Forwards Safety Insp 50-333/93-08 on 930315-19 & 0329-0402. No Violations Noted.Program for Controlling Design Changes & Plant Mods Found to Be Effective
ML20044H274
Person / Time
Site: FitzPatrick 
Issue date: 06/04/1993
From: Durr J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Harry Salmon
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
Shared Package
ML20044H275 List:
References
NUDOCS 9306080130
Download: ML20044H274 (3)


See also: IR 05000333/1993008

Text

.

.-

t

yn

,

JUN 041993

"

,

Docket No.

50-333

Mr. Harry P. Salmon, Jr.

Resident Manager

New York Power Authority

James A. FitzPatrick Nuclear Power Plant

Post Office Box 41

Lycoming, New York 13093

Dear Mr. Salmon:

SUBJECT:

ENGINEERING INSPECTION AT THE JAMES A. FITZPATRICK

NUCLEAR POWER PLANT NRC INSPECTION REPORT NO.

50-333/93-08)

This letter refers to the announced safety inspection of your design change and modification

program conducted by Messrs. L. Prividy and P. Drysdale from March 15,1993 to April 2,

1993 at the James A. FitzPatrick Nuclear Power Plant, Scriba, New York. The results of

this inspection were discussed with you and your staff at the conclusion of the inspection.

'

Areas examined during this inspection are discussed in the enclosed inspection report. The

inspection consisted of selective examinations of plant design changes, physical walkdowns of

modifications, discussions with your personnel responsible for implementing modifications

and observations by our inspectors. The control of plant design changes is important to

'

safety to assure that such changes do not degrade safety systems, structures and components.

.

i

The program for controlling design changes and plant modifications was found to be

effective. Your development of a systematic modification prioitization process was a

notable improvement. Notwithstanding your work accomplishments during the shutdown in

1992, your staff recognized the need for additional progress to reduce the engineering work

backlog consistent with the NYPA Nuclear Generation Business Plan goals.

I

t

F

f

-i

!

!

f

L

9306080130 930604

{/

PDR

ADOCK 05000333

'

PDR

g

O

w

  • .

JUN 041993

,

Mr. Harry P. Salmon, Jr.

2

No response to this letter is required, and your cooperation with us in this matter is

appreciated.

Sincerely,

~

i

Jacque P. Durr, Chief

.

Engineering Branch

I

Division of Reactor Safety

Enclosure: Inspection Report No. 50-333/93-08

l

cc w/ encl:

J. Brons, President

R. Beedle, Executive Vice President - Nuclear

G. Goldstein, Assistant General Counsel

J. Gray, Jr., Director, Nuclear Licensing - BWR

Supervisor, Town of Scriba

,

C. Donaldson, Esquire, Assistant Attomey General, New York Department ofI2w

Director, Energy & Water Division, Department of Public Service, State of New York

K. Abraham, PAO (2)

Public Document Room (PDR)

Local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

NRC Resident Inspector

State of New York, SLO Designee

i

bec w/ encl:

Region I Docket Room (with concurrences)

-!

bec: (VIA E-MAIL)

V. McCree, OEDO

j

R. Capra, NRR

B. McCabe, NRR

OFFICIAL RECORD COPY A:FITZ9308. INS

f)

.

.

JUN 041993

.

Mr. Harry P. Salmon, Jr.

3

bec w/ Letter, Report Cover Sheet

C. Hehl, DRP

J. Wiggins, DRP

M. Hodges, DRS

W. Lanning, DRS

L. Bettenhausen, DRS

J. Durr, DRS

R. Cooper, DRSS

J. Joyner, DRSS

RI:DRS

RI:DRS

RI:DRS

f

5/lI/93

5/19'93

64/93

OFFICIAL RECORD COPY A:FITZ9308. INS

,