i in$r Point 1 Nucic at Pc,wct P: ant 3
d
- > NewYorkPower e&
& Authority
~
July 28, 1993 IPN-93-092 Docket No.
50-286 License No.
DPR-64 U.S. Nuclear Regulatory Commission ATTN:
Document Control Desk Mail Station F1-137 Washington, D.C.
20555
Subject:
Indian Point 3 Nuclear Power Plant Security Plan. Revision 14
References:
1.
NYPA Letter IPN-92-098, dated June 15, 1992 from R.
E.
Beedle to Document control Desk,
Subject:
Indian Point 3 Security Plan Temporary Addendum Report, Revision 3.
This letter and its attachment provide the latest revision of the Indian Point 3 (IP3) Security Plan in accordance with 10 CFR 50.54 (p).
By Reference 1, the Authority submitted temporary changes to the plan.
This revision incorporates these changes as permanent.
In addition, this revision incorporates changes which reflect the IP3 current security organization and references to the shared administrative security boundary between Indian Points 1 and 2, and Indian Point 3.
This revision does not decrease the plan's safeguards effectiveness.
A summary of the plan changes is provided as a separate attachment.
The attachment is identified as Safeguards and Proprietary Information covered under 10 CFR 73.21 and 10 CFR 2.790 (d (1).
The Authority requests that upon receipt of this correspondence, you inventory the contents and return the Document Receipt Form to the IP3 Security Manager, Mr. J. Fitzsimmons.
Should you have any questions concerning this submittal please contact Mr. J. Fitzsimmons, IP3 Security Manager, or Mr. J. Maurer, IP3 eneral Manager - Support Services.
f John H.
Garr' y Resident Manager Indian Point 3 Nuclear Power Plant JHG/dm Attachment 9307300181 930728 T
/
PDR ADOCK 05000286 E
/
, 1 s
F PDR
[~
f u,:u
t cc:
Mr. Richard R. Keimig Chief Safeguards Section Region I 1
475 Allendale Road King of Prussia, PA 19406 l
Mr. Thomas T. Martin Regional Administrator Region I 475 Allendale Road King of Prussia, PA 19406 Mr. Nicola F. Conicella, Project Manager i
Project Directorate 1-1 Division of Reactor Projects 1/11 U.S.
Nuclear Regulatory Commission Mail Stop 14B2 Washington, D.C.
20555 Mr. Francis J. Williams Jr.,
Proj. Manager Project Directorate I-1 Division of Reactor Projects 1/II U.S/ Nuclear Regulatory Commission Mail Stop 14B2 Washington, D.C.
20555 l
Resident Inspector's Office Indian Point Unit #3 i
U.S. Nuclear Regulatory Commission P.O. Box 377 i
Buchanan, NY 10511 I
i l
I a
l r
p-
,v-e
- - --