ML20041D441

From kanterella
Jump to navigation Jump to search
Significant Deficiency Rept 10 Re HVAC Damper Deficiency. Requests Addl Time for Completion Due to Rework at Vendors Facility & Plant.Completion Expected by 820430
ML20041D441
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 02/25/1982
From: Kemper J
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
To: Haynes R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
10CFR-050.55E, NUDOCS 8203050323
Download: ML20041D441 (1)


Text

PHILADELPHIA ELECTRIC COMPANY 23O1 MARKET STREET P.O. BOX 8699 1881 -1981 PHILADELPHI A. PA.19101 (215) 841-45o2 JOHN S. KEMPER O

. ... " X "!!"7 1 < O* 8

-si + .,

Mr. Ronald C. Haynes, Director s

~ ,

United States Nuclear Regulatory Commission -

g, ,

Office of Inspection and Enforcement, Region I y.

(P 631 Park Avenue ~)

King of Prussia, Pennsylvania 19406 1

\

234f lli/i

/'

Subject:

Significant Deficiency Report No.*10 'x/

'j HVAC Damper Deficiency s Limerick Generating Station, Units l ' & ~ 2_ .-.

NRC Construction Permit Nos. CPPR-106, -107

Reference:

a) Letter dated December 26, 1980, J. S. Kemper (PECO) to B. Grier (NRC) b) Letter dated Auguet 26, 1981, J. S. Kemper (PECO) to B. Grier (NRC)

File: QUAL 2-10-2 (SDR #10)

Dear Mr. Haynes:

In our referenced (b) letter on the above subject deficiency, we com-mitted that all corrective actions were to be completed by February, 1982.

However, in addition to the rework at the vendor's facility, some work has to be performed at the plant. Hence, the work is not expected to be fully completed until April 30, 1982.

If there are any questions on the matter, we would be pleased to discuss them with you.

Sincerely, b

JMC/kk Copy to: Director of Inspection and Enforcement United States Nuclear Regulatory Commission Washington, D. C. 20555 i', :2 J. P. Durr, Resident NRC Inspector l