-/4,,.%'o UNITED STATES
)
NUCLEAR REGULATORY COMMISSION o
(
WASHINGTON, D. C. 20555 l
t FEB L s
%..+
Applied Management Systems, Inc.
ATTN: Margaret Hutchinson 6116 Executive Boulevard - Suite 440 Rockville, Maryland 20852
Dear Ms. Hutchinson:
Subject:
Modification No. 4 to Task Order No. 01 Under Contract No. NRC-33-92-203 The purpose of this modification is to: 1) add travel to the NRC Regional Offices in accordance with the attached statement of work, 2) increase the contract ceiling amount, and 3) delete Alan Dolleck as Task Manager for this task order and designate John Burton as the new Task Manager.
Travel shall-be performed in accordance with the contractor's revised cost proposal dated February 1,1993 which is hereby incorporated into the task order by reference.
The ceiling amount of this task order is increased by $12,654.46 from
$239,383.82 to $252,038.28. The amount of $242,344.50 represents the reimbursable cost and the amount of 59,693.78 represents.the fixed fee.
Your contacts for technical matters during the course of this task order are revised as follows-Technical Matters: John Burton Project Officer and Task Manager (301) 492-4836 All other terms and conditions of the subject task order remain unchanged.
Please indicate your acceptance of this Modification No. 4 to Task Order No 1 by having an official, authorized to bind your organ'zation, execute three copies of this document in the space provided and return two copies to the Contract Administrator. You should retain the' third. copy for your recordt.
A summary of obligations for this task order, from award date through the date of this action is given below:
Total FY 92 obligation $148,168.00
[
Total FY 93 obligation $ 91,000.00 s
Cumulative total of NRC obligations $239,168.00 l
I 9305120260 930204
[
w w
4 Contract No NRC-33-92-203 Modificaton No. 4 Task Order No. 1 Page 2 Task Order Summary
Title:
Project Management /Other Direct Costs Type:
Cost-Plus-Fixed-Fee Term:
8/3/92 - 7/31/93 Project Officer: John Burton Task Manager:
John Burton If you have ary questions regarding this matter, please contact Diana Clark, Contract Administrator on (301) 492-4286.
Sincerely, l
ca ry Jo at
, Centracting Office.
Contract Administration Branch No. 2 Division of Contracts and Property Management Office of Administration
Attachment:
As stated ACCEPTEDr-up/' '
/
,/b lsentLJ
>,5? x,x/~ ~'
NAME
./
)A4ucktaf TITLE JS
.3 DATE //
t r
4
-t
o, ENG DSURE 1 4
STA'HJerr OF WORK Modification No. 4 to Task Order No. 01 This Task Order shall include travel to each of the NRC Regional Offices as follows:
1.
Two contractor employees shall make on trip each to each regional office.
2.
Estimated length of each trip shall be three days.
i i
l I
_