WASHINGTON, D. C. 20555 g....+/
June 23, 1993 Docket No. 50-333 Mr. Ralph E. Beedle Executive Vice President, Nuclear Generation Power Authority of the State of New York 123 Main Street White Plains, New York 10601
Dear Mr. Beedle:
SUBJECT:
JAMES A. FITZPATRICK NUCLEAR POWER PLANT - RESPONSE TO NRC BULLETIN 93-02, " DEBRIS PLUGGING 0F EMERGENCY CORE COOLING SUCTION STRAINERS" (TAC NO. M86563)
This letter acknowledges receipt of The Power Authority of the State of New York's (PASNY's) response dated June 10, 1993, to NRC Bulletin 93-02 (Bulletin). The Bulletin was issued May 11, 1993, to all nuclear power reactor licensees.
It requested licensees to identify fibrous material in the primary containment, take any necessary compensatory measures, and remove any such material.
PASNY's response stated that no fibrous filter material or other temporary sources of fibrous material, such as described in the Bulletin, were identified as being used or stored in the containment during normal operation.
PASNY also stated that controls are in place to ensure that any such material that is temporarily used in the containment during outages is removed prior to plant startup.
Based on that, we consider your actions to be complete.
Please retain any records of your actions in response to this Bulletin, as subsequent inspection activities may be conducted in regards to this issue.
Should you have any questions, please contact me at (301) 504-1406 or the Lead Project Manager for this issue, John B. Hickman at (301) 504-3017.
Sincerely, bQ John E. Menning, Acting Project Manager Project Directorate I-l Division of Reactor Projects - I/II Office of Nuclear Reactor: Regulation cc:
See next page 10\\
-Q
.ano m
~
' ' " N 9306280306 930623 J
m-k PDR ADOCK 05000333
'<e r
~ '
O PDR
.e.
i i
Mr. ' Ralph E. Beedle James A. FitzPatrick Nuclear Power Authority of the State of New York Power Plant-cc:
l r
Mr. Gerald C. Goldstein Regional Administrator, Regio'n I:
S Assistant General Counsel U.S. Nuclear, Regulatory Commission' Power Authority of the State 475 Allendale Road
-+
of New York King of Prussia, Pennsylvania 19406
'I 1633 Broadway New York, New York 10019 -
Ms. Donna Ross.
t New York State. Energy Office Resident Inspector's 0ffice 2 Empire. State Plaza U. S. Nuclear Regulatory Commission 16th Floor s
-Post Office Box 136 Albany, New-York 12223 Lycoming, New York 13093 j
Mr. Harry P. Salmon, Jr.
Resident Manager James A. FitzPatrick Nuclear Power Plant Post Office Box 41 Lycoming, New York 13093 i
Mr. J. A. Gray, Jr.
Director Nuclear Licensing - BWR Power Authority of the State of New York 123 Main Street White Plain's, New York 10601 a
Supervisor Town of Scriba Route 8, Box 382 Oswego, New York 13126 Mr. Robert G. Schoenberger,
- Acting President-Power Authority of the State-of New York 123 Main Street.
White Plains, New York-10601
. Charles Donaldson, Esquire o
Assistant Attorney General-1
.New York Department of. Law-120 Broadway
'i New York, New York 10271-i i
l
,_~,-___r
___-,_2_u__
4 June 23, 1993 Docket No. 50-333 Distribution:
Mr. Ralph E. Beedle
' Docket File CVogan Executive Vice President, Nuclear NRC & Local PDRs JMenning Generation PDI-1 Reading OGC Power Authority of the State of SVarga ACRS (10)
New York JCalvo CCowgill, RI 123 Main Street RACapra JHickman, 13D1 White Plains, New York 10601 RBarrett, 8H7
Dear Mr. Beedle:
SUBJECT:
JAMES A. FITZPATRICK NUCLEAR POWER PLANT - RESPONSE TO NRC BULLETIN 93-02, " DEBRIS PLUGGING OF EMERGENCY CORE COOLING SUCTION STRAINERS" (TAC N0. M86563)
This letter acknowledges receipt of The Power Authority of the State of New York's (PASNY's) response dated June 10, 1993, to NRC Bulletin 93-02 (Bulletin).
The Bulletin was issued May 11, 1993, to all nuclear power reactor licensees.
It requested licensees to identify fibrous material in the primary containment, take any necessary compensatory measures, and remove any such material.
PASNY's response stated that no fibrous filter material or other temporary sources of fibrous material, such as described in the Bulletin, were identified as being used or stored in the containment during normal operation.
PASNY also stated that controls are in place to ensure that any such material that is temporarily used in the containment during outages is removed prior to plant startup.
Based on that, we consider your actions to be complete.
Please retain any records of your actions in response to this Bulletin, as subsequent inspection activities may be conducted in regards to this issue.
Should you have any questions, please contact me at-(301) 504-1406 or the Lead Project Manager for this issue, John B. Hickman at (301) 504-3017.
Sincerely, Original Signed By:
John E.'Menning, Acting Project Manager Project Directorate I-l Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation cc: See next page LA:PDI PM:PDI-l D:PDI-l CVogan cd JMenning:hm RACapra M G /23/93
(,/ u/93 6 /23/93
/ /.
/ /
/ /