Revises Completion Dates for TMI Action Plan Items II.B.3 & II.F.1 Previously Stated in .Personnel Training for Item II.B.3 Will Be Completed by 820228
ML20041B087
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 02/19/1982
From: Jackson E
VERMONT YANKEE NUCLEAR POWER CORP.
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.B.3, TASK-2.F.1, TASK-TM FVY-82-14, NUDOCS 8202230258
Download: ML20041B087 (2)


Text

.

A..

VERMONT YAN KEE NUCLEAR POWER CORPORATION SEVENTY SEVEN GROVE STREET FVY 82-14 RUTLAND, VERMONT 05701 2.C.2.1 R EPLY TOs ENGINEERING OFFICE 1671 WORCESTER ROAD FR AMINGH AM. M ASSACH USETIS 01701 TELEPHONE 617 872-8100 February 19, 1982 Q)

NECE[VED United States Nuclear Regulatory Commission g

FEstg g,

Washington, D.C.

20555 Attention:

Office of Nuclear Reactor Regulation h.

kp, itM M

Mr. Darrell G. Eisenhut, Director 4

Division of Licensing y/,g9~ h 4

References:

a)

License No. DPR-28 (Docket No. 50-271) b)

Letter, VYNPC to USNRC, FVY 82-1, dated January 5, 1982

Dear Sir:

Subject:

Vermont Yankee Supplemental Response to Reference (b)

The pu* pose of thic letter is to supplement reference (b),

which provised a status for Items II.B.3 and II.F.1 of NUREG 0737. This supplement revises the completion dates previously stated for activities associated with these items.

Item II.B.3 - Post-Accident Sampling Capability i

Supplemental Response:

The system which meets the intent of this item was installed and p m-operational testing was completed by December 30, 1981.

The applicable procedure was revised and issued January 28, 1982.

Personnel trali.1q rf11 be completed by February 28, 1982.

Item II.F.1 - Attachrment 1 - Noble Gas Monitors Supplemental Response:

The unit that failed pre-operational testing was placed back in service and successfully tested on January 21, 1982. The applicable procedure was revised and issued January 28, 1982.

. Personnel training was completed by February 12, 1982. As a 8202230258 820219 Q

POR ADOCK 05000271 p

PDR Qg 0

A.

VERMONT YANKEE NUCLEAR POWER CORPORATION '

U. S. Nuclear. Regulatory Commission February 19, 1982 Page 2 result-of work with the monitor vendor, a correlation between monitor dose reading and stack activity was established on December 17, 1981. This'information has been incorporated into

Plant Emergency Procedures, which were issued on January 28, 1982.

We trust that the additional information presented is acceptable. Please contact us if you have any questions.