|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARIR 05000412/19990071999-10-21021 October 1999 Refers to Special Team Insp 50-412/99-07 Conducted from 990720-29 & Forwards Nov.Two Violations Identified.First Violation Involved Failure to Implement C/A to Prevent Biofouling of Service Water System ML20217M1591999-10-19019 October 1999 Forwards NRC Rept Number 17, Requal Tracking Rept from Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates L-99-143, Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct1999-10-11011 October 1999 Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct L-99-152, Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections1999-10-11011 October 1999 Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections ML20217C6741999-10-0808 October 1999 Forwards RAI Re Licensee 970128 Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions, . Response Requested within 60 Days of Receipt of Ltr L-99-151, Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program1999-10-0707 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program ML20217E0301999-10-0707 October 1999 Forwards Insp Repts 50-334/99-06 & 50-412/99-06 on 990809-13 & 990823-27.Violation Noted Involving Failure to Correctly Translate Design Change Re Pertinent Operating Logs & Plant Equipment Labeling ML20212M2661999-09-30030 September 1999 Forwards Order Approving Transfer of Licenses for Beaver Valley from Dlc to Pennsylvania Power Co & Approving Conforming Amends in Response to 990505 Application ML20212K8071999-09-30030 September 1999 Informs That on 990916,NRC Staff Completed mid-cycle Plant Performance Review (PPR) of Facility.Staff Conducted Reviews of All Operating NPPs to Integrate Performance Info & to Plan for Insp Activities at Facility ML20216J9621999-09-30030 September 1999 Forwards Insp Repts 50-334/99-05 & 50-412/99-05 on 990725-0904.Two Violations Noted & Being Treated as Ncvs.One Violation Re Failure to Follow Operation Manual Procedure Associated with Configuration Control Identified L-99-149, Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion1999-09-28028 September 1999 Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion L-99-148, Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 9908171999-09-24024 September 1999 Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 990817 ML20212G0601999-09-23023 September 1999 Forwards Answer of Duquesne Light Co to Petition to Waive Time Limits & Suppl Comments of Local 29, Intl Brotherhood of Electrical Workers.Copies of Answer Have Been Served to Parties & Petitioner by e-mail or Facsimile ML20212C5521999-09-21021 September 1999 Forwards for Filing,Answer to Firstenergy Nuclear Operating Co & Pennsylvania Power Co in Opposition to Petition to Waive Time Limits & Suppl Comments of Local 29 Intl Brotherhood of Electrical Workers L-99-144, Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-031999-09-20020 September 1999 Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-03 ML20212B3291999-09-16016 September 1999 Forwards for Filing,Petition to Waive Time Limits in 10CFR2.1305 & Supplemental Comments of Local 29,Intl Brotherhood of Electrical Workers Re Beaver Valley Power Station,Units 1 & 2 L-99-134, Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC1999-09-15015 September 1999 Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC ML20211Q3431999-09-0808 September 1999 Informs That During 990903 Telcon Between L Briggs & T Kuhar,Arrangements Were Made for NRC to Inspect Licensed Operator Requalification Program at Plant,Unit 1.Insp Planned for Wk of 991115 ML20211Q5601999-09-0707 September 1999 Forwards Insp Rept 50-412/99-07 on 990720-29.Three Apparent Violations Noted & Being Considered for Escalated Ea. Violations Involve Failure to Implement C/As to Prevent bio- Fouling of Svc Water Sys L-99-138, Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d)1999-09-0303 September 1999 Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d) L-99-136, Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls1999-09-0202 September 1999 Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls L-99-098, Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods1999-09-0202 September 1999 Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods L-99-137, Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 31999-08-31031 August 1999 Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 3 L-99-022, Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl1999-08-31031 August 1999 Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl L-99-012, Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B L-99-037, Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change L-99-132, Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 21999-08-26026 August 1999 Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 2 05000412/LER-1999-007, Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info1999-08-19019 August 1999 Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info ML20211A5111999-08-18018 August 1999 Forwards Insp Repts 50-334/99-04 & 50-412/99-04 on 990613- 990724.One Violation Noted & Treated as Non-Cited Violation Involved Failure to Maintain Containment Equipment Hatch Closed During Fuel Movement L-99-127, Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel1999-08-17017 August 1999 Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel L-99-124, Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached1999-07-30030 July 1999 Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached L-99-121, Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements1999-07-28028 July 1999 Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements L-99-118, Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 20011999-07-25025 July 1999 Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 2001 L-99-120, Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations1999-07-22022 July 1999 Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations L-99-119, Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 9901221999-07-20020 July 1999 Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 990122 L-99-113, Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by1999-07-15015 July 1999 Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by L-99-111, Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes1999-07-15015 July 1999 Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes L-99-112, Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl1999-07-14014 July 1999 Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl L-99-110, Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.61999-07-14014 July 1999 Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6 ML20209G5701999-07-12012 July 1999 Discusses Closure of TACs MA0525 & MA0526 Re Response to RAI Concerning GL 92-0,Rev 1,Suppl 1, Rv Structural Integrity. Info in Rvid Revised & Released as Ver 2 as Result of Review of Response ML20207H6621999-07-0808 July 1999 Forwards RAI Re Util 981112 Response to IPEEE Evaluations for Plant,Units 1 & 2.RAI Was Discussed During 990628 Telcon in Order to Ensure Clear Consistent Understanding by All Parties of Info Needed L-99-105, Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves1999-07-0808 July 1999 Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves ML20209D8191999-07-0707 July 1999 Forwards Insp Repts 50-334/99-03 & 50-412/99-03 on 990502- 0612.No Violations Noted.Program for Maintaining Occupational Exposures as Low as Reasonably Achievable (ALARA) & for Training Personnel,Generally Effective L-99-109, Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-62301999-07-0707 July 1999 Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-6230 L-99-108, Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC1999-07-0707 July 1999 Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC L-99-104, Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl1999-06-29029 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl L-99-093, Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.51999-06-25025 June 1999 Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.5 L-99-102, Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl1999-06-22022 June 1999 Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl L-99-101, Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal1999-06-22022 June 1999 Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal L-99-062, Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages1999-06-17017 June 1999 Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages 1999-09-08
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARL-99-152, Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections1999-10-11011 October 1999 Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections L-99-143, Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct1999-10-11011 October 1999 Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct L-99-151, Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program1999-10-0707 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program L-99-149, Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion1999-09-28028 September 1999 Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion L-99-148, Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 9908171999-09-24024 September 1999 Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 990817 ML20212G0601999-09-23023 September 1999 Forwards Answer of Duquesne Light Co to Petition to Waive Time Limits & Suppl Comments of Local 29, Intl Brotherhood of Electrical Workers.Copies of Answer Have Been Served to Parties & Petitioner by e-mail or Facsimile ML20212C5521999-09-21021 September 1999 Forwards for Filing,Answer to Firstenergy Nuclear Operating Co & Pennsylvania Power Co in Opposition to Petition to Waive Time Limits & Suppl Comments of Local 29 Intl Brotherhood of Electrical Workers L-99-144, Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-031999-09-20020 September 1999 Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-03 ML20212B3291999-09-16016 September 1999 Forwards for Filing,Petition to Waive Time Limits in 10CFR2.1305 & Supplemental Comments of Local 29,Intl Brotherhood of Electrical Workers Re Beaver Valley Power Station,Units 1 & 2 L-99-134, Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC1999-09-15015 September 1999 Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC L-99-138, Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d)1999-09-0303 September 1999 Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d) L-99-136, Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls1999-09-0202 September 1999 Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls L-99-098, Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods1999-09-0202 September 1999 Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods L-99-137, Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 31999-08-31031 August 1999 Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 3 L-99-022, Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl1999-08-31031 August 1999 Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl L-99-037, Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change L-99-012, Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B L-99-132, Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 21999-08-26026 August 1999 Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 2 05000412/LER-1999-007, Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info1999-08-19019 August 1999 Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info L-99-127, Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel1999-08-17017 August 1999 Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel L-99-124, Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached1999-07-30030 July 1999 Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached L-99-121, Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements1999-07-28028 July 1999 Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements L-99-118, Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 20011999-07-25025 July 1999 Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 2001 L-99-120, Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations1999-07-22022 July 1999 Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations L-99-119, Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 9901221999-07-20020 July 1999 Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 990122 L-99-111, Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes1999-07-15015 July 1999 Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes L-99-113, Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by1999-07-15015 July 1999 Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by L-99-112, Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl1999-07-14014 July 1999 Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl L-99-110, Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.61999-07-14014 July 1999 Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6 L-99-105, Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves1999-07-0808 July 1999 Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves L-99-108, Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC1999-07-0707 July 1999 Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC L-99-109, Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-62301999-07-0707 July 1999 Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-6230 L-99-104, Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl1999-06-29029 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl L-99-093, Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.51999-06-25025 June 1999 Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.5 L-99-102, Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl1999-06-22022 June 1999 Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl L-99-101, Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal1999-06-22022 June 1999 Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal L-99-062, Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages1999-06-17017 June 1999 Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages ML20196A6601999-06-16016 June 1999 Forwards Master Decommissioning Trust Agreements Revised After 1990 for Ohio Edison Co,Cleveland Electric Illuminating Co,Toledo Edison Co & Pennsylvania Power Co Re Bvnps,Units 1 & 2,DBNPS,Unit 1 & Perry Unit 1 ML20195H4651999-06-16016 June 1999 Forwards for Filing Answer of Firstenergy Corp in Opposition to Petition for Leave to Intervene of Local 29, Intl Brotherhood of Electrical Workers. Copies of Answer Have Been Served Upon Parties & Petitioner by e-mail ML20195J5221999-06-16016 June 1999 Forwards Answer of Duquesne Light Co to Petition to Intervene of Local 29,International Brotherhood of Electrical Workers in Listed Matter.With Certificate of Svc L-99-100, Forwards Typed,Final TS Pages for LAR 109 Re Rcs.Summary Description of Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages Is Provided in Attachment B-1091999-06-15015 June 1999 Forwards Typed,Final TS Pages for LAR 109 Re Rcs.Summary Description of Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages Is Provided in Attachment B-109 L-99-095, Provides Addl Info to Support LARs 262 & 135,in Response to NRC 990527 Verbal Request.Info Describes Performance of Unit 1 Rod Position Indication Sys & Provides Some Background Info Re Normal Operation of Sys1999-06-15015 June 1999 Provides Addl Info to Support LARs 262 & 135,in Response to NRC 990527 Verbal Request.Info Describes Performance of Unit 1 Rod Position Indication Sys & Provides Some Background Info Re Normal Operation of Sys L-99-099, Requests Partial Withdrawal of LAR 120,which Requested Review of USQ Due to Increased Calculated Doses for Locked Rotor Event & Use of Unapproved Methodology for Evaluating Small Break LOCA Doses Involving W Natl Safety Advisory Ltr1999-06-14014 June 1999 Requests Partial Withdrawal of LAR 120,which Requested Review of USQ Due to Increased Calculated Doses for Locked Rotor Event & Use of Unapproved Methodology for Evaluating Small Break LOCA Doses Involving W Natl Safety Advisory Ltr ML20195H3731999-06-0303 June 1999 Forwards Petition to Intervene of Local 29,Intl Brotherhood of Electrical Workers in Matter of Firstenergy Nuclear Operating Co,For Filing L-99-090, Forwards Summary Review Completed to Verify Adequacy of Design Basis Accident Thermal Overpressure Protection for BVPS Unit 2 Containment Penetrations,Per Request1999-06-0202 June 1999 Forwards Summary Review Completed to Verify Adequacy of Design Basis Accident Thermal Overpressure Protection for BVPS Unit 2 Containment Penetrations,Per Request L-99-086, Forwards Bvps,Unit 2 SG Exam Rept for Aug 1998.Rept Provided to Document Results of SG Eddy Current Exams Performed in Aug 1998.Summary of Insps Provided in Encl 11999-05-28028 May 1999 Forwards Bvps,Unit 2 SG Exam Rept for Aug 1998.Rept Provided to Document Results of SG Eddy Current Exams Performed in Aug 1998.Summary of Insps Provided in Encl 1 L-99-089, Forwards Annual Financial Repts,Including Certified Financial Statements,Of Dqe,Firstenergy Corp,Ohio Edison Co,Pennsylvania Power Co,Cleveland Electric Illuminating Co & Toledo Edison Co,Iaw 10CFR50.71(b)1999-05-28028 May 1999 Forwards Annual Financial Repts,Including Certified Financial Statements,Of Dqe,Firstenergy Corp,Ohio Edison Co,Pennsylvania Power Co,Cleveland Electric Illuminating Co & Toledo Edison Co,Iaw 10CFR50.71(b) L-99-084, Forwards Revised marked-up TS & UFSAR Pages to 990303 LARs 259 & 131 Which Revised Qualifications for Operations Mgt & Incorporated Generic Position Titles in Ts.Encl Pages Incorporate NRC Requested Changes,Per Recent Telcon1999-05-27027 May 1999 Forwards Revised marked-up TS & UFSAR Pages to 990303 LARs 259 & 131 Which Revised Qualifications for Operations Mgt & Incorporated Generic Position Titles in Ts.Encl Pages Incorporate NRC Requested Changes,Per Recent Telcon L-99-082, Dockets Licensee Plan for Bvps,Unit 1,safety-related Small Bore Piping Evaluation Project Discussed in NRC 990311 Public Meeting at BVPS1999-05-17017 May 1999 Dockets Licensee Plan for Bvps,Unit 1,safety-related Small Bore Piping Evaluation Project Discussed in NRC 990311 Public Meeting at BVPS L-99-071, Notifies of License Withdrawal for J Scott,License SOP-11481,due to Resignation from Employment at BVPS1999-05-12012 May 1999 Notifies of License Withdrawal for J Scott,License SOP-11481,due to Resignation from Employment at BVPS 1999-09-03
[Table view] |
Text
Beaver Va ey Power Station Shippingport, PA 15077 6 4 (412) 393-5206 (412) f.43-8069 FAX GEORGE S.1HOMA$
Dmsson Vee Pmsident Nuclear Servces Nuclear Poww Division ,
U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555
Subject:
Beaver Valley Power Station, Unit No. I and No. 2 BV-1 Docket No. 50-334, License No. DPR-66 BV-2 Docket No. 50-412, License No. NPF-73 Response to Generic Letter 93-04: Rod Control System 1 Failure and Withdrawal of Rod Control Cluster Assemblics, 10 CFR 50.54(f)
Pursuant to the requirements of 10 CFR 50.54(f), the NRC issued .
Generic Letter 93-04, " Rod Control System Failure and Withdrawal of Rod Control Cluster Assemblies," on Monday, June 21, 1993 to all licensees with the Westinghouse Rod Control System (except Haddam ,
Neck) for action and to all other licensees for information.
The generic letter requires that, within 45 days from the date of the generic letter, each addressee provide an assessment of whether or not the licensing basis for each facility is still satisfied with regard to the requirements for system response to a single failure in the Rod Control System (GDC 25 or equivalent). If the assessment
[ Generic Letter Required Response 1.(a)] indicates that the licensing basis is not satisfied, then the licensee must describe compensatory short-term actions consistent with the guidelines contained in the
' generic letter, and within 90 days, provide a plan and schedule for >
long-term resolution [ Generic Letter Required Response 1. (b) ] . .
Subsequent correspondence between the Westinghouse owners Group and the NRC resulted in schedular relief for Required Response.l.(a)-(NRC- ,
Letter- to Mr. Roger Newton dated July 26, 1993). This portion of the l required actions will now be included with the 90-day licensee-response.
Duquesne Light Company (DLC) hereby submits in the Attachment to this letter- its- response to -the- Generic Letter as it applies to Beaver Valley . Power Station (DVPS) Unit No. 1 and No.'2. This response summarizes the compensatory actions taken by DLC in response to the ,
Salem rod control system failure event. It also provides a summary of the results of the generic safety analysis program conducted by the Westinghouse owners Group and its applicability to BVPS Unit No.
1 and No. 2. DLC considers this action to be complete.with respect to the 45 day required response to GL 93-04 (as amended by July 26 NRC letter to Mr. Roger Newton).
9309130057 930806 PDR_.ADOCK ' 05000334 P PDR US{
hi g}'
j( l
'AI e . .
. .Foiluro and Withdrawal.of Rod Control Cluster. l
-Assemblies, 10 CFR 50.54(f)
Page.2 ,
.j If you 'have any questions.concerning this response, please contact
(
Drexel Williams at (412):393-5226.
Sincerely,.
~
Georg }eThomas.
S.b /?Y n 3 ,
Attachment cc: Mr. L. W. Rossbach, Sr. Resident Inspector !
Mr. T. T. Martin, NRC Region I Administrator ;
Mr. G. E. Edison, Project Manager _;
h I
r h
t
I i
1 AFFIDAVIT COMMONWEALTH OF PENNSYLVANIA)
) SS: ,
COUNTY OF BEAVER ) l 1
Subject:
Beaver Valley Power Station, Unit No. 1 and No. 2 BV-1 Docket No. 50-334, License No. DPR-66 BV-2 Docket No. 50-412, License No. NPF-73 Response to Generic Letter 93-04: Rod Control System Failure and Withdrawal of Rod Control Cluster Assemblics, 10 CFR 50.54(f) ,
Before me, the undersigned notary public, in and for the County and Commonwealth aforesaid, this day personally appeared George S.
Thomas, to me known, who being duly sworn according to law, deposes and says that he is Division Vice President, Nuclear Services of the Nuclear Power Division, Duquesne Light Company, he is duly authorized to execute and file the foregoing submittal on behalf of said Company, and the statements set forth in the submittal are true and correct to the best of his knowledge, information and belief.
i i
YMcb. MR Geor6e S. Thomas Subscribed and sworn to before me on this day of inid
(
, /f(h L.d (LA'l {! /A4# #
Notary Public l NotarialSeal TraceyA BaczeK NotayPubic i Shopngret Dora,BeawsCounty th ConvrraionExpres Aug.16,1993 Mmber,Pems>4mra Araxiaonof Noah i
DUQUESNE LIGHT COMPANY Nuclear Power Division ATTACHMENT Response to NRC GL 93-04, Rod Control System Failure and Withdrawal of Rod Control Cluster Assemblies. 10 CFR 50.54(f)
I. Compensatory Actions e Describe any compensatory short-term actions taken or that will be taken to address any actual or potential degraded or nonconforming conditions (see Generic Letter 91-18, Reference 1) such as:
- 1. " additional cautions or modifications to surveillance and preventive maintenance procedures" -
Westinghouse did not make any initial recommendations regarding surveillance or preventative maintenance procedures. Based on the response provided in Westinghouse Owners Group (WOG) letter OG-93-42, there was no perceived need to increase the frequency of ;
testing on a permanent or generic basis. PSE&G had committed to a temporary increase in testing, but only until it was demonstrated that the rod control system was operating properly. A recommendation was made for utilities to ensure that their surveillance testing will demonstrate rod control system operability and address maintenance trouble-shooting. Increased surveillance testing can, in and of itself, result in higher rates of system and component failures.
Therefore, the WOG and Westinghouse have concluded that increased frequencies in surveillance testing is not required or appropriate in response to the Salem rod control system failure event.
Surveillance testing at BVPS Unit No. 1 and No. 2 meets the requirements of the individual plant -technical -'
specifications. Every 31 days, when in Modes 1 or 2, each unit verifies that each control rod not_ fully inserted in the core is operable by moving each control ,
rod at least 10 Steps in any one direction. Comparison' '
of the individual control rod position-indication with >
group position indication confirms proper control rod 1 motion. Existing surveillance procedures are adequate I to assure rod control system operability, and the existing site / station guidance with respect to maintenance troubleshooting is sufficient to handle- j anticipated problems. At BVPS Unit No. 1 the i individual rod position indication and group _ demand position indication are logged every four hours to i
I ATTACHMENT j Response to NRC GL 93-04 :
Page 2 ;
assure proper alignment of the control rods and proper response of the system to demands for rod motion. At J BVPS Unit No. 2 the rod deviation alarms will alert the operators to system malfunctions should the operator i not detect'the problem when proper control rod response-is observed during/following demands for control rod !
notion. >
i a
'i t
i 5
i i
i j
-ATTACHMENT Response to NRC GL 93-04 Page 3
- 2. " additional administrative controls for plant startup and power operation" - l l
PSE&G committed the Salem units to startup by dilution. Neither Westinghouse nor the WOG has ;
endorsed this requirement. In actual operation, the l' operators would be aware of abnormal rod movement and terminate rod demand prior to ever reaching criticality. The operator would be manually controlling the rod withdrawal such that the detection of rod mis-stepping in under 1 minute would be :
reasonable. In fact, as demonstrated during the R. E.
Ginna event, abnormal rod motion was terminated after only one step both in automatic and manual rod control. It is unrealistic to believe that the operators would permit an unchecked rod withdrawal during startup such that criticality would be reached.
Thus, the WOG and Westinghouse have concluded that startup by dilution is not required in response to the Salem rod control system failure event.
i All of the licensed operators for BVPS Unit No. 1 and No. 2 have read the Westinghouse Nuclear Safety .
Advisory Letter (NSAL-93-007) regarding the rod control system failure which occurred at Salem Unit No. 2.
Thus, the operators are alerted to the potential for improper rod motion. As a matter of routine operation, the operators at BVPS Unit No. 1 and No. 2 confirm proper response of the control rods to a demand for control rod motion. :
1 i
i l
1 l
-)
I I
ATTACHMENT Response to NRC GL 93-04 Page 4
- 3. " additional instructions and training to heighten operator awareness of potential rod control system failures and to guide operator response in the event of a rod control system malfunction" - '
l Both Westinghouse and the WOG have, at various times, !
recommended that licensees provide additional discussion, l training, standing orders, etc. to ensure that operators are aware of the Salem event. The recommendations of the Westinghouse Nuclear Safety Advisory Letter, which was subsequently endorsed by the WOG via Letter OG-93-42, recognize the benefits of ensuring that plant operators'are i knowledgeable of Salem rod control system failure event.
As stated previously, the licensed operators'at both BVPS Unit No. 1 and No. 2 have read the Westinghouse Nuclear Safety Advisory Letter (NSAL-93-007) regarding the rod f control system failure which occurred at Salem Unit No. 2.
This served to heighten the operators' awareness for potential improper response of the rod control system to a 4 demand for control rod motion. In addition, operators are programmatically trained in normal and abnormal rod control system operation, and drilled on unit-specific simulators in response to rod control system failures.
Following completion of the WOG programs, which are underway i to investigate and better understand the Salem Unit No. 2 event, recommendations for classroom and simulator training i and event response procedures may be made by WOG and/or '
Westinghouse for guidance for all affected utilities. DLC will utilize such guidance in determining appropriate revisions to training and event response procedures at BVPS Unit No. 1 and No. 2. ;
(
l l
l l
I l
i l
i ATTACHMENT .
I Response to NRC GL 93-04 page 5 II. Summary of the Generic Safety Analysis Procram Introduction As part of the Westinghouse Owners Group initiative, the WOG Analysis subcommittee is working on a generic approach to demonstrate that for all Westinghouse plants there is no safety significance for an asymmetric RCCA withdrawal. The purpose of the program is to analyze a series of asymmetric rod withdrawal cases from both subcritical and power conditions to demonstrate that DNB does not occur.
The current Westinghouse analysis methodology for the. hank withdrawal at power and from subcritical uses point-kinetics and one dimensional kinetics transient models, respectively. These models use conservative constant reactivity feedback assumptions which result in an overly conservative prediction of the core response for these events.
A three-dimensional spatial kinetics / systems transient code '
(LOFT 5/SPNOVA) is being used to show that the localized power peaking is not as severe as current codes predict. The 3-D transient analysis approach uses a representative standard 4-Loop Westinghouse plant with conservative reactivity assumptions.
Limiting asymmetric rod withdrawal statepoints (i.e., conditions associated with the limiting time in the transient) are established for the representative plant which can be applied to i all Westinghouse plants. Differences in plant designs are ;
addressed by using conservative adjustment factors to make a plant-specific DNB assessment.
Description of Asymmetric Rod Withdrawal ,
The accidental withdrawal of one or more RCCAs from the core is assumed to occur which results in an increase in the core power ,
level and the reactor coolant temperature and pressure. If the reactivity worth of the withdrawn rods is sufficient, the reactor ,
power and/or temperature may increase to the point that the transient is automatically terminated by a reactor trip on a High Nuclear Flux or Over-Temperature Delta-T (OTDT) protection signal. If the reactivity rise is small, the reactor power will reach a peak value and then decrease due to the negative feedback effect caused by the moderator temperature rise. The accidental withdrawal of a bank or banks of RCCAs in the normal overlap mode is a transient which is specifically considered in safety analysis reports. The consequences of a bank withdrawal accident meet Condition II criteria (no DNB). If, however, it is assumed >
that less than a full group or bank of control rods is withdrawn, and these rods are not symmetrically located around the core, this can cause a " tilt" in the core radial power distribution.
The " tilt" could result in a radial power distribution peaking factor which is more severe than is normally considered in the plant safety analysis report, and therefore cause a loss of DNB
ATTACHMENT Response to NRC GL 93-04 Page 6 l l
t I
margin. Due to the imperfect mixing of the fluid exiting the core before it enters the hot legs of the reactor coolant loops, j there can be an imbalance in the loop temperatures, and therefore in the measured values of T-avg and delta-T, which are used in the over-Temperature Delta-T protection system for the core. The radial power " tilt" may also affect the ex-core detector signals used for the High Nuclear Flux trip. The axial offset (AO) in the region of the core where the rods are withdrawn may become more positive than the remainder of the core, which can result in an additional DNB penalty.
Methods The LOFT 5 computer code is used to calculate the plant transient response to an asymmetric rod withdrawal. The LOFT 5 code is a combination of an advanced version of the LOFT 4 code (Reference 1), which has been used by Westinghouse in the analysis of the RCS behavior to plant transients and accidents, and the advanced nodal code SPNOVA (Reference 2).
LOFT 5 uses a full-core model, consisting of 193 fuel assemblies with one node per assembly radially and 20 axial nodes. Several
" hot" rods are specified with different input multipliers on the hot rod powers to simulate the effect of plants with different initial FAH values. A " hot" rod represents the fuel rod with the highest FAH in the assembly, and is calculated by SPNOVA within LOFT 5. DNBRs are calculated for each hot rod within LOFT 5 with a simplified DNB-evaluation model using the WRB-1 correlation. The DNBRs resulting from the LOFT 5 calculations are used for comparison purposes.
A more detailed DNBR analysis is done at the limiting transient statepoints from LOFT 5 using THINC-IV (Reference 3) and the Revised Thermal Design Procedure (RTDP). RTDP applies to all .
Westinghouse plants, maximizes DNBR margins, is approved by the :
NRC, and is licensed for a number of Westinghouse plants. The LOFT 5-calculated DNBRs are conservatively low when compared to I the THINC-IV results.
Assumptions -!
The initial power levels chosen for the performance of bank and multiple RCCA withdrawal cases are 100%, 60%, 10% and hot zero power (HZP). These power levels are the same_ powers considered in the RCCA Bank Withdrawal at Power and Bank Withdrawal from Subcritical events presented in the plant Safety Analysis ,
Reports. The plant, in accordance with RTDP, is assumed to be '
operating at nominal conditions for each power level examined. i Therefore, uncertainties will not affect the results of the LOFT 5 )
I transient analyses. For the at-power cases, all reactor coolant pumps are assumed to be in operation. For the hot zero power case (subcritical event), only 2/4 reactor coolant pumps are assumed to be in operation. A " poor mixing" assumption is used for the reactor vessel inlet and outlet mixing model.
ATTACHMENT Response to NRC GL 93-04 Page 7 Results A review of the results presented in Reference 4 indicates that for the asymmetric rod withdrawal cases analyzed with the LOFT 5 code, the DNB design basis is met. As demonstrated by the A-Factor approach (described below) for addressing various combinations of asymmetric rod withdrawals, the single most-limiting case is plant-specific and is a function of rod insertion limits, rod control pattern, and core design. The results of the A-Factor approach also demonstrates that the cases.
analyzed with the LOFT 5 computer code are sufficiently conservative for a wide range of plant configurations for various asymmetric rod withdrawals. In addition, when the design FAH is taken into account on the representative plant, the DNBR criterion is met for the at-power cases. ,
At HZP, a worst-case scenario (3-rods withdrawn from three different banks which is not possible) shows a non-limiting .
DNBR. This result is applicable to all Westinghouse plants.
Plant Applicability The 3-D transient analysis approach uses a representative I standard 4-Loop Westinghouse plant with bounding reactivity assumptions with respect to the core design. This results in ,
conservative asymmetric rod (s) withdrawal statepoints for the various asymmetric rod withdrawals analyzed. The majority of.the ;
cases analyzed either did not generate a reactor trip or were 1 terminated by a High Neutron Flux reactor trip. For the ~
Overtemperature Delta-T reactor trip, no credit is assumed for the f(AI) penalty function. The f(AI) penalty function i reduces the OTDT setpoint for highly skewed positive or negative I axial power shapes. Compared to the plant-specific OTDT setpoints including credit for the f(AI) penalty function, '
the setpoint used in the LOFT 5 analyses is conservative; i.e., for those cases that tripped on OTDT, a plant-specific OTDT l setpoint with the f(AI) penalty function wil'1 result in an i earlier reactor trip than the' LOFT 5 setpoint. This ensures that i the statepoints generated for those cases that trip on OTDT are conservative for all Westinghouse plants.
With respect to the neutronic analyses, an adjustment factor ,
("A-factor") was calcu3ated for a wide range of plant types and >
rod control configurations. The A-factor is defined as the ratio between the design FAH and the change in the maximum ;
transient FAH from the symmetric and asymmetric RCCA withdrawal cases. An appropriate and conservative plant-specific A-factor was calculated and used to determine the corresponding DNBR penalty or benefit. With respect to the_ thermal-hydraulic analyses, differences in plant conditions (including power level, RCS temperature, pressure, and flow) are addressed by sensitivities performed using THINC-IV. These sensitivities are ;
used to_ determine additional DNBR penalties or benefits.
l l
' Response to NRC GL 93-04 Page 8 i
Uncertainties in the initial conditions are accounted for in the DNB design limit. Once the differences in plant design were '
accounted for- by the adjustment approach, plant-specific DNBR calculations can be generated for all Westinghouse plants. ,
i conclusion ,
Using this approach, the preliminary results of the generic analyses' and their plant-specific application demonstrate that for Beaver Valley Power Station Unit No. 1 and No. 2 DNB does not occur for >
their worst-case asymmetric rod withdrawal. ;
References
- 1) Burnett, T.W.T., et al., "LOFTRAN Code Description," WCAP-7907-A, j April 1984. l
- 2) Chao, Y.A., et al., "SPNOVA -
A Multi-Dimensional Static and i Trnasient Computer Program for PWR Core Analysis," WCAP-12394,- ,
September 1989. ;
- 3) Friedland, A. J. and S. Ray, " Improved THINC IV Modeling for PWR Core Design," WCAP-12330-P, August 1989, j
- 4) Huegel, D., et al., " Generic Assessment of Asymmetric Rod Cluster Control Assembly Withdrawal," WCAP-13803, August 1993. .
[
1 l
)
1 1
1 l
J
'l l
I
-,