. _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
IN RESPONSE REFER 'IO M811216A '
-[
^g UNITED STATES j' 4 )
g NUCLEAR REGULATORY COMMISSION o
n
(
WASHIN GTON,0.C. 20555 O
O
/e:l Decenber 18, 1981
.....o
+
p s
c i
2 2
Lg a
p -
OFFICE OF THE t
SECRETARY
.\\
n g
MEMORAMXM EDR:
Isonard Bickwit, Jr., Gener Counsel
~
FRN:
Samuel J. Chilk, f
s SUBJECI:
STAFF REQUIREMENTS - ORAL /PpSENTATIONS A10 POSSIBLE VorE ON CLINCH RIVER BatzuEQREACIOR,10:30 A.M.,
WEDNESDAY, DECEMBER 16,1981, CDM4ISSIONERS' COtFEREtCE i'
BOCM, DC CFFICE (OPEN 'IO PUBLIC ATTEt0ANCE)
The Ccmnission heard presentations frczn the following parties to the Clinch River Breeder Reactor Pr M hg:
Applicants:
George Edgar, Attorney, Project Managenent Corporation Ihan Silverstrczn, Asst. General Cbunsel, Department of Energy Iawis E. Wal1re, -Deputy General Counsel, Tennessee Valley Authority State of 'Ibnnessee:
Ted Von Cannon, Assistant Ocrznissioner, Department of Econcznic Ccurmunity Developnent Iee Breckenridge, Attorney, Office of the Attorney General Intervenors:
Eldon Greenburg, Attorney, NRDC and Sierra Club Rarhara Financre, Attorney, NRDC Jacob Sherr, Attorney, NBDC The Ocxtmission agreed ht the Comnission, rather than the staff or an adjudicatory board, would make the decision on the Department of Energy's exsuption request. The Ocmnission also agreed that the Ocnnission would proceal.in the matter with the ccathined assistance of the staff, OPE and OGC.
The Ccmnission discussed the schedule of events required for a decision in this matter; although the Ocmnist '..) did not reach a final decision, it agreed to issue an Order on or about Dmmh=r 23, 1981, inviting ccmnents and requesting answers to questions, with responses due January 23, 1982. The General Counsel was requested to advise on legal aspects of the procedure.
(OGC) (SECY SUSPENSE:
12/21/81)
The Chairman, working with staff, will prepare and circulate further schedule proposals and alternate options.
cc: Chairman Palladino Ocmnissioner Gilinsky Ccanissioner Bradford Camnissioner Ahearne I
Ccunissioner Roberts Omnission Staff Offices.
EDO s
PDR (Mvance Copy) y-016 (Phillips) 8201050447 811218 PDR 10CFR PT9.7 PDR.