Responds to NRC Re Violations Noted in IE Insp Rept 50-244/81-22.Corrective Actions:New Procedure to Implement Emergency Response Organization Reviewed & Approved & Revised Immediate Call List Procedure Issued
ML20040H464
Person / Time
Site: Ginna Constellation icon.png
Issue date: 12/30/1981
From: Maier J
ROCHESTER GAS & ELECTRIC CORP.
To: Haynes R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML20040H453 List:
References
NUDOCS 8202180281
Download: ML20040H464 (2)


Text

r:

t f

.+

R1[?hwjm w~f '"

agr%

9'*F':

dkita U$

" ~ ~

ROCHESTER GAS AND. ELECTRIC CORPORATION e 89 EAST AVENUE, ROCHESTER, N.Y.14649.

- J OHN E. MAIER vntm ose vIct PREstDENT amu coot m 546 2700 December 30, 1981 Mr. Ronald C. Haynes U.S.. Nuclear Regulatory Commission Office of Inspection and Enforcement Region.I 631 Park Avenue King of Prussia, PA 19406-

Subject:

Emergency Preparedness Implementation Appraisal Team R. E. Ginna Nuclear Power Plant Docket No. 50-244

Dear Mr. Haynes:

t In accordance with Rochester Gas and Electric Corporation's-com-mitments as a result of the Emergency Preparedness Implementation appraisal Team inspection and documented.in your letter of December 15, 1981, the following is submitted:

With respect to Item 1 which states:

" Establish an emergency-organization which provides for all emer-gency functions needed during initial, intermediate and final ~

phases of. augmentation.

Revise the Emergency Plan to include a description of the organization, and update implementing proce-dures to be consistent with.the~ organization.

The description shall include sufficient detail to define the command hierarchy; specify its structure, reporting chains and interrelationships at any phase of augmentation; and include supervisory as well as non-supervisory elements.

Updating of implementing procedures will-be accomplished no later than December 18, 1081.

Revision of the Emergency Plan will be accomplished by March 15, 1982."

The following was accomplished:

A new procedure, SC-1.1.B Emergency Response Organization was reviewed and approved at a Plant Operations Review Committee Meeting on Decenber 14, 1981.

The purpose of this procedure is to provide a method consistent with administrative controls to define and irplement the Emergen-cy Response Organization with respect to the various levels of Emergency Classifications as defined in Ginna procedures.

8202180281 820203 PDR ADOCK 05000244 G

PDR

r d

~

With respect to Item 2 which states:

"For each functional area specified within the emergency organi-zation referred to in item 1, provide a list of personnel trained and qualified to perform the tasks associated with the area.

These lists shall identify the current status of each individual.

Provisions to maintain lists current shall be developed and in-plemented.

This will be accomplished no later than December 18, 1981."

The following was accomplished:

An existing procedure, SC-1.12A Immediate Call List, Revision 19, was reviewed and approved at a Plant Operations Review Committee Meeting on December 114, 1981.

This revision included attachments to the procedure which added lists of functions and such persons authorized to perform those functions.

Due to recent changes in administrative processing, this procedure was issued with an _ffective date of Decenber 21, 1981.

We will inform your office in writing when additional items are corpleted.

Sincerely, N-Q,bff'l w John E.

Maler JEM/nh cc:

Document Control Desk