EN-93-054:on 930528,notice of Proposed Imposition of Civil Penalty in Amount of $325,000 Issued to Licensee.Action Based on Violation Involving Inoperability of Unit 1 AFW Pump for Approx 33 Days
ML20044G673
Person / Time
Site: South Texas STP Nuclear Operating Company icon.png
Issue date: 05/28/1993
From: Lieberman J, Troskoski W
NRC OFFICE OF ENFORCEMENT (OE)
To:
References
EA-93-057, EA-93-57, EN-93-054, EN-93-54, NUDOCS 9306040080
Download: ML20044G673 (2)


Text

.

J

~

May 28, 1993 EN 93-054 OFFICE OF ENFORCEMENT NOTIFICATION OF SIGNIFICANT ENFORCEMENT ACTION Licensee:

Houston Lighting & Power Company (EA 93-057)

(South Texas Project Units 1 & 2)

Docket Nos. 50-498 and 499 Subiect:

PROPOSED IMPOSITION OF CIVIL PENALTIES - $ 325,000 This is to inform the commission that a Notice of Violation and Proposed Imposition of Civil Penalties in the cumulative amount of $325,000 will be issued today, May 28, 1993, to the Houston Lighting & Power Company.

This action is based on two Severity Level III problems, each involving multiple violations.

This action was submitted to the Commission in SECY-93-146 and today the Commission indicated that it had no objection to the issuance of the action.

In the first, the most significant violation involved the inoperability of the Unit 1 turbine-driven auxiliary feedwater pump for approximately 33 day.

In the second, the most significant violation involved the inoperablity of one of the Unit 1 emergency diesel generators for a period of approximately 24 days.

A civil penalty of $175,000 is being proposed for the first problem after finding escalation was appropriate for NRC identification, multiple opportunties to identify, and duration.

A civil penalty of $150,000 is being proposed for the second problem after finding escalation appropriate for prior opportunties to identify and duration.

It should be noted that the licensee has not been specifically informed of the enforcement action.

The schedule of issuance and notification is:

Mailing of Notice May 28, 1993 Telephone Notification of Licensee May 28, 1993 The State of Texas will be notified.

The licensee has thirty days from the date of the Notice in which to respond.

Following NRC evaluation of the response, the civil penalty may be remitted, mitigated, or imposed by Order.

Contact:

W. Troskoski, OE, 504-3281 J.

Lieberman, OE, 504-2741-9306040080 930528 h,\\

PDR I&E EN-93-054 PDR

\\

/6= ' 33

a EN 93-054 Distribution:

OWFN J / bc OWFN.2: b MNBB 3',So PHIL<2: 2r3 NL M ' &c Chairman Selin EDO OC IRM Comm. Rogers DEDR AEOD Comm. Curtiss DEDS Op Ctr Comm. Remick OE Comm. de Planque NMSS SECY NRR OCA OI OSP OGC GPA Regional Offices MAIL RI 4'b RIV 2-%

ADM: Doc. Mgt. Br.

RII,a h

RV 2 3r PDR ACRS RIII2 2, c RES OIG PRELIMINARY INFORMATION - NOT FOR PUBLIC DISCLOSURE UNTIL PUBLICLY ANNOUNCED