Forwards Summary of 930405 Meeting Re Status of Actions to Identify Items &/Or Programs to Be Corrected Prior to Restart of Units.List of Attendees & Handouts Also Encl
ML20036B159
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 05/04/1993
From: Gibson A
NRC Office of Inspection & Enforcement (IE Region II)
To: Medford M
Tennessee Valley Authority
References
NUDOCS 9305180228
Download: ML20036B159 (7)


Text

May 4, 1993 Docket Nos. 50-327, 50-328 License Nos. DPR-77, DPR-79 Tennessee Valley Authority ATTN: Dr. Mark 0. Medford, Vice President Technical Support 3B Lockout Place 1101 Market Street Chattancoga, Tennessee 3740?-2801 Gentlemen:

SUBJECT:

MEETING

SUMMARY

-SEQUOYAH RESTART ISSUES This refers to the meeting conducted at our request at the Sequoyah Nuclear Power Plant on April 5, 1993. The purpose of the meeting was for you to present to the NRC Restart Panel the status of your actions to identify items and/or programs to be corrected prior to restart of the Sequoyah Units.

A list of attendees, a meeting summary and a copy of your handouts are enclosed.

l It i.s our opinion that this meeting was beneficial to us in aiding our understanding of the actions that you are taking to prepare the Sequoyah Units for restart.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, i

Title 10, Code of Federal Regulations, a copy of this letter and its I

enclosures will be placed in the NRC Public Document Room.

l Should you have any questions concerning this matter, please contact us.

l l

Sincerely, (0RIGINAL SIGNED BY A. F. GIBSON) l l

l Albert F. Gibson, Director Division of Reactor Safety l

Enclosures:

1. List of Attendees i
2. Meeting Summary
3. License Handouts cc w/encls: (See page 2) 9305180228 930504 g

DR ADOCK 0500 7

1 1~EO/

m

Tennessee Valley Authority 2

May 4, 1993 cc w/encls:

Mr. John B. Waters, Director Mr. M. J. Burzynski, Manager Tennessee Valley Authority Nuclear Licensing and ET I?.A Regulatory Affairs 1

400 West Summit Hill Drive Tennessee Valley Authority Knoxville, TN 37902 5B Lookout Place Chattanooga, Tennessee 37402-2801 TVA Representative Tennessee Valley Authority Rockville Office Mr. Michael H. Mobley, Director 11921 Rockville Pike Division of Radiological Health Suite 402 T.E.R.R.A. Building 6th Floor Rockville, MD 20852 150 9th Avenue North Nashville, TN 37219-5404 General Counsel Tennessee Valley Authority County Judge ET llH Hamilton County Courthouse 400 West Summit Hill Drive Chattanooga, TN 37402 Knoxville, TN 37902 bcc w/encls:

(See page 3)

Mr. J. R. Bynum, Vice President Nuclear Operations Tennessee Valley Authority i

3B Lookout Place 101 Market Street l

1 Chattanooga, TN 37402-2801 4

Ms. Marci Cooper, Site Licensing Manager Sequoyah Nuclear Plant

~

Tennessee Valley Authority P. O. Box 2000 i

Soddy-Daisy, TN 37379 t

Mr. Robert Fenech, Vice President Sequoyah Nuclear Plant Tennessee Valley Authority P.-0. Box 2000 Soddy-Daisy, TN 37379 l

l 1

f l

~

- - - - - - a

F Tennessee Valley Authority 3

May 4, 1993 r

bcc w/encis:

J. R. Johnson, RII G. C. Lainas, NRR F. J. Hebdon, NRR j

P. J. Kellogg, RII J. L. Mathis, RII D. E. Labarge, NRR NRC Document Control Desk NRC Senior Resident Inspector r

U.S. Nuclear Regulatory Commission 2600 Igou Ferry Soddy-Daisy, TN 37379 l

t

.i i

i i

i i

i E

r RII DP i

i PKellogg i

5/j)/93 5

6

l I

I ENCLOSURE 1 LIST OF ATTENDEES I

NRC A. F. Gibson, Director, Division of Reactor Safety, Region II (RII)

P. J. Kellogg, Chief, Reactor Projects Section 4A, Division of Reactor Projects (DRP), RII W. E. Holland, Senior Resident Inspector, DRP, RII l

S. M. Shaeffer, Resident Inspector, DRP, RII D. E. LaBarge, Senior Project Manager, Office of Nuclear Reactor Regulation I

(NRR)

V. Nerses, Acting Director, Project Directorate II-4, NRR j

e TVA J. R. Bynum, Vice President, Nuclear Operations M. O. Medford, Vice President, Technical Support R. A. Fenech, Vice President, Sequoyah R. J. Beecken, Plant Manager J. S. Baumstark, Operations Manager

[

N.13elsh, Operations Superintendent M. A. Cooper, Site Licensing Manager J. P. Maciejewski, Quality Assurance Manager T. A. Flippo, Site Quality Manager

!'i P. G. Trudel, Engineering Manager J. N. Ward, Engineering and Modifications Manager D. L. Lundy, Technical Support Manager

[

T. McGrath, chairman, Nuclear Safety Review Board M. Starzinski, Manager Technical Programs I

r l

i r

l l

  • t

- w

MEETING

SUMMARY

The initial meeting of the Sequoyah Restart Review Panel was called to order by the Chairman Mr. A.F. Gibson. Mr. Gibson then presented an outline for the meeting. The purpose of the meeting was to develop a draft restart Action Plan, a draft Restart Checklist, and draft inspection charters.

The Panel then commenced a review of the checklists contained in NRC Manual Chapter (MC) 0350. The decision was made to utilize those items from the generic checklist of MC 0350 and create a site specific checklist.

An overview of the Augmented Inspection (AIT) team findings was presented by Mr. J. J. Blake, the AIT Team Leader. The root causes of the failure of the erosion / corrosion program were identified to be failure of management to clearly assign responsibilities and provide appropriate oversight and direction for monitoring and maintaining balance of plant piping. Mr. Blake indicated that TVA had missed several opportunities to identify the degraded piping and the CHECKMATE program which was intended to predict piping degradation was not effective because of implementation deficiencies.

The Panel then established a generic inspection outline for each inspection to be conducted prior restart.

The generic outline consisted of an inspection charter, a mission statement, proposed dates for the inspections and the inspection leader.

)

The Panel then attended a meeting with TVA to ascertain the actions that TVA thought would be necessary to complete prior to restart.

The agenda of this meeting is attached as well as TVA's handout concerning the development of restart items.

f i

l J

4 I

==-. - ~.~.

I I

AGENDA NRC/ SON RESTART WORKING MEETING

{

APRIL 5, 1993 l

i OPENING STATEMENTS R.

FENECH 10-15 MIN._

- MEETING PURPOSE /

OBJECTIVE t

1 CONFIRMATORY ACTION LETTER J. WARD 1 HR.

t I

ISSUES

- Problem Statements

[

- Root Causes Corrective Actions f

- Status 1

TECHNICAL PROGRAMS MARCI COOPER /

1HR.

- Team Reviews TOM McGRATH/

- Review Methodology M.

SKARZINSKI

- Results To Date

- Ongoing Activities

- Technical Program organization Impl.

- Assessments l

t

]

RESTART EVALUATIONS / KEY R.

FENECH 1 HR.

SITE ACTIVITIES

- Restart Evaluation Philosophy & Process

- Key site activities l

  • Eqpt
  • BOP DENNIS LUNDY Backlog P. TRUDEL
  • Personnel Perf./

J.BAUMSTARK Process / Procedure i

l ASSESSMENTS R.

FENECH 30 MIN.

j

- Independent

{

- QA-T.

FLIPPO SCHEDULE STATUS /

R.

FENECH 15 MIN.

j LONGER TERM POST RESTART t

EFFORTS i

CPEN DISCUSSION ALL 30 MIN.

REGULATORY ACTIONS LEADING MARCI COOPER /NRC 20 MIN.

TO RESTART MEETING

SUMMARY

R.

FENECH 10 MIN.

E/C PROGRAM REVIEW LARGE BORE PIPING EVALUATION-tNSP/MODEUNG/R&RS SMALL BORE UPGRADED PROGRAM LOW TEMP OV EVALUATION & TESTING RESULTS lMPACT ON OTHER EQPT EVENT RESPONSE ROOT CAUSE CAL ISSUES r'

y TECH PROGRAM g

REVtEWS

____._____________4 f

NUCLEAR SAFETY OPER. IMPACT SIP r

HARDWARE REL! ABILITY INPO y

PROGRAM ADEQUACY PERSONNEL PERFORMANCE MGMNT _

^

REVIEWS ITERATIVE " SCRUB" Y

f NSRB PREllM E ART EMPLOYE

\\r

^

^

FEEDBACK UST A

gg

\\

p

\\

KEUTER HARDWARE g

PROGRAM / PROCESS g OPS PERFORMANCE g

BACKLOG 1

m BACKLOG REDUCTION

^

REVIEWS DEPARTNENT

^

LONGER TERM QA y

SHORT &

POST RESTART LONG TERM I

(SIP)

SYSTEM-DESIGN REVIEWS SALP

.