Text
-- ! ;
0
-hfhb a l' Mt te/H95 CERTIFIED By:
Paul Shewmon, Chairman Date:
1/12/93 Summary of Minutes ACRS Planning & Procedures Subcommittee Meeting January 6, 1993 Attendees ACES P. G.
Shewmon, Chairman J. E. Wilkins J. C.
Carroll R.
F.
Fraley Etaf.f.
J. T.
Larkins, Acting Executive Director R.
P. Savic S. Duraiswamy M.
F.
Lee M. MacWilliams Others Helen Pastis, NRR (Part time) e Egrnose To discuss aspects of ACRS activities related to:
1.
Status of appointment of new members 2.
DELETION - FOIA EX(b) (6) 3.
Status of actions related to R.
Fraley's retirement 4.
ACRS/ACNW Budget 5.
Future Committee Activities i
50\\
9306250329 930122 DESIGNATED ORIGINAL -
0\\
- er*,ified By.
i 7 3,
es 2
e Discussion / Conclusions i
1.
Status of Members Appgintments DELETION FOIA EX(b) (6)
INFORMATION t'
We expect that his appointment will be completed by the 394th ACRS meeting (February 11-13, 1993).
i DELETION FOIA EX(b) (6) 2.
INFORMATION
-l i
.+.
'?'.
3 DELETION - FOIA EX (b) (6) 3.
Status of Actions Related to R.
Fraley's Retirement DELETION FOIA EX(b) (6)
INFORMATION 4.
ACRS/ACNW Budaet The ACRS Program Support / Travel Budget has an additional
$135,000 available over the estimate last month,- due to correction of a mathematical error in the spreadsheet used for this calculation.
This should relieve any concern about travel,. expenditures, etc.
Members af firmed that the work on scaling methodology proposed -
l by Dr. Wolfgang Wulff (27 day effort costing ($46,250.00) is l
3
~.
d e
4 better left to Westinghouse or the staff rather than having ACRS fund this work.
It was agreed that the ACRS staff should contact the'GPR (Mr.
Candelli) to obtain a status report regarding the status of the multilateral meeting of advisory bodies.
5.
Future ACRS Activities i
The list of topics proposed for consideration by.the full Committee was discussed.
A revised version will be provided for consideration by the full Committee.
It was noted that the December 24, 1992 SRM resulting from the.
December 11, 1992 ACRS meeting with ' the NRC Commissioners) requests the ACRS to consider how the Maintenance Rule might be used as a means to address the activities required of licensees by the License Renewal Rule.
J.
Carroll noted that several additional requests by individual Commissioners were also made (see Attachment A, pp.
1-66) and should be considered by the ACRS subject to the availability of time and resources.
l ATTACHMENT
- l
a i
5 l
A List of additional requests by individual Commissioners
~
during ACRS Meeting with Commissioners on December 11, 1992, with transcript Y
1
ADDITIONALREQUESiSBYCOMMISSIONERS Transcript of Commission Meeting of 12/11/92 P.12, Line 25 to P.17, Line 3 - Rogers-Reliability values used in ABWR PRA i
P.17, Line 8 to P. 20, Line 17 - Rogers-Debris coolability P. 21, Line 8 to P. 24, Line 1 - Rogers-Multiple SGTRs P. 24, Line 8 to P. 25, Line 18 - Remick-Control room prototype P. 25, Line 21 to P. 27, Line 11 - Remick-Safety and non safety equipment s
P. 27, Line 12 to P. 30, Line 10 - Remick-Various kinds of ITTACs; COL P. 43, Line 6 to P. 44, Line 2 - Selin-Keep working with the staff on digital I&C (Carroll-C&B on Lewis)
P. 53, Lines 14 to 23 - Curtiss-Suggested that the Committee invite Vesley and Loftgren to make a presentation on their RBR work P. 54, Lines 6 to 11 - Selin-ACRS "should focus on the management process and instilling PRA..."
P. 57, Lines 24 to p. 60, Line 23 - Curtiss-Maintenance, license extension and RAPS ATTACHMENT A
/.
- - -