Ltr Contract,Confirming Verbal Authorization to Commence Work Under Task Order 1 to Technical Assistance for NRC Dam Safety Program Implementation
ML20044B644
Person / Time
Issue date: 10/20/1992
From: Michael Scott
NRC OFFICE OF ADMINISTRATION (ADM)
To: Shank C
FEDERAL ENERGY REGULATORY COMMISSION
References
CON-FIN-L-2291-2, CON-NRC-02-92-001, CON-NRC-2-92-1 NUDOCS 9303010040
Download: ML20044B644 (5)


Text

2 f-fcg Vo UNITED STATES 3-I,, E NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555

\\...../

m, 001 2 9 1992 Federal Energy Regulatory Commission ATTN:

Mr. Charles Shank, Contracting Officer ;

810 First Street, N.E., Room 600 Washington, D.C.

20426

Dear Mr. Shank:

Subject:

Task 1 under Interagency Agreement No. NRC-02-92-001 Entitled

" Technical Assistance for NRC Dam Safety Program Implementation" The purpose of this letter is to confirm verbal authorization provided to you on October 14, 1992, by John Eastman, of my staff, to commence work under the subject task order effective October 16, 1992 with a temporary ceiling of $25,000.00.

In accordance with Article II, Task Order Procedures, of the Interagency 4

Agreement, this letter definitizes Task No.1.

This effort shall be performed in accordance with the enclosed Statement of Work.

The period of Performance for Task No. 1 is October 16, 1992 to March 3, 1993. The cost ceiling is $34,890.00.

Funds for this task order were obligated under the Interagency agreement.

The following individuals are considered by the Government to be essential to the successful performance of the work hereunder:

Primary: Mr. Ronald Corso Alteranate:

Mr. Constantine Tjoumas The issuance of this task does not amend any other terms or conditions of l

Agreement.

l l

I

)

9303010040 921020 PDR CONTR i

NRC-02-92-Oog pyg

I_

.. i

..c=

/

l Interagency Agreement No. 02-92-001 Task Order No. 1 Page 2 of 2 Your contacts during the course of this task order are:

Technical Matters:

Mr. John T. Greeves, (301) 504-3334 Mr. Robert E. Shewmaker, (301) 504-2596 Contractural Matters:

John Eastman, Contract Administrator (301) 492-7139 Please indicate your acceptance of this task by having an official, authorized to bind your organization, execute three copies of this document in the space provided and return two copies to the Contract Administrator.'

You should retain the third copy for your records.

Sincerely, l%

<b u

Mary Lynn Scott, Contracting Officer Contract Administration Branch No. 1 Division of Contracts ~and.

Property Management Office of Administration

Enclosure:

g, Mgd J.

As Stated ACCEPTED:

tWtr'

~

AM'N (Inu17:/?dYlh6 (fYI' TITLE

/B90-FL DATE:

y T

FIN L2291-2 9/25/92 TASK ORDER #2 PERFORM DAM SAFETY INSPECTION AT THE LUCKY MCGAS HILLS URANIUM MILL DAM #4 Fremont County, Wyoming i

1.0 BACKGROUND

The NRC Dam Safety Program Plan defined in SECY-91-193, dated June 25, 1991, and noted as approved in a memorandum from SECY to-the EDO, dated July 30, 1991, outlined the use of personnel from the Federal Energy Regulatory Commission (FERC) to provide technical and field support-for the program. This technical assistance was to be obtained through a Memorandum of Agreement and an Interagency Agreement. The Memorandum of Agreement was finalized on June 1, 1992 and the Interagency Agreement was signed and finalized on September 2, 1992. Work under this Task Order is to be performed under the guidance of these two base documents.

2.0 WORK REQUIRED FERC personnel will perform an operation inspection at the facility that will focus on the operation and maintenance aspects of the facility. The inspection will focus on the conformance of the facility with respect to the Federal Guidelines for Dam Safety (FGDS), June 1979, the various NRC guidance documents relevant to dam safety and other documents incorporated into the-lHIC Dam Safety Program-.-These documents have been identified in the Memorandum of Agreement between FERC and NRC. FERC~will provide the results of the inspection.in an operation inspection i

report to NRC. This report is the technical letter report provided for in the Interagency Agreement, t

3.0 REPORTING REQUIREMENTS i

i 3;1 Quarterly Letter Status Reports This task shall be summarized in the Quarterly Letter Status.

Report, along with any other active task orders that are to be submitted by FERC to NRC, under the provisions of the Interagency Agreement. The entry for the task'shall be by the assigned Tash Order Number.

3.2 Technical Letter-Reports

-FERC shall prepare a draft and final technical letter report in ace'ordance with the provisions of the Interagency Agreement

~

i_,

0,-

~-

' '.$,.~

I I

s i

t which reports the results of the operation inspection performed on the facility.

identified in the FERC Operating Manual for InspectioThe report Reports chall be addressed to the NRC Dam Safety O n of John T. Greeves, U.

, Mr.

D.C. 20555. Five (5) S. Nuclear Regulatory Commission, copies of the report are to be submitted. Washington, 4.0 SCHEDULE This Task Order is targeted for completion by December 31 however circumstances such as other FERC commitments a

1992, weather may result in schedule elippage.

5.0 MEETINGS AND TRAVEL The major inspection effort for the Task Order is contemplated for assignment since this Task representsto the Portland Regional Office of FERC, however is anticipated that effort will possibly be expended bythe first field ins It is expected that the inspection will be completed durin a FERC single field visit by these personnel. One meeting is anticipated that would be held at an NRC office, either in the Denver area or in the Washington, D.C. area after completion of the report.

6.0 NRC FURNISHED MATERIALS NRC will provide FERC with all relevant reports, information retrievable from NRC records for executing this T data and NRC will also initiate and obtain any additional information fask.

the licensee that will be necessary rom the execution of the inspection defined under this Tackin the preparation for and 7.0 PERIOD OF PERFORMANCE The period of performance for the work specified in the Task chall begin the date of execution of the Task Order and shall continue through March 1, 1993.

8.0 TECHNICAL DIRECTION t

The NRC Dam Safety Officer is John T. Greeves Technical Assistance Project Manager (TAPM)

(301/504-3334). The (301/504-2596) and the is Robert E.

Shewmaker (301/504-2573).

Technical Monitor (TM) is Daniel S. Rom 9.0 ESTIMATED LEVEL OF EFFORT 1

The estimated effort for this first inspection task is as follows

t t--

3 ^

f I

in terms of person-days of effort. These include preparation, travel, inspection, report preparation, meetings and issuance of a final report.

i 1

1 FERC Headquarters 5 days.(total)

FERC Portland 3 days (preparation) 5 days (travel & inspect) 10 days (report)

FERC (other region) 3 days (preparation) 5 days-(travel & inspect) 3 days (report input) l FERC (All) 6 days (meetings) i Miscellaneous 5 days.

TOTAL 45 person-days i