Notice of Violation from Insp on 930420-23.Violation Noted: Security Force Drill Conducted to Provide Training of Security Force in Reacting to Safeguard Contingencies & Drill Rules Not Followed
ML20045D811
Person / Time
Site: River Bend Entergy icon.png
Issue date: 06/25/1993
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20045D807 List:
References
50-458-93-14, EA-93-118, NUDOCS 9306300087
Download: ML20045D811 (2)


Text

__

O NOTICE OF VIOLATION Gulf States Utilities Docket No. 50-458 River Bend Station License No. NPF-47 EA 93-118 During an NRC inspection conducted April 20-23, 1993, a violation of NRC requirements was identified.

In accordance with the " General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C, the violation is listed:

Condition 2.D of River Bend Station Operating License NPF-47 requires the licensee to maintain in effect and fully implement all provisions of the Commission approved Physical Security Pian.

This includes amendments and changes made pursuant to the authority of 10 CFR 50.54(p).

The Introduction Section of the Physical Security Plan states that security procedures provide the detailed instructions necessary to implement the plan.

Paragraph 2.1 of the Training and Qualification Plan requires the licensee to conduct periodic exercises to maintain the effectiveness of the security force in contingency reponse tasks.

Procedure PSP-4-501, " Training Program (Security Force Drills)," as revised by Interim Procedure Change 4-501-3-2, dated October 29, 1992, states in Section 5.0, in part, that security force drills are conducted to provide training for the security force in reacting to safeguard contingencies.

Section 6.3 of this procedure, " Drill Rules," states, in part, that: 1) all communications relating to a drill, by whatever means, shall be preceded and followed by "This is a drill"; and 2) revolvers and shotguns in firing order shall not be drawn or carried during the drill.

Contrary to the above, on April 16, 1993, a security force drill was conducted to provide training of the security force in reacting to safeguard contingencies and the above drill rules were not followed.

Specifically,1) all communications relating to the drill were not preceded and followed by "This is a drill" (the term Code Blue was used instead); and 2) revolvers that were in firing order were carried and drawn by drill participants.

This is a repetitive Severity Level IV violation (Supplement Ill).

Pursuant to the provisions of 10 CFR 2.201, Gulf States Utilities is hereby required to submit a written statement or explanation to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, D.C. 20555, with a copy to the Regional Administrator, Region IV, 611 Ryan Plaza Drive, Suite 400, Arlington, Texas 76011, and a copy to the NRC Resident Inspector at the River Bend Station facility, within 30 days of the date of the letter transmitting this Notice of Violation (Notice).

This reply should be clearly marked as a " Reply to a Notice of Violation" and should include for each violation:

(1) the reason for the violation, or, if contested, the basis for disputing the violation, (2) the corrective steps that have been taken and the results achieved, (3) the corrective steps that will be taken to avoid further 9306300087 930625 PDR ADOCK 05000459 G

PDR

Notice of Violation :

violations, and (4) the date when full compliance will be achieved.

If an adequate reply is not received within the time specified in this Notice,'an order or a demand for information may be issued to show cause why the license should not be modified, suspended, or revoked, or why such other action as may be proper should not be taken. -Consideration may be given to extending the response time for good cause shown.

Under the authority of Section 182 of the Act, 42 U.S.C. 2232, this response shall be submitted under oath or affirmation.

Dated at Arlington, Texas, this 25th day of June 1993 i

JLN 251993 l

Gulf States Utilities '

bcc w/

Enclosure:

HQ DISTRIBUTION:

PDR l

LPDR SECY CA JSniezek, DEDR TMurley, NRR JPartlow, NRR/ADP JLieberman, OE (4)(I-single sided)

LChandler, OGC JGoldberg, OGC Enforcement Officers RI, RII, RIII, RV FIngram, PA DWilliams, OIG EJordan, AEOD

,BHayes, 0I

{

iDCS RIV DISTRIBUTION:

GMilhoan JMontgomery LJCallan>DChamberlain BMurray>BEarnest i

ABBeach*TPGwynn WSmith SCollins>AHowell JGilliland CHackney WBrown GSanborn*RWise>EAFile LWilliamson RIV Files MIS Coordinator j

~

OE R1 D

an orn LJC lan \\ ^ JLieberman J1113 hoan 6/25/93 6{/93

\\ 6/24/93 4,,6/13 /93 b'. \\T-i 290016