APPENDIX A NOTICE OF VIOLATION Boston Edison Company Docket No. 50-293 Pilgrim _ Nuclear Power Station License No. DPR-35 During an NRC inspection conducted en June 14-18,1993, a violation of NRC requirements was identified. In accordance with the " General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C, the violation is listed below:
The Pilgrim Nuclear Power Station Physical Security Plan, dated December 22,1992, ISSUE 2, Revision 11, Section 6.1, states, in part, that areas within the Protected Area, the perimeter and Isolation Zones are illuminated to a minimum of 0.2 foot-candles measured at ground level.
Additionally, Section 6.1. states, in part, that approved procedures are developed to provide direction for compensatory measures during periods oflighting loss, and for obtaining maintenance.cuppon to return the lighting system to normal operation.
In addition, Section 6.2, Revision 2, of Station Instruction SI-SC.1215, " Identification of Protected Area Lighting Imss," states, in part, that at least once every seven days, the OIC (Officer-In-Charge) will initiate a lighting survey of perimeter and Protected Area Lighting. The results will be documented on the Weekly Lighting Survey Map. Section 6.3, of Station Instruction SI-SC.1215, also states, in part, that on a bi-monthly basis, not to exceed 60 days, I&C technician (s) and the BSSS (Beco Security Shift Supervisor) shall conduct a lighting survey of the perimeter and Protected Area lighting. The survey will be performed by use of a calibrated light meter and all darkened areas of the Protected Area and Isolation Zone (s) will be selected and tested.
Contrary to the above, on June 15, 1993, the inspector determined that, while the OIC had performed a lighting survey at least once every seven days, it was performed with ~
a light meter that had never been calibrated since it was purchased by the security department in excess of two years ago. Additionally, one of the I&C department's light meters was sent for calibration in December 1992 and the other, on March 31,1993; neither had been returned by June 15,1993. Therefore, the required bi-monthly lighting survey could not have been conducted during the period, April 1 - June 15,1993, a period exceeding 60 days.
This is a Severity Leve! IV violation (Supplement III).
Pursuant to the provisions of 10 CFR 2.201, Boston Edison Company it hereby required to submit a written statement or explanation to the U.S. Nuclear Regulatory Commission, ATfN:
Document Control Desk, Washington, D.C. 20555 with a copy to the Regional. Administrator,
)
Region I, and a copy to the NRC Resident Inspector at the facility that is the subject of this Notice, within 30 days of the date of the letter transmitting this Notice of Violation (Notice).
i 9307270013 930716.._
Ql71CIAl.RECO N W PDR ADDCK 05000293 O
i f
Aplendix A 2
This reply should be clearly marked as a " Reply to a Notice of Violation" and should include for each violation: (1) the reason for the violation, or, if contested, the basis for disputing the violation, (2) the corrective steps that have been taken and the results achieved, (3) the corrective steps that will be taken to avoid further violations, and (4) the date when full compliance will be achieved. If an adequate reply is not received within the time specified in this Notice, an order or a Demand for Information may be issued to show cause why the license should not be modified, suspended, or revoked, or why such other action as may be proper should not be taken. V'here good cause is shown, consideration will be given to extending the response time.
l Dated at King of Prussia, Pennsylvania this M. day of July,1993
)
i J
OFFICIAL RECORD COPY 4
~