VPN-013-99, Forwards Fitness for Duty Program Performance Data Rept for July-Dec 1998
VPN-015-99, Submits Following Info That Will Be Needed for NRC Staff to Complete Review & Issue Trojan ISFSI License,As Result of 990121 Meeting with NRC Following Insp & Observation of ISFSI Preoperational Testing During Wk of 990118
VPN-012-99, Forwards Rev 0 to PGE-1076, Trojan Reactor Vessel Package Sar. Approval,With Certain Conditions,For one-time Shipment of Trojan Reactor Vessel Package Granted by Commission Via Ltr
VPN-021-99, Forwards Proposed Ts,Update to ISFSI SAR & Revised Calculation,Per Application for Trojan ISFSI License
VPN-028-99, Forwards Endorsements 139 to Nelia Policy NF-0225 & 2 to Nelia Policy NW-0602
ML18107A691
VPN-029-99, Forwards Amend 21 to PGE-1012, Trojan Nuclear Plant Fire Protection Plan, Per 10CFR50.48(f).Amend Reflects Revs Made During Decommissioning Activities
VPN-030-99, Forwards Rev 6 to PGE-1061, Trojan Nuclear Plant Decommissioning Plan. Summary of Changes,Attached.Revised Portions Denoted by Side Bars
VPN-008-99, Transmits Tnp co-owners Annual Rept of Status of Decommissioning Funding for Tnp.Rept Is Based on Most Recent Analysis of Tnp Decommissioning Estimate & Funding Plan,Per Rev 6 to Pge, Tnp Decommissioning Plan
VPN-007-99, Forwards License Amend Application 247 Requesting Amend to License NPF-1 to Add License Condition Denoting NRC Approval of PGE-1078, Trojan Nuclear Plant License Termination Plan, Also Encl.With Certificate of Svc
VPN-037-99, Forwards Licensee Comments on NRC Preliminary SER & License Re Trojan Isfsi.Encl Includes Justification for Inclusion in ISFSI TS of Alternative Method to 10CFR20.1601(c) for Controlling Access to High Radiation Areas
VPN-036-99, Forwards Rev 4 to PGE-1063, Suppl to Applicants Environ Rept - Post Operating License Stage
VPN-038-99, Forwards Updated TS 5.6 Re High Radiation Area,Per Telcons with Nrc.Justification for TS Was Provided Previously with Util Ltr Dtd 990317,but Has Been Updated & Is Included as Encl 2
VPN-027-99, Transmits Completed Application for Renewal of NPDES Permit for Trojan Nuclear Plant,Iaw License NPF-1,App B,Epp,Section 3.2
VPN-032-99, Forwards PGE-1009-98, Operational Ecological Monitoring Program for TNP,Jan-Dec 1998, Including All Existing non-radiological Effluents
ML20205N906
ML20205T547
VPN-031-99, Forwards Trojan Nuclear Plant,Radiological Environ Monitoring Rept for CY98. Rept Submitted in Accordance with Trojan Permanently Defueled TS 5.8.1.2 & Sections IV.B.2, IV.B.3 & Iv.C of App I to Title 10CFR50
ML20206C959
ML20206C922
ML20206E021
ML20206E173
ML20206N157
ML20206H433
ML20206J793
ML20206J868
VPN-049-99, Forwards Revised Epips,Including Rev 7 to EPIP 3, Response Organization Checklists & Rev 9 to EPIP 5, Emergency Preparedness Test Propgram. Changes to EPIPs 3 & 5 Ref New Owners of on-site Railroad Line,Portland & Western Railroad
ML20207A275
ML20196L125
ML20207D386
ML20195J011
VPN-051-99, Forwards Amend 22 to PGE-1012, Trojan Nuclear Plant Fire Protection Plan, IAW 10CFR50.48(f).Amend Reflects Revs Made During Decommissioning Activities & Does Not Reduce Effectiveness of Fire Protection
VPN-056-99, Responds to NRC 990609 RAI Re License Change Application 244 & Accompanying Request for Exemption.Detailed Info Supports Estimation of Remaining Radioactive Matl Previously Provided by Licensee
VPN-053-99, Forwards Rev 8 to Defueled Sar,Including Changes Since Last Submittal.Attachment Includes Brief Description of Each Change Included in Rev
ML20209D623
VPN-061-99, Forwards Rept Describing Effects of Earthquake That Occurred on 990702 Near Satsop,Wa,Iaw Trojan Nuclear Plant Defueled Sar,Section 4.1.3.1
ML20210A640
VPN-069-99, Forwards Rev 1 to PGE-1076, Trojan Reactor Vessel Package Sar. Changes to Rept Contained in Rev 1 Received NRC Approval by Ltr
ML20216D661
ML20210H597
VPN-067-99, Forwards Proposed Rev 23 to PGE-8010, Trojan Nuclear QAP, in Response to NRC 990708 RAI Re Relocation of TS ACs to Qap.Revised QAP Will Be Made Effective Concurrently with Implementation of License Change Application Lca 245
ML20211B409
ML20211A713
VPN-074-99, Forwards fitness-for-duty Program Performance Data Rept for Period of 990101-0630,IAW 10CFR26.71(d)
ML20211J210
ML20211Q328
ML20216F287
ML20216F762
ML20217C817
VPN-084-99, Submits Notification of Major Changes to Trojan Liquid Radioactive Waste Treatment Sys,Iaw PGE-1201.Detailed Description of Change Provided
VPN-076-98, Forwards Final Rept of Matl Properties of Neutron Shielding Matl to Be Used in Trojan ISFSI & Test Repts That Verified Matl Properties
VPN-080-98, Forwards Updated ISFSI Emergency Plan,Per 981123 & Discussion in Meeting with NRC on 981119.Description of Changes Encl
VPN-001-99, Requests That Svc List for Delivery of Documents from NRC Be Updated,Per 981230 Telcon.Substitute for Listings of HR Pate & J Westvold,Submitted
VPN-004-99, Forwards Rev 5 to PGE-1061, Trojan Nuclear Plant Decommissioning Plan. Table 2.2-5 Is Revised to Depict Major Components Removed from Plant During 1998.Revs Are Denoted by Side Bars
VPN-002-99, Forwards Rev 1 to PGE-1073 Tnp ISFSI Security Plan,As Result of 981208 Telcon with Nrc.Encl Withheld,Per 10CFR73.21
ML20199J080
ML20199J166
VPN-013-99, Forwards Fitness for Duty Program Performance Data Rept for July-Dec 1998
VPN-015-99, Submits Following Info That Will Be Needed for NRC Staff to Complete Review & Issue Trojan ISFSI License,As Result of 990121 Meeting with NRC Following Insp & Observation of ISFSI Preoperational Testing During Wk of 990118
VPN-012-99, Forwards Rev 0 to PGE-1076, Trojan Reactor Vessel Package Sar. Approval,With Certain Conditions,For one-time Shipment of Trojan Reactor Vessel Package Granted by Commission Via Ltr
VPN-021-99, Forwards Proposed Ts,Update to ISFSI SAR & Revised Calculation,Per Application for Trojan ISFSI License
VPN-028-99, Forwards Endorsements 139 to Nelia Policy NF-0225 & 2 to Nelia Policy NW-0602
VPN-029-99, Forwards Amend 21 to PGE-1012, Trojan Nuclear Plant Fire Protection Plan, Per 10CFR50.48(f).Amend Reflects Revs Made During Decommissioning Activities
VPN-030-99, Forwards Rev 6 to PGE-1061, Trojan Nuclear Plant Decommissioning Plan. Summary of Changes,Attached.Revised Portions Denoted by Side Bars
VPN-008-99, Transmits Tnp co-owners Annual Rept of Status of Decommissioning Funding for Tnp.Rept Is Based on Most Recent Analysis of Tnp Decommissioning Estimate & Funding Plan,Per Rev 6 to Pge, Tnp Decommissioning Plan
VPN-007-99, Forwards License Amend Application 247 Requesting Amend to License NPF-1 to Add License Condition Denoting NRC Approval of PGE-1078, Trojan Nuclear Plant License Termination Plan, Also Encl.With Certificate of Svc
VPN-037-99, Forwards Licensee Comments on NRC Preliminary SER & License Re Trojan Isfsi.Encl Includes Justification for Inclusion in ISFSI TS of Alternative Method to 10CFR20.1601(c) for Controlling Access to High Radiation Areas
VPN-038-99, Forwards Updated TS 5.6 Re High Radiation Area,Per Telcons with Nrc.Justification for TS Was Provided Previously with Util Ltr Dtd 990317,but Has Been Updated & Is Included as Encl 2
VPN-036-99, Forwards Rev 4 to PGE-1063, Suppl to Applicants Environ Rept - Post Operating License Stage
VPN-027-99, Transmits Completed Application for Renewal of NPDES Permit for Trojan Nuclear Plant,Iaw License NPF-1,App B,Epp,Section 3.2
VPN-032-99, Forwards PGE-1009-98, Operational Ecological Monitoring Program for TNP,Jan-Dec 1998, Including All Existing non-radiological Effluents
VPN-031-99, Forwards Trojan Nuclear Plant,Radiological Environ Monitoring Rept for CY98. Rept Submitted in Accordance with Trojan Permanently Defueled TS 5.8.1.2 & Sections IV.B.2, IV.B.3 & Iv.C of App I to Title 10CFR50
VPN-049-99, Forwards Revised Epips,Including Rev 7 to EPIP 3, Response Organization Checklists & Rev 9 to EPIP 5, Emergency Preparedness Test Propgram. Changes to EPIPs 3 & 5 Ref New Owners of on-site Railroad Line,Portland & Western Railroad
ML20196L125
ML20207D386
VPN-051-99, Forwards Amend 22 to PGE-1012, Trojan Nuclear Plant Fire Protection Plan, IAW 10CFR50.48(f).Amend Reflects Revs Made During Decommissioning Activities & Does Not Reduce Effectiveness of Fire Protection
VPN-056-99, Responds to NRC 990609 RAI Re License Change Application 244 & Accompanying Request for Exemption.Detailed Info Supports Estimation of Remaining Radioactive Matl Previously Provided by Licensee
VPN-053-99, Forwards Rev 8 to Defueled Sar,Including Changes Since Last Submittal.Attachment Includes Brief Description of Each Change Included in Rev
VPN-061-99, Forwards Rept Describing Effects of Earthquake That Occurred on 990702 Near Satsop,Wa,Iaw Trojan Nuclear Plant Defueled Sar,Section 4.1.3.1
VPN-069-99, Forwards Rev 1 to PGE-1076, Trojan Reactor Vessel Package Sar. Changes to Rept Contained in Rev 1 Received NRC Approval by Ltr
ML20216D661
VPN-067-99, Forwards Proposed Rev 23 to PGE-8010, Trojan Nuclear QAP, in Response to NRC 990708 RAI Re Relocation of TS ACs to Qap.Revised QAP Will Be Made Effective Concurrently with Implementation of License Change Application Lca 245
VPN-074-99, Forwards fitness-for-duty Program Performance Data Rept for Period of 990101-0630,IAW 10CFR26.71(d)
ML20216F287
ML20216F762
VPN-084-99, Submits Notification of Major Changes to Trojan Liquid Radioactive Waste Treatment Sys,Iaw PGE-1201.Detailed Description of Change Provided
05000344/LER-1990-016, Forwards LER 90-016-00 Advising That Calibr of Main Steam Flow Instruments Did Not Include All Required Elements.W/O Encl
ML20043G584
ML20043H917
ML20043H987
ML20044A088
ML20055D709
ML20055D044
ML20055D041
ML20058K489
05000344/LER-1990-015, Forwards LER 90-015-00 Re Control Room Emergency Ventilation Sys Coolers Found Inadequately Sized to Maintain Design Basis Temp.Rept Submitted 2 Wks Beyond 30-day Requirement Due to Difficulties Encountered in Preparation
Trojan Nuclear Plant Reactor-Vessel Material Surveillance Program In a March 27, 1990 conversation with Messrs. Bevan, Randall, and Tsao of' l
~the U.S~. Nuclear Regulatory Comission Portland Ceneral Electric Company, 2
~
(PGE) was requested.to identify the references containing the most complete listing of the Trojan reactor vesse1~ materlais and their preservice c
properties.s The attached listing identifies these references and-the specific tables containing the requested information.
TNeo references have all.been previously transmitted to the U.S. Nuclear Regulatory Commission.
If'any additional copies are needed, please let us know.
sincerely, 3
T. D. Walt Acting Vice President, Nuclear
Attachment c:
Mr. John B. Martin -
. Regional Administrator, Region V U.S. Nuclear Regulatory Commission Mr. David Stewart-Smith State of Oregon Department of Energy l
Mr. R. C. Barr NRC, Resident Inspector Trojan Nuclear Plant
$E0"l88348egygg PDC 121 SW Sa men S'reet. Portand. Oregon 97204 d
--- ~-----
l O>
i
,h
,): y.
,rj. i-9,2 pm w m y
Trojan Nuclear Plant Document Control Desk Docket 50-344 ;
June 19, 1990
-License NPF-1:
Attachment Page 1 of 1 p
TROJAN NUCLEAR PLANT REACTOR VESSEL MATrem e ApptIr m w g.,._;_gg o
haa - t
~ Location
?
Portland General Riectric Company.
Figure 1, Tables 1 through 8 (PGR) letter to Nuclear Regulatory Comunission.(NRC)- dated May 22, 1978 Westinghouse Comunercial Atomic Power Tables 3-1 through 3-5 i
(WCAP) 8426, PGE Trojan Unit No. 1 Reactor Vessel Radiation Survalliance Program,; January 1975-WCAP 9469, Analysis of Capsule U from Table A-1 PGE Trojan Reactor Vessel Radiation Surveillance Program, May 1979.