Northern States Power Company 414 NicoHet Malt Minneapohs, Mennesota 55401 Telephone (612) 330-5500 10 December 29, 1981 e
RECEIVED 1
2-JAN5 1982> 7 Director Of fice of Nuclear Reactor Regulation I!scarr.#Er m '
Attn: Document Control Desk
\\
D EATJO H U S Nuclear Regulatory Commission Washington, DC 20555 PRAIRIE ISLAND NUCLEAR GENERATING PLANT
-n-Docket Nos. 282 License No. DPR-42 306 DPR-60 Items II.K.3.30, NUREG-0737 Re fe rences :
1.
Letter Rahe (Westinghouse) to Eisenhut (NRC) dated November 25,1981, (Letter number W NS-EPR 2524) 2.
Letter G Owsley (Exxon) to Eisenhut (NRC) dated November 23, 1981 (subject: Exxon Nuclear PWR Small Break LOCA Evaluation Model)
Mr Eisenhut's October 31, 1980 letter, containing NUREG-0737, requested a response to item II.K.3.30, Revised Small-Break Loss-of-Coolant-Accident Methods To Show Compliance with 10 CFR Part 50, Appendix K by January 1, 1982. Currently using Exxon and Westinghouse fuel, we have identified that both vendors will not have completed their review of their small-break loss-of-coolant-accident methods by January 1, 1982 Westinghouse plans to complete their review of this concern by April 1, 1982 (Reference 1);
Exxon plans to complete their review by June 30, 1982 (Reference 2).
We request a change in schedule for itet II.K.3.30 to July 30, 1982 to allow time for Westinghouse and Exxon to complete their reviews.
h.
L G Mayer, PE Manager of Nuclear Support Services LOM/TMP/bd cc: Regional Administrator-III, NRC NRR Project Manager NRC NRC Resident Inspector G Charnoff