a DFFICA1 RECORD COP
~
AUG 4 g43 p
Docket No. 50-416 License No. NPF-29 i
Entergy Operations, Inc.
ATTN:
C. R. Hutchinson, Vice President Operations - Grand Gulf J
Entergy Operations, Inc.
P. O. Box 756 Port Gibsoa, MS 39150 i
Gentlemen:
SUBJECT:
REVIEW 0F REVISIONS NOS. 23 AND 24 AND CHANGE NOS. 23-001-92, 23 9
002-93, AND 23-003-93 TO EMERGENCY PLAN FOR GRAND GULF Based on our review of the subject submittal, we have concluded that the changes therein meet the planning standards of 10 CFR 50.47(b) and the requirements of Appcndix E to 10 CFR Part 50.
Please be reminded that 10 CFR 50.54(q) requires that proposed._ changes which decrease the effectiveness of your Emergency Plan'shall not be implemented without application to and approval by the Commission. However, changes _may l
be made without Commission approval if such changes do not decrease the.
effectiveness of the Plan, and the Plan,.as changed, continues to meet the standards of 10 CFR 50.47(b) and the requirements'of Appendix E to 10 CFR t
Part 50.
If..a. change is made without approval, ycu should furnish copies in accordance with 10 CFR 50.54(q). Also, any changes to the Emergency Plan Implementing Procedures should be made in accordance with the requirements of Apoendix E to 10 CFR Part 50.
. Sincerely, 3
William E. Cline, Chief Radiological Protection and Emergency Preparedness. Branch Division of Radiation Safety and Safeguards o
cc:
(See page 2)
V.
9308130002 930B04 PDR ADDCK 05000416' F
PDR k
JE 9
t' 1
. Entergy Operations, Inc.
2 s
cc: Mr. H. W. Keiser, Executive Vice President and Chief Executive Officer Entergy Operations, Inc.
P. O. Box 31995 Jackson, MS 39286-1995 General Manager Grand Gulf Nuclear Station Entergy Operations, Inc.
P. O. Box 756 Port Gibson, MS 39150 M. J. Meisner, Director Nuclear Licensing Entergy Operations, Inc.
P. O. Box 756 Port Gibson, MS 39150 Mike Morre, Attorney General Frank Spencer, Asst. Attorney General State of Mississippi P. O. Box 22947 Jackson, MS 39225 J. P. McGaha Vice President, Operations Support Entergy Operations, Inc.
P. O. Box 31995 Jackson, MS 39286-1995 R. B. McGehee, Esq.
Wise, Carter, Child, Steen and Caraway P. O. Box 651 Jackson, MS 39205 N. S. Reynolds, Esq.
Winston & Strawn 1400 L Street, NW, 12th Floor Washington, D. C.
20005-3502 Alton B. Cobb, M.D.
State Health Officer State Board of Health P. O. Box 1700 Jackson, MS 39205 cc:
(Cont'd on page 3)
j 1
Entergy Operations, Inc.
3 (cc: cont'd) l The Honorable William J. Guste, Jr.
Attorney General Department _of Justice State of Louisiana P. O. Box 94005 Baton Rouge, LA 70804-9005 i
Office of the Governor State of Mississippi j
Jackson, MS 39201 Sam Mabry, Chief Hazardous Waste Division Mississippi Department of Environmental Quality P. O. Box 10385 Jackson, MS 39209 i
President l
Clairborne County Board i
of Supervisors l
Port Gibson, MS 39150 l
i K. G. Hess i
Vice President l
Bechtel Power Corporation P. O. Box 2166 Houston, TX 77252-2166 l
4 W. W. Watson l
Project Manager Becht Power Corporation P. O. Box 808 i
4600 W. Main i
Russellville, AR 72801 l
bcc: P. O'Connor, NRR H. Rood, NRR F. Cantrell, RII Document Control Desk NRC Resident Inspector U.S. Nuclear Regulatory Commission Route 2, Box 399 Port Gibson, MS 39150
.:DRSS Rld DRSS RII:
)"f
$4'2 u JKreh KBarr FC ntrell fB/4/93 8///93 8 /93
.