MONTHYEARML24031A0502024-01-31031 January 2024 COL Docs - FW Erroneous Description of Tier 2 Change Process in Construction Lessons-Learned Report ML24017A1122024-01-17017 January 2024 NRR E-mail Capture - Request for Access to Cyber Security Data - Vogtle, Units 3 and 4 ML23360A0042023-12-23023 December 2023 NRR E-mail Capture - Fyi - Office of Nuclear Regulatory Research (RES) Requests for Vogtle 3 & 4 ML23348A0782023-12-13013 December 2023 NRR E-mail Capture - Voluntary Request for Closed Meeting Regarding Cyber Security Assessments at Vogtle, Units 3 and 4 ML23342A0802023-12-0808 December 2023 NRR E-mail Capture - Request for Additional Information (RAI) - Vogtle, Unit 1 - Review of SG Tube Inspection Report for Refueling Outage 24 (L-2023-LRO-0067) ML23331A9992023-11-27027 November 2023 COL Docs - Re Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23331A9492023-11-26026 November 2023 Email Dated November 26, 2023, from Bo Pham to SNC and NRC - Vogtle Seismic Hazard Report ML23326A2802023-11-22022 November 2023 COL Docs - Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23331A9622023-11-22022 November 2023 Email Dated November 22, 2023, from SNC to NRC - Vogtle Seismic Hazard Report ML23320A0342023-11-16016 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Companys License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23320A2372023-11-0808 November 2023 NRR E-mail Capture - (External_Sender) Proposed LAR Regarding the Ultimate Heat Sink at Vogtle, Units 1 and 2 ML23312A2632023-11-0808 November 2023 COL Docs - Action Request for State of Georgia Comment by 5pm Monday, November 13, 2023 - Vogtle Units 3&4, LAR-22-002, TS 3.8.3, Inverters - Operating Completion Time Extension ML23311A1512023-11-0707 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Companys License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23304A2272023-10-31031 October 2023 NRR E-mail Capture - Request for State of Georgia Comment by 5pm Monday, Nov. 6, 2023 - License Amendment Request for Vogtle Unit 4 - to Remove Combined License Appendix C ML23289A1362023-10-16016 October 2023 COL Docs - Action Request for State of Georgia Comment by 5pm Friday, October 20, 2023 - Vogtle Units 3&4, LAR-23-006, Rev.1, More Restrictive Action for Tech. Spec. 3.1.9 ML23283A0332023-10-10010 October 2023 COL Docs - FW Vogtle Units 3 and 4 (LAR 23-009) ML23283A0452023-10-0808 October 2023 E-Mail Re Plant Vogtle - Neop Letter Dated October 8, 2023 - Vogtle 3 & 4 - TS 3.7.6 License Amendment Request ML23279A2082023-10-0505 October 2023 Issuance of Formal RAIs - Vogtle, Units 1 and 2 - Proposed LAR and Proposed Alternative Request to Revise TS 3.4.14.1 and IST ALT-VR-02 (EPIDs L-2023-LLA-0061 and L-2023-LLR-0023) ML23275A1002023-10-0202 October 2023 COL Docs - Re Action Summary of 9.27.23 Clarification Call with Southern Nuclear Company on LAR-22-0002, TS 3.8.3 Inverters - Operating Completion Time ML23270B1912023-09-27027 September 2023 COL Docs - Update Vogtle Units 3&4 Acceptance Letter for LAR-22-002 Technical Specification 3.8.3, Inverters Operating ML23263A1042023-09-20020 September 2023 COL Docs - FW Fyi for Tomorrow'S Psm Meeting ML23257A2092023-09-14014 September 2023 NRR E-mail Capture - Formal Issuance of 2nd Round RAIs for Surry Units 1&2 and North Anna Units 1&2 Emergency Plans LAR ML23257A0632023-09-13013 September 2023 NRR E-mail Capture - Acceptance Review of Southern Nuclear Operating Company'S License Amendment Request to Remove Combined License Appendix C ML23256A2682023-09-13013 September 2023 COL Docs - Acceptance Review of Southern Nuclear Operating Companys License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23248A3482023-09-0505 September 2023 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) 6 - Vogtle - TSTF-339 LAR (L-2023-LLA-0053) ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) ML23243A9172023-08-31031 August 2023 NRR E-mail Capture - (External_Sender) Re Question - Legal Contact(S) for Vogtle Electric Generating Plant, Units 3 & 4 ML23241A0452023-08-29029 August 2023 COL Docs - FW Draft LAR and Exemption Request Regarding Tier 1 and Tier 2 Requirements ML23229A2322023-08-17017 August 2023 COL Docs - FW Re LAR 22-002 Second Round RAI Approved ML23188A151 for Vogtle Units 3 & 4 ML23223A0142023-08-10010 August 2023 NRR E-mail Capture - Acceptance Review - SNC Fleet Exemption to 10 CFR 73.2, Physical Barriers ML23221A3982023-08-0909 August 2023 COL Docs - LAR 22-002 Second Round RAI Approved ML23188A151 ML23216A1592023-08-0404 August 2023 COL Docs - FW Acceptance Review - Requested Licensing Action Regarding TS Revision to Adopt WCAP-17661-P-A, Improved Relaxed Axial Offset Control and Constant Axial Offset Control Fq Surveillance TS (L-2022-LLA-0148 and L-2022-LLA-0149) ML23212A9642023-07-31031 July 2023 COL Docs - Action - Start of Annual Fees - Vogtle Unit 3 Completion of Power Ascension Testing and Declaration of Commercial Operations ML23216A0962023-07-26026 July 2023 Document Request for Vogtle 1 & 2 RP Inspection, Report No. 05000424/2023003 and 05000425/2023003 ML23220A0572023-07-26026 July 2023 Document Request for Vogtle Units 1 and 2 - Radiation Protection Inspection - Inspection Report 2023-03 ML23200A0112023-07-18018 July 2023 Document Request for Vogtle Unit 3 RP Inspection ML23198A1552023-07-17017 July 2023 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) - Hatch, Farley, and Vogtle, Units 1 and 2 Quality Assurance Topical Report (QATR) Submittal Dated June 15, 2023 ML23193A7832023-07-12012 July 2023 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) - Vogtle - TSTF-339 LAR (L-2023-LLA-0053) 2024-01-31
[Table view] |
Text
From: Habib, Donald Sent: Tuesday, February 11, 2020 8:31 AM To: Vogtle PEmails
Subject:
Audit Questions Vogtle Units 3 and 4 - LAR 19-017 2020-01-08 Redacted-Public.docx Attachments: Audit Questions LAR 19-017 2020-01-08 Redacted-Public.docx
Hearing Identifier: Vogtle_COL_Docs_Public Email Number: 535 Mail Envelope Properties (BL0PR0901MB366719EAF28C2FC2F9FCBF5E97180)
Subject:
Audit Questions Vogtle Units 3 and 4 - LAR 19-017 2020-01-08 Redacted-Public.docx Sent Date: 2/11/2020 8:31:00 AM Received Date: 2/11/2020 8:31:03 AM From: Habib, Donald Created By: Donald.Habib@nrc.gov Recipients:
"Vogtle PEmails" <Vogtle.PEmails@nrc.gov>
Tracking Status: None Post Office: BL0PR0901MB3667.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 6 2/11/2020 8:31:03 AM Audit Questions LAR 19-017 2020-01-08 Redacted-Public.docx 33235 Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
LAR-19-017- Audit Questions/Comments January 8, 2020
- 1) The LAR proposes to include line resistance acceptance criterion for the PRHR subsystem of 3.085e-6 ft/gpm^2. [
]
- 2) [
]
- 3) E&DC Licensing Impact Determination Checklist Question 10 (Does the proposed AP1000 Activity deviate from the applicable CLB Regulatory Guides, codes and standards?) was answered No. Why? RG 1.68 specifies performance of a natural circulation test; therefore, without such a test there cannot be conformance with that portion of the guidance.
- 4) [
]
- 5) After SNC submitted LAR 19-017 to the NRC on September 6, 2019, there were several interactions with the staff and the SNC was planning to send a supplement to the LAR.
For the staff to be able to focus on the audit, please provide a draft of the supplement you are working on and a planned date of submittal.
- 6) It is not clear how different data supports LAR 19-017. For example, whether the line resistance PRHR is going to be used for calculating natural circulation flow is not clear.
- 7) Providing a roadmap for the documents provided on Westinghouse ERR will make the audit more efficient. The staff is interested in knowing how those documents support LAR 19-017.
- 8) Enclosure 1 to LAR 19-017 states the following:
In the AP600 Final Safety Evaluation Report (FSER), the NRC staff confirmed that the exception to RG 1.68 was acceptable provided that the training requirements (described in UFSAR Subsection 1.9.4.2.1, TMI Action Plan Issues, under I.G.I, Training Requirements) are met and that Westinghouse demonstrates that all plants remain identical in physical layout and configuration of the proposed plant key components, and validate that acceptance criteria for the ranges of values for other system flow performance measurements that are taken during the ITP confirm that the overall flow characteristics of the proposed plant are
LAR-19-017- Audit Questions/Comments January 8, 2020 equivalent to the reference plant. Demonstrations of the layout of primary components as well as flow measurements are confirmed during the ITAAC closure process and preoperational testing.
Therefore, conformance with the RG requirements as described by the NRC staff in the AP600 FSER is maintained without performance of the preoperational PRHR heat exchanger natural circulation test.
However, AP600 FSER Section 14.2.9.2 states the following:
The staff confirmed that the new Section 14.2.10.3.7, "Passive Residual Heat Removal Heat Exchanger (First Plant Only)," provides for natural circulation testing of the PRHR system during startup testing of the initial plant. In addition, all plants are subjected to natural circulation testing of the PRHR during hot functional testing as described in Section 14.2.9.1.3.(e), (f), and (g). The staff finds that these testing provisions, in conjunction with the issues addressed in SSAR Section 1.9.4.2.1, item I.G.1, and the exception to RG 1.68, Appendix A.4.t in SSAR Appendix 1A, adequately address natural circulation testing for the AP600 design. On these bases, the staff also finds that a COL action item is no longer required on this subject. The staff finds this acceptable, and therefore, OSER COL Action Item 14.2.8-1 is dropped and OSER Open Item 14.2.8-7 is closed.
As such in AP600 FSER the staff has relied on Section 14.2.9.1.3(f) testing which LAR 19-017 proposes to remove and the exception to RG 1.68 apply to the Section 14.2.10.3.7, "Passive Residual Heat Removal Heat Exchanger (First Plant Only) test but not to the Section 14.2.9.1.3(f) test. Please explain.