Summary of Calvert Cliffs Assessment Panel 900607 Meeting in King of Prussia,Pa Re Update of Status of Calvert Cliffs Performance Improvement Plan.List of Attendees Encl
ML20044A772
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 06/21/1990
From: Boger B
NRC - CALVERT CLIFFS ASSESSMENT PANEL
To:
NRC - CALVERT CLIFFS ASSESSMENT PANEL
References
NUDOCS 9007020224
Download: ML20044A772 (5)


Text

-

6' 1

,,kY og UNITED STATES y ' )3 g

NUCLEAR REGULATORY COMMISSION r,

i

,, ;j W ASmNOTON, D, C. 20655

'N v /

v....

MEMORANDUM FOR:

Calvert Cliffs Assessment Panel FROM:

Bruce A. Boger, Chairman Calvert Cliffs Assessment Panel

SUBJECT:

MEETING MINUTES FROM THE CALVERT CLIFFS ASSESSMENT PANEL MEETING #5 - PUBLIC MEETING WITH BALTIMORE GAS AND ELECTRIC ON THE CALVERT.

CLIFFS PERFORMANCE IMPROVEMENT PLAN - 06/07/90

+

I A public meeting was conducted between Baltimore Gas and Electric (BG&E) and l

the Calvert Cliffs Assessment Panel (CCAP) on June 7.-1990, to provide an update of the status for the Calvert Cliffs Performance Improvement Plan by BGAE. The meeting was held at the NRC Region I Office in King of Prussia, Pennsylvania.- A list of attendees is attached, as well as a copy of the slides l

provided.

Mr. Bruce Boger began the meeting with a brief recap of events concerning Calvert Cliffs over the past year, including plant restart and submission of PIP revisions. There was an introduction of attendees. Mr. George Creel (BG&E) made brief opening remarks, giving a progress report on the status of the PIP.

Lee Russell'(PG8E) began the BGLE presentation with an outline of the meeting i

surpose and agenda, tie stated the objectives of the meeting were to review to 11 story of the PIP, describe revisions to the PIP, present the current status ofthePIPImplementationProgram(PIPIP)and'discusstheImplementation program management. He outlined development of the PIP and creation of the PIP ~

Implementation program. He detailed the PIP program structure and the need for i

issuance of PIP revisions due to additional action plans. The question was-l asked as to why new action plans were necessary. Rich Olson (BG&E) stated that ongoing PIP activities highlighted the need for additional plans..Also there was the need to consolidate smaller systems of-management into the PIP process, as well as feedback received from employee meetings and the PIP verification program.

x Rich Olson continued the BG&E presentation with a discussion of BG&E's Implementation Program Management. He discussed PIP action plan' schedules and resource loadings. He outlined the program controls used, both at the project level and management level.

He discussed PIP. verification' assessments, outlining how the assessment was performed and the results. During questions j

l it was noted that an action plan is considered complete by BG&E in its data-J base when the implementation verification is complete. Since this is prior to the effectiveness verification, discussions centered on the role of the BG&E i

effectiveness verification process.

BG&E noted that one effectiveness verifica-tion inspection is complete and the second one is planned for later this year.

'l 9007020224 900621 ADOCKOSOOg317 hhj DR j

i

' T Q l

l

i

- June 21, 1990 At this point in the presentation, three BG&E managers individually discussed representative PIP activity results.

Charlie Cruse discussed System Engineering, Communications, Root Cause analysis improvements. Mike Markowski discussed Commitment Tracking System and the current status count of NRC commitments and g

cumulative performance. Jim Lemons discussed the Procedure Upgrade Project status and the Communications Plan implementation.

The issue of effectiveness verification was not resolved at the conclusion of the meeting. BG&E was advised that the NRC needed some confidence in the utility's ability to verify the effectiveness of action plan implementation before the NRC could reach a conclusion on whether the PIP contains an adequate process for resolving PIP identified root causes.

After brief closing comments by Mr. Boger and Mr. Creel, the meeting was adjourned.

o Bruce A. Boge, Chairman Calvert Cliffs Assessment Panel

Enclosures:

As Stated

4

' June 21, 1990 At this point in the presentation, three BG8E managers individually discussed representative PIP activity results. Charlie Cruse discussed System Engineering, Communications, Root Cause analysis improvements. Mike Markowski discussed Commitment Tracking System and the current status count of NRC connitments and g

cumulative performance. Jim Lemons discussed the Procedure Upgrade Project status and the Communications Plan implementation.

The issue of effectiveness verification was not resolved at the conclusion of the meeting. BGAE was advised that the NRC needed some confidence in the utility's ability to verify the effectiveness of action plan implementation before the NRC could reach a conclusion on whether the PIP contains an adequate process for resolving PIP identified root causes.

After brief closing connents by Mr. Boger and Mr. Creel, the meeting was adjourned.

ORIGINAL SIGNED:

Bruce A. Boger, Chairman Calvert Cliffs Assessment Panel

Enclosures:

i As Stated

[CCAP3]

iend a:ct

( /90

i i

CALVERT CLIFFS ASSESSMENT PANEL MEETING JUNE 7, 1990 LIST OF ATTENDEES j

'1

(

.CCAP.NEMBERS ORGANIZATION

. Bruce Boger

.NRR/DRP(CCAPCHAIRMAN)

William Kane DRP,. Region I

-Jim Linville DRP,. Region !

Curt Cowgill DRP, Region I Robert Capra NRR/DRP Robert Gallo DRS, Reg (ionICCAPCOORDINATOR i

NRR/DRP Anthony Mendiola-Dan Mcdonald NRR/DRP Larry Nicholson, SRI,.Calvert Cliffs BG&E. MEMBERS Charles Cruse BGAE i

Richard Olson BG8E George Creel BG&E, VP - Nuclear-Mike Markowski BG&E Ann Donahoe BG&E J. Lemons BGAE L. Russell BG&E G.'Detter BG&E~

OTHER.NRC Kirke Lathrop DRP, Region I T. J. Kim RI, Calvert Cliffs' Mike Case NRR/DLPQ James Caldwell EDO:

3 Allen Howe RI, Calvert Cliffs Robert Bores DRS, Region I-l Victor McCree RI, Calvert Cliffs OTHER. ATTENDEES j

Richard McLean Maryland DNR l

t

....0

.l; 4

e I

d

+

. DISTRIBUTION I

' m: 6 450-317/318)

NRC & Local PDRs AD RI RF BBoger AJMendiola JCaldwell, EDO-JPartlow SVarga I

WKane, RI RCapra 11 Case DMcDonald RGallo, RI-JWiggins, RI.

JDiDonato, RI JLinville, RI i

CCowgill, RI-LNicholson, SRI Calvert Cliffs e