ML20043B743

From kanterella
Jump to navigation Jump to search
Summary of 900423 Meeting in Tuba City,Az Re Site Tour & Review of QC Records
ML20043B743
Person / Time
Issue date: 05/14/1990
From: Jacoby D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
Shared Package
ML20043B741 List:
References
REF-WM-73 NUDOCS 9005310226
Download: ML20043B743 (5)


Text

M+1 s

nh.

--w s

4

  • i

-Y 4 C x

e 3, f s.m[

g{-;p --v

+

[,:4 }

'n, 4

UNITED STATES '

8%g.

v Y

..u.

NUCLEAR REGULATORY COMMISSION; x

< i n'

~ - -

REGION IV URANIUM RECOVERY FIELD UF*lCE -

P

., m,.

sox 5335 DENVER. COLORADO 80325 '

1 o

s gg; I 41990 m

U i URFO': DLJ.

F

' Docket No.- WM-73.

n

(

- MEMORAN'DUM FOR:

Docket' File No..WM-73~~

s w#

FROM::

D. J.-lJacoby J ;",

. Project' Manager M

SUBJECT:

TUBA CITY UMTRA' PROJECT INSPECTION'

.n r

Kf,

p

L

{3

. Date: ' April 23,:1990 y,

' Location:

Tub'a City, Arizona -

Participants:

NRC DOE-u[

E. ~ Hawkins, Deputy Director M.LAbrams,; Site Engineer R.-Gonzales,LProject Manager

'M. Scoutaris; QA Manager:

r g

D. Jacoby, Project Manager and Team Leader L{

7:

. 'TACL fK. Agogino,' Site Manager

N. Larsen, Site Engineer 4

0.; Van Bibber, QALEnginee'r M. Alewine, QA Specialist g

h,

~E. Storms,' Site Hydrologist-1 C.-Persson-Reeves,' Site.NEPA Coordinator gg

==E b

Purpose:

DOE' requested.that NRC be present.during their Final! Inspection

'~

(walk-over) so that concurrent' but separate evaluations could be E

obtained.s 'NRC conducted'a review of construction activities to ascess'.the effectiveness of the construction.and' quality control

,_[

. program to' assure. compliance with.the RAP and EPA standards.

n 1:L h a

u, iji Following an^ introduction.of-participants and a safety orientation by the RAC, the,NRC staff toured the site and reviewed the quality control records.

DOE m 'r '

,C personnel conducted-separate site tours and perforred a record evaluation of l

the type A. riprap placement.

E E

r (N lfi "f

z

( 93, 9005310226 900514 N

- h?

PDR WASTE 3

PDC

= y;:p:n.,;

WM-73 ELR kn

=

w y$h, t.

s

'y

- - ' ' " ' ' ' - ~ " '

n4

.\\ t f,, '

+

S s

MAY I4 !930 m

Site Tour J

LA'RAC representative, Bob.Hindman, accompanied the NRC staff.on the site tour.

' Observed aspectsfof the project were:

  • : Locations of monitoring ' wells.

Reclaimed embankment structure.

  • 1 Diversion systems (Interceptor Ditches No. 1 and 2).

)

  • Toe ditches'(Nos' 1 and.2).
  • -Site monuments.

, Construction activities observed included completion.of placement of the

' erosion protection on the southeast outslope'and final handgrading~of the rock in several locations.

The riprap erosion protection'is dense,:well graded basai 2 that should resist-long' exposure to weathering..The individual stone fragments are reasonably well contained within the layer thickness <of each rock size. The surface of the'riprep'on'the embankment and in the diversions'and-Editches~.is'well-keyed with a minimum number'of voids.

During theisite tour,-the.NRC staff observed two thickness verification tests being conducted' by DOE on theltype A riprap.- Both tests indicated that

~

6einches of' type A riprap'was present. ~Small. pockets appearing to'contain

< excessive amounts-of' fine material were~ observed on the embankment top..These

~ areas were small and contained a significant amount of rock, so the overall.-

. design willinot be affected.

The slope of. Interceptor Ditch No. 2 appears to have a negative gradient at the-outlet.:. This negative gradient may result in some-ponding in this. area, but should not affect performance during the design flood event.

It.was also noted t

that'a.significant amount of " sanding in" had already occurred'in several

' riprapped areas.: The most noticeable of these areas being along the north

section'of Interceptor Ditch No. 1.

'This was expected, due to the desert

.. envi ronment.

Record Review

.The. staff selectively reviewed testing and daily inspection records to determine if~the specifications had been met.

Reviews were conducted on the

-following records:

3 1.=

. Radon barrier placement-density and moisture.

/

2.'

Radon barrier classification.

v 3.L Radon _ barrier gradation.

,y l

h, I

,m,

-p

-t

x L

c t

g 3

3 MAY l 41990

%uWs 4.

Radon barrier 1 point compaction tests.

5..

Testing sand calibration.

6.

' Correlation between oven and microwave moisture contents.

7; Erosion' protection gradations, i

t

- 8.;

Erosion protection durability tests.

Radon Barrier. Records Radon barrur material;was.placed from November 1988 to August of 1989., Spot checks of placement density'and moisture records up to April 1,1989, were

~

-found acceptable to support:the RAP.. However,- beginning, April 1; 1989,-the recording system was changed, and the l'AC no longer maintained a record of-

[

volume of material-placed. "Therefore, it was not possible'during the-i A mection' to verify-all specifications;and testing frequencies tied to ;

pjacement volume. :The RAC representative indicated that the required records.

can be developed from other sources.. Another deviation from the RAP and RAIP.

a cided the number of.placament tests between:1 point compaction tests. : Spot

'i 1.N 31ngJrecords indicateu...dt more'than 10 placement' tests were-performed' uutween 1 point: compaction tests during two time' periods in July 1989.. -:These

, incidents areLisolated and do not appear to have negatively affected the QC.

program.. The compaction-test results and' frequencies,were not checked due~to:

0

. time' restraints.1

(

Rock Testing'

' Review of-testing records indicated gradation and durability-tests were f

conducted by.00E in~accordance with specified test procedures and frequencies.

L

' Records indicate that erosion protection materials mettor exceed the

-specificationsk Issues

.At'the request of DOE, representatives of the.RAC were not included in the exit i

L iconference.

Items discussed included:

k

?l

1...

'The slope at the' outlet of Interceptor Drain No. 1.

No action was i

h.

requested.

i 2.-

.The pockets of fines in the type A riprap.

No action-was requested.

m 7

3.

The lack of placement volume records for the radon barrier materials.

DOE will be requested to obtain the required records and then summarize the testing program results, p

4.

'The deviation from the RAIP in regard to the 1 point compaction tests.

No

. action was requested.

1 b

5.

I p

.N

v. w-n.

n'

.9 n

l*

'{

j;;

,s e

i 4

g ; g ggg t

5.. ' PID, Nos.: 18-S-21,- 18-S-14, and 18-S-15.

DOE will'be requesta: a provide sections 01055 and-01056, and orawing TUB-PS-10-0835, of the specifications.

referenced by PID Nos. 18-S-11 and-18-S-14.. Also,-tha revisions for PID No.:-l18-5-15 will be requested.-

g D. L Jacob Pro ct Man er i

Approved by:-

M Rdon E. Hall

/

l Director x,

t 3

l.';.-

3 g

i

..h' 1:

a

_p

~

' n-mm :.-

l$

j l1 5

t4i r

'.{

J i

s L'

1'-

.i l

I,:

p;..

I

.')

/.-

i rff

1'.

r

, ;y 7't

,,,a A

f

'N

--.--.+-

, 1-9, 1

s 3y::h' !>:

W:.;

i 4._ t:i::'L 7

,, ; ;,;b,

~

z t

. iy 141',,

e s

ti r

n

.,.i. :

taw:

r I

.a J

5

'WM-73/DLJ/90/04/26/M.

A-

"s

DISTRIBUTION.

.c -

i *..,

Docket File WM '

c im

FPDR/DCS9/-

W'

-URF0 r/fi

!ABBeach, RIV'.

s s LLO Branch,: LLWM.

1 H

o-

[S", ;2 DJacoby-ij 4

RGonzales t^

sEHawkins l

'RCPD,'AZz s

m

? --

1 3,c 1, l

, c-8 E

-: 4 -

n I

'4

.; j,

.[_ l,.. y

,.--].

T 3

.F

..i, :

1E J[-i s

'f

a..

M

)CONCURRENCEi>

-DATE:

n..

DJacoby/URF0/lv--

M S/J/90 k

/ RGonzales/URFO.

8f8 s

m.

'/EHawkins/dRF0

[/o.hD S

,3

+M./F r

oj

, d /#

,I

REHall/URF0' e

g

(

L

?

'4

2. #,.

1 f,,

a

~

1 3

-5 NI,

)

+.

') f 3>

t.}lfcl,

1 ':

.'f

!yy,...

a

. ; U.

ch/

k b.

i jj i :# 3;7..., 1 hf;f l:l0lE: '; l!A--

,j c

--1 i