Interim Deficiency Rept 81-10 Re Stainless Steel Reactor Cooling Underground Suction & Return Piping.Unit 1 Replacement Piping Will Be Completed by Jul 1982 & Unit 2 by Fuel Load
ML20040D882
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 01/25/1982
From: Sargent C
COMMONWEALTH EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, 3312N, NUDOCS 8202020346
Download: ML20040D882 (2)


Text

.-

. cN Commonwealth Edison I One First Natiort1 Piaza Chic:go Illincis d

.k O

Address Reply to: Post Office Box 767

-(

, Chicago, Illinois 60690 Janua ry 25, 1982 4

Mr.. James G.'Keppler, Regional Administrator

,9f O

Directorate of Inspection and

'7 f[ FEB1 OdOEll/ED

)

Enforcement - Region III U.S. Nuclear Regulatory Commission

~

1982h 799 Roosevelt Road i e n.E,, p}

Glen Ellyn, IL 60137

\\

a.

LaSalleCountyStationUnits1a)N E

t

Subject:

10 CFR 50.55(e) 30 Day Report #81-RCIC Underground Piping. Final Report NRC Docket Nos. 50-373 and 50-374

Dear Mr. Keppler:

Un December 28, 1981, Commonwealth Edison Comptm notified Mr. Roger Walker of your office of a deficiency with the stainless-steel Reactor Cooling Isolation Cooling (RCIC) underground suction

~

and return piping.

That notification was made in accordance with 10 CFR 50.55(e).

This letter fulfills the 30-day reporting requirement of that regulation.

Preservice inspection and a hydrostatic test indicated that a leak was present at the cycled condensate (CY) tank and in the underground portion of the line east of the o ff gas building for the Unit II suction line.

Apparently a schedule mismatch between the fittings and pipe and resulting welding difficulties caused sensiti-zation of the weld heat affected zones.

Although the Unit I lines have successfully passed the required tests, concerns over possible weld cracking of pipe under-ground with resulting leakage causing gr,ound contamination, has led t

to the decision to abandon the lines in Unit I and II.

Replacement pipe and fittings will be of the same schedule (schedule 40),

eliminating the welding problem.

The Unit I lines will be utilized until after the replacement is completed af ter Unit I fuel load.

Baseline ' inspection of the remaining RCIC system and other stainless steel lines have shown that similar problems do not exist in other areas of the piping systems.

g2gp#o$

Te.17 s

tJAN 2 9 se g

.a. *

)

J. G. Keppler Janua ry ~ 2 5, 1982

.The Unit I replacement piping will be completed by July 1982 and the' Unit II replacement piping by fue1L load on Unit' II.

If-there are any further questions in this regard, please-contact'this office.

7 Very truly yours,-

(E5E!

1 C. E.

Sargent Nuclear Licensing Administrator CES/Im cc: