ML20042A153
| ML20042A153 | |
| Person / Time | |
|---|---|
| Site: | Fermi |
| Issue date: | 03/10/1982 |
| From: | Wells D DETROIT EDISON CO. |
| To: | James Keppler NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| References | |
| REF-PT21-82-573-000 10CFR-50.55E, EF2-57150, PT21-82-573, PT21-82-573-000, NUDOCS 8203230147 | |
| Download: ML20042A153 (2) | |
Text
,
Donald A. Wells W
mm ^-
2000 Second Aven Edison mm ue March 10, 1982 EF2-57150 (g 3, d
N
?si G?/
-x ;
Mr. James G. Keppler, Director
- [
. ~
Region III J
e p 3 2 jgg2>
U.S. Nuclear Regulatory Ccmnission
('i gy y, am 799 Roosevelt Road
(.
u! L M a e['
Glen Ellyn, Illinois 60137
\\;A
Subject:
Final Report of 10CFR50.55(e) Item on Non-Seismic Equ Erected Over Seismic (#26).
Dear Mr. Keppler:
This is subnitted as Detroit Edison's final report on Non-Seismic Equiptent erected over Seismic problem which was reported per 50.55(e) requirements.
The problem was originally reported to Mr. J. Konklin of NRC-Region III by Mr. R.W. Barr, Detroit Edison Project Quality Assurance Director, by tele-phone on January 18, 1980. It had been noted, at that time, that non-seismic equipnent was erected over and/or in close proximity to safety related equip-ment.
Edison Engineering had identified the affected equignent as non-seismic pieces of INAC duct located in the Reactor and Auxiliary Buildings. The problem did not exist in the RIIR cmplex, as all INAC duct work there has been seismically designed; nor does it exist in other Fermi 2 buildings such as the Turbine or Radwaste Buildings, as no safety related equipnent is located there.
A redesign of supports in the problem areas was necessary. A contract to do this work was awarded to Giffels Associates, Inc. Giffels conducted a study on the ducts, and an actual reanalysis'of duct hangers was started in July and has been completed. Edison Engineering released to the field the design, erection and detail drawings of the INAC ducts for all systems, (5th floor through sub-basement). This empletes the engineering portion of this item.
Where electrical cables were involved, Sargent and Lundy performed the work under existing contracts. The " Final Piping System Report" was issued by Sargent and Lundy on December 28, 1981. A walkdown is scheduled to begin on March 15, 1982.
If you have questions concerning this matter, please contact Mr. II.A. Walker, Supervisor-Construction Quality Assurance.
Very truly yours, j
f
' < Ylh
. 1 l
DAW /IIAW/cp
/
/ fI(]
i 8203230147 820310
"/
/
j//
PDR ADOCK 05000341 S
.~
Mr. Jarres G. Keppler March 10, 1982 Page 'IWo EF2-57150 cc: Mr.
Richard DeYcang, Director Office of Inspection and Enforement Division of Reactor Inspection Programs U. S. Nuclear Regulatory Camission Washington, DC 20555 Mr. Bruce Little, Resident Inspector U. S. Nuclear Regulatory Comnission 6450 North Dixie Highway Newport, MI 48166