ML20041B087
| ML20041B087 | |
| Person / Time | |
|---|---|
| Site: | Vermont Yankee File:NorthStar Vermont Yankee icon.png |
| Issue date: | 02/19/1982 |
| From: | Jackson E VERMONT YANKEE NUCLEAR POWER CORP. |
| To: | Eisenhut D Office of Nuclear Reactor Regulation |
| References | |
| RTR-NUREG-0737, RTR-NUREG-737, TASK-2.B.3, TASK-2.F.1, TASK-TM FVY-82-14, NUDOCS 8202230258 | |
| Download: ML20041B087 (2) | |
Text
.
A..
VERMONT YAN KEE NUCLEAR POWER CORPORATION SEVENTY SEVEN GROVE STREET FVY 82-14 RUTLAND, VERMONT 05701 2.C.2.1 R EPLY TOs ENGINEERING OFFICE 1671 WORCESTER ROAD FR AMINGH AM. M ASSACH USETIS 01701 TELEPHONE 617 872-8100 February 19, 1982 Q)
NECE[VED United States Nuclear Regulatory Commission g
FEstg g,
Washington, D.C.
20555 Attention:
Office of Nuclear Reactor Regulation h.
kp, itM M
Mr. Darrell G. Eisenhut, Director 4
Division of Licensing y/,g9~ h 4
References:
a)
License No. DPR-28 (Docket No. 50-271) b)
Letter, VYNPC to USNRC, FVY 82-1, dated January 5, 1982
Dear Sir:
Subject:
Vermont Yankee Supplemental Response to Reference (b)
The pu* pose of thic letter is to supplement reference (b),
which provised a status for Items II.B.3 and II.F.1 of NUREG 0737. This supplement revises the completion dates previously stated for activities associated with these items.
Item II.B.3 - Post-Accident Sampling Capability i
Supplemental Response:
The system which meets the intent of this item was installed and p m-operational testing was completed by December 30, 1981.
The applicable procedure was revised and issued January 28, 1982.
Personnel trali.1q rf11 be completed by February 28, 1982.
Item II.F.1 - Attachrment 1 - Noble Gas Monitors Supplemental Response:
The unit that failed pre-operational testing was placed back in service and successfully tested on January 21, 1982. The applicable procedure was revised and issued January 28, 1982.
. Personnel training was completed by February 12, 1982. As a 8202230258 820219 Q
POR ADOCK 05000271 p
PDR Qg 0
A.
VERMONT YANKEE NUCLEAR POWER CORPORATION '
U. S. Nuclear. Regulatory Commission February 19, 1982 Page 2 result-of work with the monitor vendor, a correlation between monitor dose reading and stack activity was established on December 17, 1981. This'information has been incorporated into
- Plant Emergency Procedures, which were issued on January 28, 1982.
We trust that the additional information presented is acceptable. Please contact us if you have any questions.
Very truly yours,-