Requests Shutdown No Later than 820409 for Insp of Four High Pressure Injection Nozzles Discussed During 820316 Meeting. Insp Will Include Both Radiographic & Ultrasonic Exams
ML20042A534
Person / Time
Site: Rancho Seco
Issue date: 03/19/1982
From: Mattimoe J
SACRAMENTO MUNICIPAL UTILITY DISTRICT
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
NUDOCS 8203230530
Download: ML20042A534 (1)


Text

I e suuo SACRAMENTO MUNICIPAL UTILITY DISTRICT O 62o1 S Street. Box 15830. Sacramento, Cahfornia 95813; (916) 452 3211 March 19, 1982 Q

3

~

e w.

~

J

$10, ' EN:

.% c

)

o; m

DIRECTOR OF NUCLEAR REACTOR REGULATION N.

~

o, ATTENTION DARRELL G EISENHUT DIRECTOR N'

DIVISION OF LICENSING U S NUCLEAR REGULATORY COMMISSION WASHINGTON D C 20555 i

DOCKET 50-312 RANCHO SEC0 NUCLEAR GENERATING STATION UNIT 1 j

In response to the conclusions of the meeting of March 16, 1982, the Rancho Seco Nuclear Generating Unit will shut down and inspect the four high-pressure injection nozzles.

This inspection will include both radiographic and ultrasonic examinations.

At the March 16, 1980 meeting, you had discussed a shutdown date of April 6, 1982.

I am requesting that the shutdown be no later than April 9, 1982.

I feel the few extra days will allow us to properly prepare for the inspection and repairs if required.

We are now preparing for the shutdown with activities such as procedures, welder qualification, material procurement, including regular reviews and approvals. We will shut down for our inspection as soon as we are ready, but in no event later than April 9,1982.

,a ohn. Mattimoe Assistant General Manager and Chief Engineer ool 1

/ o 8203230530 820319 PDR ADOCK 0S000312 G