Notifies That Schedule for Suppl to FSAR Section 3.9.3, Describing Program to Assure long-term Operability of Deep Draft Pumps,Will Be Submitted in Amend by June 1982,per 811123 Request
ML20039C395
Person / Time
Site: Clinton Constellation icon.png
Issue date: 12/21/1981
From: Wuller G
ILLINOIS POWER CO.
To: John Miller
Office of Nuclear Reactor Regulation
References
U-0394, U-394, NUDOCS 8112290307
Download: ML20039C395 (1)


Text

ILLINDIS POWER COA 1PANY

~

U-0394 l g{,

739_g3z32_23y_g 500 SOUTH 27TH STREFr DECATUR, ILUNOIS 62525 December 21, 1981 ashb

/V y+

b Mr. James R. Miller, Chief d

' N.h'ED OE Standardization & Special Projects Branch O c: w"C80 7981A Division of Licensing E"]"mg }

Office of Nuclear Reactor Regulation j

4-Mi U.S. Nuclear Regulatory Commission 2

Washington, D.C.

20555

('

4$

T\\

Dear Mr. Miller:

'0' Clinton Power Station Unit 1 Docket No. 50-461

Reference:

Letter R. L. Tedesco (NRC) to G. E. Wuller (IP);

subj ect :

Long Term Operability of Deep Draft Pumps, November 23, 1981; Docket No. 50-461 The reference letter requested a schedule for a supplement to FSAR Section 3.9.3 to describe a program to assure long-term operability of deep draft pumps.

It included a very extensive recommended program as an attachment.

The requested information will be provided in an CPC-FSAR Amendment by June 1982.

Sincerely, 7

l-G. E. Wuller Supervisor-Licensing Nuclear Station Engineering s PEW /lt cc:

J. H. Williams, NRC Clinton Proj ect Manager H. H. Livermore, NRC Resident Inspector

?>oo I S

IU 8112290307 811221 PDR ADOCK 05000461 A