10 CFR 50.90 PHILADELPHIA ELECTRIC COMPANY NUCLEAR GROUP HEADQUARTERS 955-65 CHESTERBROOK BLVD.
WAYNE, PA 19087-5691 c is) w o u co June 7, 1993 Docket Nos.
50-277 50-278 STADON SUPPORT DEPARTMENT License Nos. DPR-44 DPR-56 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555
SUBJECT:
Peach Bottom Atomic Power Station, Units 2 and 3 Technical Specifications Change Request (TSCR 92-03)
Supplement 2
REFERENCE:
Letter dated 9/28/92 from G. J. Beck (PECo) to NRC, TSCR 92-03, Changes to Accommodate a 24-Month' Fuel Cycle
Dear Sir:
Ihe referenced letter s Gmitted Philadelphia Electric Company's (PECo)
Technical Specification Change Request (TSCR) 92-03 in accordance with 10 CFR 50.90 requesting a change to Appendix A of the Peach Bottom Facility Operating Licenses. This letter submits a revision to that TSCR. This revision is necessary to correct an oversight in the original submittal, and has' been discussed with the NRC Project Manager for Peach Bottom Atomic Power Station.
Enclosed is the revised Technical Specification (TS) page 188 for both units. The revised TS pages change the notes for TS Table 3.7.2 through 3.7.4.
The requested change is to replace the wording in Note 5 from: " Local leak tests on all testable isolation valves shall be performed each operating cycle but in no case at intervals greater than 2 years" to " Local leak tests on all testable isolation valves shall be performed per 10CFR50 Appendix J requirements." Note 6 will be changed from: " Local leak tests on all testable penetrations shall be-performed each operating cycle but in no case at intervals greater than 2 years" to " Local leak tests on all testable penetrations shall be performed per 10CFR50 Appendix J requirements."
This change is the same as the proposed change to TS page 169, which was identified as an administrative change and assessed for its safety significance
~
in the above referenced letter; therefore, this change may also be considered an administrative change.
Inclusion of this change does not affect the information supporting a finding of no significant h?zards consideration.
d 1 ALLD41 iI l-9306150357 930607 sp ADOCK 0500 7 ${.;
,PDR
U.S. Nuclear Regulatory Commission June 7, 1993
- Document Control Desk Page 2 0
c If you have any questions regarding this matter, please contact us.
Very truly yours,
. d.
4 G. A. Hunger, b+irector Licensing Section
Enclosures:
Affidavit Corrected proposed TS pages 188 cc:
T. T. Martin, Administrator, Region I, USNRC J. J. Lyash, USNRC Senior Resident Inspector, PBAPS W. P. Dornsife, Commonwealth of Pennsylvania t
t
i s
i COMMONWEALTH OF PENNSYLVANIA :
1 ss.
COUNTY OF CHESTER G. R. Rainey, being first' duly sworn, deposes and says:
That he is Vice President of Philadelphia Electric Company; the Applicant herein; that he has read Technical Specifications Change Request Supplement 2 (Number 92-03) and the Request for Additional Information~for Peach Bottom
[
Facility Operating Licenses DPR-44 and DPR-56, and knows the contents thereof; j
and that the statements and matters set forth therein are true and correct to i
the best of his knowledge, information and belief.
4 3
f}!h p i
Vice President
{
1 I
l Subscribed and sworn to beforemethisr/YG r
day of "C 1993.
) ')
i b >s M j g-q Ncrtary Public runsseat Eta A Santort NotaryPJic Tredytt.inTwg.Crester County MyCommmon ExpresJJy10.1tG5
.