Text

-

/

  • /

UNITED STATES

'1 NUCLEAR REGULATORY COMMISSION

{

WASHINGTON, D. C. 20555

^

%s...../

m o3 s Science Applications International Corp.

Attention:

Mr. Thomas Rodehau, Deputy Contracts Manager 11251 Roger Bacon Drive Reston, VA 22090

Subject:

Task Order No. 20 entitled, " Technical Support for the Rulemaking for the Certificate of Compliance for Pacific Sierra Nuclear" Under Contract No. NRC-02-90-009 c

Dear Mr. Rodehau:

This confirms verbal authorization provided to your firm on December 2, 1992 to commence work under Task Order No. 20 on that date with a temporary ceiling of $8,000.00.

In accordance with the task order procedures of the subject contract, this letter definitizes Task Order No. 20.

This effort shall be performed in accordance with the enclosed statement of work, the Contractor's technical proposal dated January 20, 1993, and the following telephonic changes of February 3, 1993:

Decrease M&S Overhead from 2% to 1.8%

Decrease G&A from 10.3% to 10.2%

Reduce the total estimated cost of ETM Intercompany Work Order from $7,398.00 to $7,391.00 Reduce subcontractor costs from $8,652 to $8,574 Reduce the fixed fee from $3,943 (10%) to $2,829 (7.2%)

Based on the above changes, adjust the total proposed estimated cost plus fixed fee from $43,368 to $42,127.

ggg TaskOrderNo.20shallbeineffectfromDecember2,199/throughApril 30, 1993, with a cost ceiling of $42,127.00, inclusive of the amount authorized verbally.

The anount of $39,298.00 represents total estimated reimbursable costs, and the amount of $2,829.00 represents the fixed fee.

1 Accounting data for this task order is as follows:

B&R No.

350-19-401-100 Job Code:

J5003 Appropriation No.

31X0200 Amount Obligated: $42,127.00 The following individuals are considered to be essential to the successful performance of the work hereunder:

Mr. John Stokley, Dr. Thomas Albert, Mr. David Williamson, Mr. Aris Papadopoulus, Mr. Steven Mirsky, and Dr.

Daniel Prelewicz.

The Contractor agrees that such personnel shall not be removed from the effort under the task order without compliance with contract clause H.1, Key Personnel.

{

A "1 0 0 Q 3

[

9304080264 930205

]\\

{g,

PDR CONTR I

NRC-02-90-OO9 PDR

'o

Your contacts during the course of this task order are:

Technical Matters:

David Tiktinsky Project Officer Telephone:

(301) 492-2656 Contractual Matters:

Catherine Hiltner Contract Administrator Telephone: (301) 492-4291 The issuance of this task order does not amend any terms or conditions of the subject contract including the contract ceiling amount of $3,563,337.

Please indicate your acceptance of this task order by having an official authorized to bind your organization execute three copies of this document in the space provided and return two copies to the Contract Administrator.

You may retain the third copy for your records.

Sincerely, dig h

d<M Mary Lynn Scott, Contracting Officer Contract Administration Branch No. 1 Division of Contracts and Property Management Office of Administration

Enclosure:

As stated ACCEPTED:

chuW, h/tse y

Name Thomas J. Rodehau Title ue M y 7 nTrac W 6ager Energy Systems Group Date " ~L))A.LLLi 0

ISY r

tL4f/

~

j m

TASK ORDER 20, MODIFICATION 1

" FUEL CYCLE LICENSING TECHNICAL ASSISTANCE" TECHNICAL SUPPORT FOR THE RULEMAKING FOR THE CERTIFICATE OF COMPLIANCE FOR PACIFIC SIERRA NUCLEAR

1.0 Background

As a result of the CRGR meeting held on December 18, 1992 and a subsequent conference call with CRGR members, we have received substantial technical comments.

In parellel, we are also in the arocess of implementing the release the proprietary information used in the review process" decisiontoy'nerallicenseapplication.

for VSC-24 ge 2.0 Work Required Technical assistance is required from SAIC to assist the NRC in resolving the technical matters raised by CRGR.

In addition, SAIC will need to revise the Safety Evaluation Report (SER) to the Topical Report of 1991; the SER, Safety Analysis Report (SAR); and the Certificate of Compliance of May,1992 to incorporate all of the CRGR technical comments as well as revisions to release the relevant proprietary information used during the review.

The contractor will provide one project manager, and four technical support professionals who are familiar with the PSN application.

In addition on administrative support person is needed.

3.0 Schedule The reports for this task should be provided to NRC by March 31, 1993.

4.0 Task Reports The reports that need to be provided under this task are as follcws:

1) Revised SER to Topical report of 1991
2) Revised SER, SAR and Certificate of Compliance of May,1992.

5.0 Travel The travel that is anticipated for this task consists of 3 trips for 4 people (total of 12) to Rockville, Md..

All of this travel is expected to be local 6.0 NRC Furnished Material The NRC will provide the contractor copies of any CRGR technical comments.

7.0 Completion Date The completion date for this task should be extended from January 8, 1993 until April 30, 1993.

8.0 Level of Effort The estimated level of effort for this modification is 8 staff weeks.

.