Southern Naclear Operating Company
\\
Post O*fice Box 1295 Birminoham. Alabama 35201 l
Tek*p6cne 205 808 5006 a-Southern Nudear Operating Company y'y*;;
- he southem elec:nc sntem April 29, 1993 Docket Nos.
50-348 50-364 009604 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D. C.
20555 Joseph M. rarley Nuclear Plant 1992 Annual Environmental Operatina Report (Nonradioloaical)
Gentlemen:
Enclosed in accordance with Subsection 5.4.1 of the Joseph M. Farley Nuclear Plant Environmental Protection Plan (Units 1 & 2), Appendix B to Facility Operating License Nos. NPF-2 and NPF-8, is the report summarizing implementation of the Environmental Protection Plan during the calendar year 1992.
If you have any questions, please advise.
Respectfully submitted,
\\NydM 3.Woodard JDW/TCM:sls ENV-93-159
Enclosure:
1992 Annual Environmental Operating Report (Nonradiological) cc: (See next page.)
040118 ffh
- rmn neik 1
R
s-a O. S. Nuclear Regulatory Commission Page 2 cc:
Southern Nuclear Operatina Company R. D. Hill, Plant Manager U. S. Nuclear Reaulatory Commission. Washinoton, D. C.
T. A. Reed, Licensing Project Manager, NRR U.
S.' Nuclear Reaulatory Commission. Reaion II S. D. Ebneter, Regional Administrator G. F. Maxwell, Senior Resident Inspector 009604-
o i
SOUTHERN NUCLEAR OPERATING COMPANY JOSEPH M. FARLEY NUCLEAR PLANT - UNITS 1 AND 2 NRC DOCKET N05. 50-348 AND 50-364 FACILITY OPERATING LICENSE NOS. NPF-2 AND NPF-8 ANNUAL ENVIRONMENTAL OPERATING REPORT FOR 1992 (NONRADIOLOGICAL) i
)
f r
h i
l D
\\
s J
JOSEPH N. FARLEY NUCLEAR PLANT - UNITS 1 AND 2 ANNUAL ENVIRONMENTAL OPERATING REPORT FOR 1992 (NONRADIOLOGICAL) i INTRODUCTION In accordance with Subsection 5.4.1 of the Joseph M. Farley Nuclear Plant Environmental Protection Plan (Units 1 and 2), Appendix B to f acility Operating License Nos. NPF-2 and NPF-8, this report is submitted summarizing l
implementation of the Environmental Protection Plan for the calendar year 1992.
REPORTING REQUIREMENTS The following is submitted in accordance with Subsection 5.4.1 of the Environmental Protection Plan.
A.
ENVIRONMENTAL PROTECTION PLAN (EPP) NONCOMPLIANCES AND CORRECTIVE ACTIONS There were no EPP noncompliances during 1992.
B.
CHANGES IN STATION DESIGN OR OPERATION, TESTS, AND EXPERIMENTS MADE IN ACCORDANCE WITH EPP SUBSECTION 3.1 WHICH INVOLVED A POTENTIALLY SIGNIFICANT UNREVIEWEC ENVIRONMENTAL ISSUE t
There were no changes in station design or operation, tests, or experiments which involved a potentially significant unreeiewed environmental issue.
C.
NONROUTINE REPORTS SUBMITTED IN ACCORDANCE WITH EPP SUBSECTION 5.4.2 There were no nonroutine reports submitted during 1992.