ILLINDIS POWER COA 1PANY
~
U-0394 l g{,
739_g3z32_23y_g 500 SOUTH 27TH STREFr DECATUR, ILUNOIS 62525 December 21, 1981 ashb
/V y+
b Mr. James R. Miller, Chief d
' N.h'ED OE Standardization & Special Projects Branch O c: w"C80 7981A Division of Licensing E"]"mg }
Office of Nuclear Reactor Regulation j
4-Mi U.S. Nuclear Regulatory Commission 2
Washington, D.C.
20555
('
4$
T\\
Dear Mr. Miller:
'0' Clinton Power Station Unit 1 Docket No. 50-461
Reference:
Letter R. L. Tedesco (NRC) to G. E. Wuller (IP);
subj ect :
Long Term Operability of Deep Draft Pumps, November 23, 1981; Docket No. 50-461 The reference letter requested a schedule for a supplement to FSAR Section 3.9.3 to describe a program to assure long-term operability of deep draft pumps.
It included a very extensive recommended program as an attachment.
The requested information will be provided in an CPC-FSAR Amendment by June 1982.
Sincerely, 7
l-G. E. Wuller Supervisor-Licensing Nuclear Station Engineering s PEW /lt cc:
J. H. Williams, NRC Clinton Proj ect Manager H. H. Livermore, NRC Resident Inspector