Fr.bruary 1, 1982 PRINCIPAT, STAFF DIR E&IS' 9/D PAO Docket No. 50-346 A/D 91 0 rotroo or m J
% m EDISON License No. NPF-3
' )"MI N E 2.30.1.5 O
d EP&Of Pfle RR 2 P-2-8 W
Mr. James G. Keppler D
s
\\
Regional Director, Region III p
Office of Inspection and Enforcement TsECEfVED U.S. Nuclear Regulatory Commission MR 051982m 8
~
799 Roosevelt Road Glen Ellyn, Illinois 60137 N azar
Dear Mr. Keppler:
Semiannual Radioactive Liquid and Gaseous Release Report
=
For the Period from July 1,1981 Through Decenber 31, 1981 Davis-Besse Nuclear Power Station Unit 1 Enclosed find two (2) copies of the Semiannual Radioactive Liquid and Gaseous Release Report for Davis-Besse Nuclear Power Station covering the third and fourth quarters of 1981.
The applicable portions of Regulatory Guides 1.109, 1.111, and 1.113 have been used along with NUREG-0133 for dose calculations and meteorological modeling methodology to demonstrate compliance with Appendix I to 10 CFR Part 50.
Sincerely, fmON Terry D. Murray Station Superintendent Davis-Besse Nuclear Power Station TDM/DWB/skj Enclosures cc:
Mr. Victor Stello, Jr., Director Office of Inspection and Enforcement Enc 1: 25 copies Ohio Environmental Protection Agency Northwest District Office Encl: 1 copy Mr. Luis Reyes NRC Resident Inspector Encl: 1 copy 6'I THE TOLEDO EDISON COMPANY EDISON PLAZA 300 MADISON AVENUE TOLEDO, OHlO 43652 F203050385 820201 ff DR ADOCK 050 1 1982- [ I ! /
SR