Monthly Operating Repts for Mar 1993 for Calvert Cliffs Nuclear Power Plant,Units 1 & 2
ML20035F342
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 03/31/1993
From: Piazza F
BALTIMORE GAS & ELECTRIC CO.
To:
Shared Package
ML20035F339 List:
References
NUDOCS 9304210174
Download: ML20035F342 (10)


Text

-

oco*************************************************************************

UNIT 1 i

OPERATING DATA REPORT oco********************************4****************************************

Docket No. 50-317 April 13, 1993 Prepared by Frank Piazza Telephone:(410)260-3821 OPERATING STATUS

1. UNIT NAME Calvert Cliffs Unit 1
2. REPORTING PERIOD MARCH 1993 3.

LICENSED THERMAL POWER (MWT) 2700

4. NAMEPLATE RATING (GROSS MWe) 918
5. DESIGN ELECTRICAL RATING (NET MWe) 845
6. MAXIMUM DEPENDABLE CAP'Y (GROSS MWe) 860
7. MAXIMUM DEPENDABLE CAP'Y (NET MWe) 825 8.

CHANGE IN CAPACITY RATINGS NONE 9.

POWER LEVEL TO WHICH RESTRICTED N/A

10. REASONS FOR RESTRICTIONS N/A Cumulative This month Year-to-Date to Date
11. HOURS IN REPORTING PERIOD 744 2,160 156,901
12. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 2,160.0 110,510.0
13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 3,019.4
14. HOURS GENERATOR ON LINE 744.0 2,160.0 108,138.9
15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
16. GROSS THERMAL ENERGY GENERATED (MWH) 2,002,761 5,820,028 273,098,879
17. GROSS ELECTRICAL ENERGY GEN'TED(MWH) 677,997 1,962,801 90,790,335
18. NET ELECTRICAL ENERGY GENERATED (MWH) 651,683 1,886,240 86,355,626
19. UNIT SERVICE FACTOR 100.0 100.0 68.9
20. UNIT AVAILABILITY FACTOR 100.0 100.0 68.9
21. UNIT CAPACITY FACTOR (USING MDC NET) 106.2 105.8 66.7
22. UNIT CAPACITY FACTOR (USING DER NET) 103.7 103.3 65.1
23. UNIT FORCED OUTAGE RATE 0.0 0.0 9.1
24. SHUTDOWNS SCHEDULED OVER THE NEXT SIX MONTHS (TYPE, DATE AND DURATION):

Maintenance, October 1, 1993 for 18 days

25. IF SHUTDOWN _AT END OF REPORT PERIOD, ESTIMATED DATE OF START-UP:

N/A 9304210174 930413 PDR ADOCK 05000317 R

PDR j

UNITSilUTDOWNS AND POWER REDULTIONS DOCKET NO.

50-317 UNIT NAME Calvert Cliffs-U1 DATE April 13.1993 COMPLETED BY Frank Piar2a TELEPHONE (4101260-3821 REPORT MONTII March 1993 METilOD OF r

SillTI'nNG LICENSEE CAUSE & CORRECUVE DURATION DOWN EVTET SYSTEM COMPONENT AC110N TO NO.

DATE TYPEI (IIOURS)

REASON 2 REACTOR 3 REPORT #

CODE 4 CODES PREVENT RECURRENCE There were no significant power reductions this month.

IEkE5a idard 805-1984 1 F: Forced 2 Reason:

3 Method:

4 S: Scheduled A - Equipment Failure 1 - Manual B - Maintenance or Test 2 - Manual Scram.

C-Refueling 3 - Automatic Scram.

5 IEEE Standard 803A-1983 D - Regulatory Restriction 4 - Continued E - Operator Training & License Examination 5 - Reduced Load

. F-Administrative 9 - Other G - Operational Error H - Other

.. ~.

.. - ~...

I l

9 i

AVERAGE DAILY UNIT POWER LEVEL oce*********************************************************************

Docket No. 50-317 t

Calvert Cliffs Unit No. 1 April 13, 1993 Prepared by Frank Piazza Telephone: (410) 260-3821 MARCH 1993 Average Daily Power Level Average Daily Power Level Day (MWe-Net)

Day (MWe-Net) 1 873 17 878 2

874 18 878 i

t 3

873 19 878 4

873 20 876 5

874 21 877 6

873 22 878 7

874 23 879 r

8 873 24 880 9

873 25 879 10 871 26 877 I

11 873 27 878 12 873 28 878 e

13 875 29 879 14 876 30 879 15 877 31 880

{

16 877 I

)

P

.i DOCKET NO. 50-317 CALVERT CLIFFS - UNIT 1 April 13,1993

[

i

SUMMARY

OF OPERATING EXPERIENCE March 1993 The unit was at 100% all month.

i 0

i i

3 l

i l

I l

.l

April 5, 1993 REFUELING INFORMATION RE00ESI I

1.

Name of facility: Calvert Cliffs Nuclear Power Plant, Unit No.1.

2.

Scheduled date for next refueling shutdown: March 5, 1994.

3.

Scheduled date for restart following refueling:

None identified at this time.

4.

Will refueling or resumption of operation thereafter require a Technical Specification change or other license amendment?

None identified at this time.

5.

Scheduled date(s) for submitting proposed licensing action and supporting information.

December 1993 for UIC12.

6.

Important licensing considerations associated with the refueling.

None identified at this time.

7.

The number of fuel assemblies (a) in the core and (b) in the spent fuel storage pool.

(a) 217.

(b) 1627*.

Spent fuel pools are common to Units 1 and 2.

8.

(a) The present licensed spent fuel pool storage capacity, and (b) the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies.

(a) 4710. (NOTE 1)

(b)

O.

9.

The projected date of the last refueling that can be discharged to the Spent Fuel Pool assuming the present licensed capacity and maintaining space for one full core off-load.

March 2014 NOTE 1: 4710 total licensed site storage capacity.

(1830 pool + 2880 ISFSI)

  • Entry has changed since last reported.

i coo *************************************************************************

UNIT 2.

OPERATING DATA REPORT i

coo *************************************************************************

1 Docket No. 50-318 April 13, 1993 Prepared by Frank Piazza Telephone:(410)260-3821 1

OPERATING STATUS

1. UNIT NAME Calvert Cliffs Unit 2
2. REPORTING PERIOD MARCH 1993 3.

LICENSED THERMAL POWER (MWT) 2700

]

4. NAMEPLATE RATING (GROSS MWe) 911
5. DESIGN ELECTRICAL RATING (NET MWe) 845
6. MAXIMUM DEPENDABLE CAP'Y (GROSS MWe) 860 1

7.

MAXIMUM DEPENDABLE CAP'Y (NET MWe) 825 8.

CHANGE IN CAPACITY RATINGS NONE 9.

POWER LEVEL TO WHICH RESTRICTED N/A

10. REASONS FOR RESTRICTIONS N/A Cumulative This month Year-to-Date to Date
11. HOURS IN REPORTING PERIOD 744 2,160 140,256
12. NUMBER OF HOURS REACTOR WAS CRITICAL 0.0 1,203.6 101,168.0
13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 1,296.6
14. HOURS GENERATOR ON LINE 0.0 1,201.7 99,783.5
15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
16. GROSS THERMAL ENERGY GENERATED (MWH)

O_

3,222,124 254,366,916

17. GROSS ELECTRICAL ENERGY GEN'TED(MWH) 0 1,072,647 84,031,425
18. NET ELECTRICAL ENERGY GENERATED (MWH) 0 1,028,672 80,297,101
19. UNIT SERVICE FACTOR 0.0 55.6

'71.1

20. UNIT AVAILABILITY FACTOR 0.0 55.6 71.1
21. UNIT CAPACITY FACTOR (USING MDC NET) 0.0 57.7 69.4
22. UNIT CAPACITY FACTOR (USING DER NET) 0.0 56.4 67.8 i
23. UNIT FORCED OUTAGE RATE 0.0 0.0 5.9
24. SHUTDOWNS SCHEDULED OVER THE NEXT SIX MONTHS (TYPE, DATE AND DURATION):

N/A

25. IF UNIT IS SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START-UP:

June 4, 1993.

I i

P

UNIT S11UTDOWNS AND POWER REDUCTIONS

~

DOCKET NO.

50-318 UNIT NAME Calvert Cliffs-U2 DATE Ariril 13.1993 COMPLETED BY Frank Piazza TELEPHONE (410) 260-3821 REPORTMONTil March 1993 METilOD OF SIIITITINO LICENSEE CAUSE & CORRECTIVE DURATION DOWN EVENT SYS111M COMPONENT AC110N TO NO.

D A TTI TYPEI (IIOURS)

REASONI REACTOR 3 REPORT #

CODE 4 CODES PREVENT RECURRENCE 934d 930220 S

744.0 C

1 N/A N/A N/A Unit shutdown for planned Refueling Outage.

1 p. Forced 2 Reason:

3 Method:

4 IEEE L'tandard 805-1984 S: Scheduled A-Equipment Failure 1 - Manual B - Maintenance or Test 2 - Manual Scram.

C - Refueling 3 - Automatic Scram.

5 IEEE Standard 803A-1983 D - Regulatory Restriction 4 - Continued E - Operator Training & License Examination 5 - Reduced Load F-Administrative 9 - Other

' G - Operational Error H - Other.

... ~

AVERAGE DAILY UNIT POWER LEVEL oeo*********************************************************************

Docket No. 50-318 Calvert Cliffs Unit No. 2 April 13, 1993 Prepared by Frank Piazza Telephone: (410) 260-3821 MARCH 1993 Average Daily Power Level Average Daily Power Level Day (MWe-Net)

Day (MWe-Net) 1 0

17 0

2 0

18 0

3 0

19 0

4 0

20 0

5 0

21 0

6 0

22 0

7 0

23 0

8 0

24 0

9 0

25 0

10 0

26 0

11 0

27 0

12 0

28 0

13 0

29 0

14 0

30 0

15 0

31 0

16 0

._.=. -

)

r i

DOCKET NO. 50-318 CALVERT CLIFFS-UNIT 2 April 13,1993

{

?

SUMMARY

OF OPERATING EXPERIENCE j

March 1993 i

i The unit is shutdown for Refueling Outage. The following significant work was completed.

- 12 EDG was overhauled.

j

- Unit entered Mode 6 on 03/06S3.

- Unit core offload complete on 03/19S3.

l

- Saltwater header work started and is ongoing.

1 h

i s

?

~f 3

S l

l r

l l

r i

~

~

l April 5, 1993 REFUELING INFiAMATION RE0 VEST r

1.

Name of facility: Calvert Cliffs Nuclear Power Plant, Unit No. 2 2.

Scheduled date for next refueling shutdown: Currently in Refueling /Next Refuelireg, March 1995.

r 3.

Scheduled date for restart following refueling: June 4, 1993/ unknown.

4.

Will refueling or resumption of operation thereafter require a Technical Specification change or other license amendment?

No/ unknown.

t 5.

Scheduled date(s) for submitting proposed licensing action and supporting information, i

Hone required /anknown.

6.

Important licensing considerations associated with the refueling.

None identified at this time.

t 7.

The number of fuel assemblies (a) in the core and (b) in the spent fuel storage pool.

(a) 0*

(b) 1627*.

Spent fuel pools are common to Units 1 and 2.

8.

(a) The present licensed spent fuel pool storage capacity, and (b) the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies.

(a) 4710 (NOTE 1)

(b)

O.

9.

The projected date of the last refueling that can be discharged to the Spent fuel Pool assuming the present licensed capacity and maintaining space for one full core off-load.

March 2016.

NOTE 1: 4710 total licensed site storage capacity.

(1830 pool + 2880 13p31)

  • Entry has changed since last reported.