Notification of 930413 Meeting W/Util in Rockville,Md to Discuss Design of Planned Power Line from Conowingo Hydroelectric Station to PBAPS for Purpose of Serving as Alternate Ac Power Source
ML20035C647
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 04/05/1993
From: James Shea
Office of Nuclear Reactor Regulation
To: Chris Miller
Office of Nuclear Reactor Regulation
References
NUDOCS 9304080240
Download: ML20035C647 (4)


Text

.

April 5, 1993 Docket Nos. 50-277 and 50-278 MEMORANDUM FOR:

Charles L. Miller, Director Project Directorate I-2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation FROM:

Joseph W. Shea, Project Manager Project Directorate I-2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation

SUBJECT:

PHILADELPHIA ELECTRIC COMPANY (PEco) MEETING WITH NRC STAFF ON PLANNED INSTALLATION OF DEDICATED POWER LINE FROM CONOWINGO HYDROELECTRIC STATION TO PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 DATE & TIME:

Tuesday, April 13, 1993 10:00 a.m.

I LOCATION:

One White Flint North 11555 Rockville Pike Rockville, Maryland Room IF-5 q

PURPOSE:

To discuss design of planned power line from Conowingo Hydroelectric Station to Peach Bottom for the purpose of serving as an Alternate AC power source.

PARTICIPANTS *:

NRC PEco A. Gill W. Mindick C. Thomas A. Jones C. Miller M. Kray J. Shea

/S/

Joseph W. Shea, Project Manager Project Directorate I-2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation cc:

See next page

  • Meetings between NRC technical staff and applicants or licensees are open for j

interested members of the public, petitioners, intervenors, or other parties to attend as observers pursuant to "Open Meeting Statement of NRC Staff Policy," 43 Federal Register 28056 6/28/78.

PDJ47/M PDI-2/PlV)

PDI-M OFFICE Mkbfk JShea:rh CMi N [

NAME DATE h/h93 t/ / 5/93 o V //ff93 0FFICIAL RECORD COPY DOCUMENT NAME:

PB4-13.MTG M D P O ? n ~P" '

~^

9304080240 930405 iLM' PDR ADOCK 05000277 60057

' {~ h\\

2 fg P

PDR

I, p* "ave

's

['-

UNITED STATES 3,"'

E NUCLEAR REGULATORY COMMISSION

[

WASHINGTON, D.C. 20555 s, w..... "d' April 5, 1993 Docket Nos. 50-277 and 50-278 MEMORANDUM FOR:

Charles L. Miller, Director Project Directorate I-2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation FROM:

Joseph W. Shea, Project Manager Project Directorate I-2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation

SUBJECT:

PHILADELPHIA ELECTRIC COMPANY (PEco) MEETING WITH NRC STAFF ON PLANNED INSTALLATION OF DEDICATED POWER LINE FROM CON 0WINGO HYDROELECTRIC STATION TO PEACH BOTTOM ATOMIC POWER i

STATION, UNITS 2 AND 3 I

DATE & TIME:

Tuesday, April 13, 1993 10:00 a.m.

LOCATION:

One White Flint North 11555 Rockville Pike Rockville, Maryland Room IF-5 PURPOSE:

To discuss design of planned power line from Conowingo Hydroelectric Station to Peach Bottom for the purpose of serving as an Alternate AC power source.

PARTICIPANTS *-

NRC PECo A. Gill W. Mindick C. Thomas A. Jones C. Miller M. Kray.

J. Shea l

l o

i

~ N

-(, ;Q k osep,!W.Shea,ProjectManager i

Project Directorate I-2 l

Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation l

cc:

See next page r

  • Meetings between NRC technical staff and applicants or licensees are open for interested members of the public, petitioners, intervenors, or other parties to attend as observers pursuant to "Open Meeting Statement of NRC Staff Policy," 43 Federal Reaister 28058, 6/28/78.

r.

~

Philadelphia' Electric Company Peach Bottom Atomic Power Station, Units 2 and 3 cc:

J. W. Durham, Sr., Esquire Mr. William P. Dornsife, Director Sr. V.P. & General Counsel Bureau of Radiation Protection Philadelphia Electric Company Pennsylvania Department of 2301 Market Street, S26-1 Environmental Resources Philadelphia, Pennsylvania 19101 P. O. Box 2063 Harrisburg, Pennsylvania 17120 Philadelphia Electric Company ATTN: Mr. D. B. Miller, Vice President Boardlof Supervisors Peach Bottom Atomic Power Station Peach Bottom Township Route 1, Box 208 R. D. #1 Delta, Pennsylvania 17314 Delta, Pennsylvania 17314 Philadelphia Electric Company Public Service Commission of Maryland ATTN:

Regulatory Engineer, Al-25 Engineering Division Peach Bottom Atomic Power Station ATTN:

Chief Engineer Route 1, Box 208 231 E. Baltimore Street Delta, Pennsylvania 17314 Baltimore, MD 21202-3486 Resident Inspector Mr. Richard McLean U.S. Nuclear Regulatory Commission Power Plant and Environmental Peach Bottom Atomic Power Station Review Division P.O. Box 399 Department of Natural Resources Delta, Pennsylvania 17314 B-3, Tawes States Office Building Annapolis, Maryland 21401 Regional Administrator, Region i U.S. Nuclear Regulatory Commission Mr. George A. Hunger, Jr.

475 Allendale Road Director-Licensing, MC 52A-5 King of Prussia, Pennsylvania 19406 Philadelphia Electric Company Nuclear Group Headquarters Mr. Roland Fletcher Correspondence Control Desk Department of Environment P.O. Box No. 195 201 West Preston Street Wayne, Pennsylvania 19087-0195 Baltimore, Maryland 21201 Carl D. Schaefer External Operations - Nuclear Delmarva Power & Light Company P.O. Box 231 Wilmington, DE 19899 l

l l

1

DISTRIBUTIQH

! Docket' File NRC & Local PDRs PDI-2 Reading T. Murley/F. Miraglia J. Partlow S. Varga J. Calvo C. Miller J. Shea M. O'Brien A. Chaffee, OEAB 0GC E. Jordan, 3701 E. Rossi-Receptionist (0WFN)

A. Gill C. Thomas ACRS(10)

OPA NRR Mailroom, PMAS, 12/G/18 (must be handcarried)

P. O' Dell, PMAS (must be handcarried)

G. Zech, RPEB V. McCree, EDO E. Wenzinger, RGN-I C. Anderson, RGN-I J. Lyash, RI K. Abraham /D. Screnci, RGN-I J. Durr, RGN-I C. Berlinger cc:

Licensee & Service List 4

A a

-v -iA+.

1 P

.