A projected eight week installation period will bring the, final installation date to. February 26,1982.

Procedures and training relevant to this system shall be completed by April,1982.

The fire patrol that was established in, accordance with the requirements of our Technical Specifications and our response in Reference (a) shall continue until the SBGTS Deluge System modification is completed. Further, interim corrective measures and procedural changes have been emplaced to insure system operability.

If you have any questions concerning this request, please contact us.

Very truly yours 8203030415 820224 PDR ADOCK 05000293