COL Docs - NRC Slides for the Technical Exchange on Non-Material Issues Related to Completion of ITAAC
ML20042E344
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 02/11/2020
From:
NRC
To:
NRC/NRR/DNRL
References
Download: ML20042E344 (8)


Text

From:

Rankin, Jennivine Sent:

Tuesday, February 11, 2020 1:32 PM To:

Humphrey, Mark Phillips; Chamberlain, Amy Christine; Arafeh, Yasmeen N.

Cc:

Hall, Victor; Vogtle PEmails

Subject:

NRC slides for the Technical Exchange on Non-Material Issues Related to Completion of ITAAC Attachments:

NRC slides for 0213 public meeting on expedited LAR.pdf Good afternoon, The NRC staff looks forward to our technical exchange on Thursday, February 13, 2020 regarding non-material issues related to completion of ITAACs. The NRC staff has had internal discussions and have developed the attached slides to aid in our discussion on Thursday.

Please let me know if you have any questions.

Thanks, Jennie Jennie Rankin, Project Manager Vogtle Project Office Office of Nuclear Reactor Regulation

Hearing Identifier:

Vogtle_COL_Docs_Public Email Number:

537 Mail Envelope Properties (BL0PR0901MB376316D49F24539C63C1703B98180)

Subject:

NRC slides for the Technical Exchange on Non-Material Issues Related to Completion of ITAAC Sent Date:

2/11/2020 1:31:57 PM Received Date:

2/11/2020 1:32:00 PM From:

Rankin, Jennivine Created By:

Jennivine.Rankin@nrc.gov Recipients:

"Hall, Victor" <Victor.Hall@nrc.gov>

Tracking Status: None "Vogtle PEmails" <Vogtle.PEmails@nrc.gov>

Tracking Status: None "Humphrey, Mark Phillips" <MPHUMPHR@southernco.com>

Tracking Status: None "Chamberlain, Amy Christine" <ACCHAMBE@southernco.com>

Tracking Status: None "Arafeh, Yasmeen N." <YNARAFEH@southernco.com>

Tracking Status: None Post Office:

BL0PR0901MB3763.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 485 2/11/2020 1:32:00 PM NRC slides for 0213 public meeting on expedited LAR.pdf 117747 Options Priority:

Normal Return Notification:

No Reply Requested:

No Sensitivity:

Normal Expiration Date:

Expedited License Amendment Request February 13, 2020 Public Meeting with Southern Nuclear Operating Company

Expedited License Amendment Review (LAR)

  • The quickest turnaround time for a non-exigent LAR is approximately 35 days.
  • The staff would aim to issue an individual Federal Register Notice (FRN) within 5 days of receiving the LAR.

Applicability and Resource

  • Applies to low-risk, low-complexity, or Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) compliance LARs that impact the construction schedule.
  • Schedule assumes requests for additional information or supplements are not needed.
  • Resource hours expected to start at 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> and increase based on complexity.

Examples of Potential Types of Requests Tier 1 definitions of as-built and test limit flexibility to test systems.

  • ITAAC 195 requires inspections on coating density to ensure coating will not transport. A potential LAR would change the time the inspections are complete until after the 103(g) finding.

Special Steps for NRC Staff

  • Expedite docketing of the application into ADAMS.
  • Expedite issuance of individual FRN.
  • For straight-forward compliance LARs where alignment between project manager (PM) and technical staff has been reached during pre-application activities, PM may draft the safety evaluation and technical staff concur, if necessary.
  • Potential expedited OGC review.

The pilot will confirm

  • Feasibility of publishing individual FRN in 5 days.
  • Accuracy of initial resource estimate.
  • Any potential safety evaluation boilerplate language/conclusions that can be leveraged.