Responds to NRC Re Violations Noted in IE Insp Repts 50-254/81-14 & 50-265/81-14.Corrective Actions Withheld (Ref 10CFR2.790)
ML20038B148
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 10/26/1981
From: Delgeorge L
COMMONWEALTH EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML20038B142 List:
References
NUDOCS 8111240774
Download: ML20038B148 (1)


Text

..

ka.e.k m t a]- 10 CFR 2.790 I [ X Commonwealth Edison M ggpgg BLIG DISCLOSURE .I ~ ) One First National Plaza. Chicago, Ilknois a ~7 Address Reply to: Post Othee Box 767 (j Chicago, libnois 60690 October 26, 1981 Mr. James G. Keppler, Director Directorate of Inspection and Enforcement - Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137

Subject:

Quad Cities Station Units 1 and 2 Response to I.E. Inspection Report Nos. 50-254/81-14 and 50-265/81-14 NRC Docket Nos. 50-254/265 Reference (a): R. L. Spessard letter to Cordell Reed dated October 1, 1981.

Dear Mr. Keppler:

The following is in response to concerns identified in the Subject inspection conducted by Messrs. N. J. Chrissotimos and S. G. DuPont on August 5 through September 4, 1981, of activities at Quad Cities Nuclear Power Station. Reference (a) ioentified one item of noncompliance. The Attachment to this letter contains the Common-wealth Edison Company response to this item. This attachment contains information concerning the security plan for a nuclear generating station and should be withheld from public disclosure in accordance with Section 2.790 of 10 CFR Part 2. Please address any questions you may have concerning this matter to this o f fice. Very truly yours, ^& L. O. DelGeorg Director of Nuclear Licensing Attachment Im SUBSCRIBED AND SWORN to of J 198. @#0.10 Comm N Q g gt. ) INDUSTR 8 S R DATA ~' Notary Public I 2750N 8111240774 811119 DR ADOCK 05000 y OCT 3 0 1981}}