ML20040B726

From kanterella
Jump to navigation Jump to search
Requests That Guard Training & Qualification Plan Approved by NRC for Unit 2 Be Included by Ref in Application for OL for Units 1 & 4
ML20040B726
Person / Time
Site: Washington Public Power Supply System
Issue date: 01/15/1982
From: Bouchey G
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: Adensam E
Office of Nuclear Reactor Regulation
References
GO-1-82-0019, GO-1-82-19, NUDOCS 8201260359
Download: ML20040B726 (2)


Text

_

Washington Public Power Supply System P.O. Box 968 3000 GeorgeWashington Way Richland, Washington 99352 (509)372-5000 Docket No. 50-460 50-513 G

Q (9

[y G0-1-82-0019 I

- 2519BF:q January 15, 1982

'g-

,. 5m,

~

agg,g I

e Ms. E. Adensam, Chief A

g Licensing Branch No. 4 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D. C.

20555

Dear Ms. Adensam:

Subject:

NUCLEAR PROJECTS NOS. 1 AND 4

'iUARD TRAINING AND QUALIFICATION PLAN

Reference:

Letter R. L. Tedesco NRC to R. L Ferguson -

WNP-2 Guard Training and Qualification Plan, dated August 5, 1981 The Supply System Guard Training and Qualification Plan has been submitted to and approved by the NRC (reference) in conjunction with the Operating License Application for WNP-2 (Docket No. 50-397).

Because the training tasks outlined in the WNP-2 Guard Training and Qualification Plan are identical to the tasks being performed at WNP-1 and 4, it is requested that the WNP-2 Guard Training and Qualification Plan be included by reference in the WNP-1/4 Operating License Application.

The Guard Training and Qualification Plan which has been reviewed and approved by the NRC for WNP-2 is being applied generally to WNP-1, 2 and 4 since the security officers and supervisors are:

(a) members of the same organization under the control of one manager, (b) interchange job assignments at all three projects, and (c) perform duties on the same security systems and equipment at each plant.

8$

8201260359 820115 PDR ADOCK 05000460 tl 1@

i F

PDR i

\\

/

Ms. E. Adensam January 15, 1982 Page 2 WNP-l/4 - Guard Training & Qualification Plan Since the training tasks, conditions and standards are identical and the training programs the scme, the Supply System is committed to a consolidated Guard Training and Qualification Plan for our three nuclear projects (1, 2 and 4) located on the Hanford Reservation.

All subsequent changes to the Guard Training and Qualification Plan 1

shall reflect changes for nuclear projects 1, 2 and 4.

Very truly yours, G. D. Bouchey, Depu y Director Safety & Security RJG/sm