Forwards Zion Generating Station Unit 2,Cycle 13 Startup Test Rept. Details of Replacement Fuel Design Described in NRC SE for Amend 128 to License DPR-48 & Related Util Submittals
ML20044F963
Person / Time
Site: Zion File:ZionSolutions icon.png
Issue date: 05/18/1993
From: Stimac S
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20044F964 List:
References
NUDOCS 9306010263
Download: ML20044F963 (1)


Text

y y

'- 1

'N Cimmrnw;cith Edis:n O

1400 Opus Place

[

  • ~

CJ Downers Grove, illinois 60515 l

\\s/$E;-

i May 18, 1993 t

U.S.

Nuclear Regulatory Commission Washington, D.C.

20555 i

Attention:

Document Control Desk

Subject:

Zion Station Unit 2 Cycle 13 Startup Report NRC Docket No. 50-304

Reference:

June 26, 1992 letter from C.P.

Patel to T.J. Kovach Pursuant to Facility Operating License No. DPR-48, Appendix A,

Technical Specification 6.6.1 and 10 CFR 50.4, Commonwealth Edison Company (CECO) is transmitting the attached " Zion Generating Station Unit 2 Cycle 13 Start..p Test Report."

Submittal of this report fulfills the requirement of Technical Specification 6.6.1. A. (3 ) to submit a summary report of plant startup and power eocalation testing following installation of fuel that has a different design.

Details of the replacement fuel aesign are described in the referenced ~NRC Safety Evaluation for Amendment No. 128 to DPR-48 and in the~related CECO submittals.

1 Please direct any questions you may have to this office.

Sincerely,

/l.

i Stephen F.

Stimac Nuclear Licensing Administrator l

Attachment cc:

A.

Bert Davis, Regional-Administrator - RIII C.Y.

Shiraki, Project Manager - NRR J.D.

Smith, Senior Resident Inspector - Zion s

g:ssmay:1.

270091 Ah'}i

/<

F 9306010263 930518 PDR ADOCK 05000304

[

P' PDR it.

'