Metropolitan Edison Company Post Office Box 480 Middletown, Pennsylvania 17057 Writer's Direct Dial Numtar November 18, 1981 LL2-81-0269 f][b>f,k TMI Program Office Attn:
Dr. B. J. Snyder, Program Director d
~ /
I i
U. S. Nticlear Regulatory Commission Washington, D.C.
20555 e9 A
U A'Oy0 hh 8
Dear Sir.
S ~
0,,'
IS8lg
?
Three Mile Island Nuclear Station, Unit 2 (TMI-2)
%'Qtr[?
Operating License No. DPR-73
,A Docket No. 50-320
/
s
/Ih_h.
Safety and Radiological Evaluation of the r
Containment Building Decontamination Experiment Enclosed for your approval is the Safety and Radiological Evaluation of the Containment Building Decontamination Experiment. This document represents the radiological and safety evaluation of activities to be performed in the containment as given in the TMI-2 " Containment Building Decontamination Experiment Purpose and Scope of Work" transmitted to you on October 30, 1981.
Included are evaluations of the following:
a) Effluents to the environment.
b) Occupational exposures.
c) Radioactive waste management.
d) Safety evaluation (10CFR50.59).
Based upon these evaluations CPU concludes that:
1.
Offsite releases and dose.: for the decontamination experiment are well within the bounds of the 'l 11-2 Technical Specification limits, even making very conservative assumptions and incor..,-
e rating a larger scope of activities than the deconta.nination experiment.
2.
Occupational exposures to perform the decontamination experiment are consistent with ALARA considerations.
O[
I 3.
The decontamination experiment does not constitute an unreviewed safety question as defined by 10CFR50.59.
Accordingly, we request that you approve the Radiological and Safety Evaluation, as well as the Scope, and authorize performance of the n111240347 811110 PDH ADOCK 05000320 P
PDR Metropotran Edman Company e a Member of the General Pubhc Utdities System
Dr. B. J. Snyder LL2-81-0269 Decontamination Experiment upon your verification that requisite admin-istrative controls are in place.
Si f'ere k_
- 4. '
on r.
I-2 JJB:JEL:djb Enclosure cc' L. H. Barrett, Deputy Program Director
.