Text
e-pa arco
- ~
6 '
- 4 UNITED STATES
[
j NUCLEAR REGULATORY COMMISSION 2
WASHINGTON D.C. 20555-0001 S
May 17,1993 Docket Nos. 50-321 and 50-366 Mr. W. G. Hairstun, III Senior Vice President -
Nuclear Operations Georgia Power Company P. O. Box 1295 Birmingham, Alabama 35201
Dear Mr. Hairstor:
SUBJECT:
EDWIN 1. HATCH NUCLEAR PLANT, UNITS 1 AND 2 - RESPONSE TO GENERIC LETTER 92-00, " THERM 0-LAG 330-1 FIRE BARRIERS,"
TAC NOS. M85557 AND M85558 Sy letter dated April 16, 1993, you provided a response to Generic Letter (GL) 92-08 for Plant Hatch. Your response states that the Thermo-Lag fire barriers-installed at Plant Hatch were qualified by the vendor based on NRC guidance in existence at the time of the qualification.
The Architect Engineer (AE) for Plant Hatch reviewed and approved the Thermo-Lag qualification demonstration prior to installation of the Thermo-Lag barriers. Your response also states that installed configurations which deviated from tested configurations were evaluated by the AE at the time of installation.
Although Thermo-Lag barriers were evaluated and may have been considered qualified, the results of recent tests and inspections indicate that further actions are now necessary to address fire endurance and ampacity deratirg of Thermo-Lag barriers.
Your resoonse states that appropriate actions to resolve these concerns are being develor N
,<1h an industry program coordinated by NUMARC and you would apply the r.
4 the industry program, when completed, to the Thermo-Lag 330-1.nstallations at Plant Hatch. Compensatory measures for an inoperable barrier are in place and will remain in~ place until the fire barriers can be declared operable.
Your response to GL 92-08, however, did not provide a schedule by which corrective actions would be completed.
In your response to GL 92-08 you indicated that the actions necessary to restore (or confirm) the operability of these barriers will be based on the results of the NUMARC program. The staff expects that licensees referencing this program, will review the testing results and, within 30 days after the completion of this test program, inform the NRC of the actions necessary and the schedule for restoring the operability of thesc ' ire barriers.
For those plant specific or unique configurations that i.re.w dound by the NUMARC program, please provide within 30 days from the receipt of this letter, your schedules for site specific fire endurance testing of these unique u m a W "5 (M W s ad N]
l R C%'
.orCR Mic M; 9305270271 930517 PDR ADOCK 05000321 1
p F
Mr. W. G. Hairston May D, N confiaurations and the implementation of any potential barrier upgrades resulting from this testing.
In accordance with the reporting requirements of GL 92-08, you are also requested to confirm in writing, completion of the corrective actions.
The information requested by this letter is within the scope of the overall burden estimate in GL 92-08, which was an average of 300 person-hours for each addressee's response. This request is covered by Office of Management and Budget Clearance Number 3150-0011, which expires June 30, 1994.
Sincerely,
/s/
Kahtan N. Jabbour, Project Manager Project Directorate 11-3 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation cc:
See next page DISTRIBUTION Docket File NRC/ Local PDRs PDII-S.R/F S. Varga G. Lainas D. Matthews K. Jabbour L. Berry OGC 4
C. McCracken, SELB C. Berlinger, EELB ACRS (10)
E. Merschoff, RII A. Masciantonio, PDIII-I OSEE PREVIOUS CONCURRENCE J[
tfomf!Ikf3 Mr, J, _
PDII-3kh PDII-3/PM PDIII-1/PM*
BC.:SPtS/7 BC:EELB*
P[IN3/D //l OTFIE L.BERkY K.JABBOUR A.MASCIANTONI'0 CMkRNCKEN C.BERLINGER D.MATTHEWS
[/d/93 f//7/93 05/04/93
[//7/93 05/05/93
$//l/93 DME 0FFICIAL RECORD COPY I
FILE NAME:G:\\ HATCH \\GL9208.LTR I
i
~
.e '
Mr. W. G. Hairston May 17, 1993 configurations and the implementation of any potential barrier upgrades resulting from this testing.
In accordance with the reporting requirements of GL 92-08, you are also requested to confirm in writing, completion of the corrective actions.
The information requested by this letter is within the scope of the overall burden estimate in GL 92-08, which was an average of 300 person-hours for each addressee's response. This request is covered by Office of Management and Budget Clearance Number 3150-0011, which expires June 30, 1994.
Sincerely,
&l= bl.
W Kahtan N. Jabbour, Project Manager
+
Project Directorate II-3 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation n;;'
cc: See next page 4
s
l j
i Mr. W. G. Hairston, III-Georgia Power Company Edwin I. Hatch Nuclear Plant cc:
Mr. Ernest L. Blake, Jr.'
Mr. R. P. Mcdonald i
Shaw, Pittman, Potts and Trowbridge Executive Vice President -
i 2300 N Street, NW.
Nuclear Operations 1
Washington, DC 20037 Georgia Power Company P.'0. Box 1295 Mr. J. T. Beckham Birmingham, Alabama 35201
.l Vice President - Plant Hatch 4
Georgia Power Company W. Alan R. Herdt, Chief
+
P. O. Box 1295 Project. Branch #3 Birmingham, Alabama 35201 U. S. Nuclear Regulatory Comission i
101 Marietta Street, NW, Suite 2900 Mr. S. J. Bethay Atlanta, Georgia =30323--
Manager Licensing - Hatch i
Georgia Power Company Mr. Dan H. Smith, Vice President.
- q P. O. Box 1295 Pcwer Supply Operations J
d Birmingham, Alabama 35201 Oglethorpe Power Corporation-ln 2100 East Exchange Place
-E Mr. L. Sumner Tucker,: Georgia 30085-1349 i
General Manager, Nuclear Plant Georgia Power Company
. Charles A.- Patrizia, Esquire Route 1, Box 439 Paul, Hastings Janofsky & Walker Baxley, Georgia 31513 12th Floor 1
1050 Connecticut Avenue, NW.
Resident Inspector Washington, DC 20036 U. S. Nuclear Regulatory Comission Route 1, Box 725 l
Baxley, Georgia 31513 Regional Administrator, Region II U. S. Nuclear Regulatory Comission 101 Marietta Street, NW. Suite 2900 i
Atlanta, Georgia 30323 Mr. Charles H. Badger Office of Planning and Budget Room 610 270 Washington Street, SW.
Atlanta, Georgia 30334 i
Harc1d Reheis, Director Department of Natural Resources 205 Butler Street, SE., Suite 1252 Atlanta, Georgia 30334 i
Chairman Appling County Comissioners County Courthouse Baxley, Georgia 31513 l
-l
.-