m
{
C March 23, 1993 i
Docket No. 50-344 Mr. James E. Cross L
Vice President Nuclear Portland General Electric Company
- 121 S.- W. Salmon Street Portland, Oregon 97204 j
L
Dear Mr. Cross:
f
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION ON THE CERTIFIED FUEL HANDLER TRAINING AND RETRAINING PROGRAMS FOR THE TROJAN NUCLEAR POWER PLANT j
i By letter dated January 27, 1993, you submitted to the NRC staff for review l
'the Certified Fuel Handler Training and Retraining Programs for Trojan Nuclear Pl ant. 2e have determined that additional information or further clarifica-tion-on>a number of issues relative to this document is required. We request
~
that you respond to the list of questions contained in the enclosure.
Since j
our ieview must be completed before we can issue your license change application (LCA) 230, we request your response by the end of March 1993.
The reporting and/or recordkeeping requirements contained in this letter affect fewer than 10 respondents, therefore, OMB clearance is not required under P.L.96-511.
Sincerely, i
Original signed by:
.i Michael T. Masnik, Senior Project Manager
[
Non-Power Reactors and Decommissioning Project Directcrate
)
Division of Operating Reactor Support Office of Nuclear Reactor Regulation Enclosure-As stated
[
pp n e vw m..
t cc w/ enclosure:
lb4 b fa d b G db bu i See next page DISTRIBUTION:
I Docketfilei50f344' BGrimes RDudley ACRS (10) r PDRs SWeiss MMasrik Region V ONDD r/f EHylton 0GC JMelfi, RV LBell n
/
cpo t
'Ej%dfon 260068 MMasnik[.{f4 ON[)D:W ONDD:PM DNDD ONDI:D RDudley
,,,s,Sweiss 3/f}/93 3/22/93 3/n /93 J/n//2 3/24/93 0FFICIAL RECORD COPY
. DOCUMENT NAME: A: CROSS.MM (TROJAN Diskette)
{
-93C3290325 930323
[
l' PDR ADOCX 05000344 n
P-PDR
e
[>% MC L
'o UNITED STATES
~,
8 3,
j NUCLEAR REGULATORY COMMISSION y E W ASHINGT ON, D. C. 20555.
o March 23, 1993 Docket No. 50-344 Mr. James E. Cross Vice President Nuclear Portland General Electric Company 121 S. W. Salmon Street Portland, Oregon 97204
Dear Mr. Cross:
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION ON THE CERTIFIED FUEL HANDLER TRAINING AND RETRAINING PROGRAMS FOR THE TROJAN NUCLEAR POWER PLANT By letter dated January 27, 1993, you submitted to the NRC staff for review the Certified Fuel Handler Training and Retraining Programs for Trojan Nuclear Pl ant. We have determined that additional information or further clarifica-tion on a number of issues relative to this document is required. We request that you respond to the list of questions contained in the enclosure. Since our review must be completed before we can issue your license change application (LCA) 230, we request your response by the end of March 1993.
The reporting and/or recordieeping requiremei.ts contained in this letter affect fewer than 10 respondents, therefore, OMB clearance is not required under P.L.96-511.
Sincerely,
/,
<m a
// /
keh -
l c
Michael T. Masnik, Senior Project Manager i
Non-Power Reactors and Deconaissioning Project Directorate Division of Operating Reactor Support i
Office of Nuclear Reactor Regulation
Enclosure:
As stated cc w/ enclosure:
See next page i
J
Mr. James E. Cross Trojan Nuclear Plant Portland General Electric Company Docket No. 50-344 i
i cc:
Senior Resident Inspector U.S. Nuclear Regulatory Commission Trojan Nuclear Plant P. O. Box 250 Rainier, Oregon 97048 Mr. Michael J. Sykes, Chairman Board of County Commissioners l
Columbia County St. Helens, Oregon 97501 I
Mr. David Stewart-Smith Oregon Department of Energy Salem, Oregon 97310 Regional Administrator, Region V U.S. Nuclear Regulatory Commission 1450 Maria Lane, Suite 210 Walnut Creek, California 94595 l
J Mr. Tom Walt General Manager, Technical Functions l
Trojan Nuclear Plant 71760 Columbia River Highway j
Rainier, Oregon 97048 Mr. Lloyd K. Marbet 19142 S.E. Bakers Ferry Road Boring, Oregon 97009 l
}
Mr. Jerry Wilson i
j Do It Yourself Committee i
570 N.E. 53rd Hillsboro, Oregon 97124 l
Mr. Eugene Rosolie i
Northwest Environmental Advocates 302 Haseltine Building 133 S.W. 2nd Avenue i
Portland, Oregon 97204 5
i i
]
ENCLOSURE l
l 1
PORTLAND GENERAL ELECTRIC COMPANY f
. CERTIFIED FUEL HANDLER TRAINING AND RETRAINING PROGRAMS I
I 1
j The following information is requested to complete the review of the l
l Certified fuel Handler Training and Retraining Programs for the Portland General Electric Company's (PGE) Trojan Nuclear Power Plant.
l 1.
The Abstract states "The criteria upon which the program becomes effective j
are specified." Where are the criteria specified? What are the criteria?
l
)
l 2.
On page 1.0-1, " Introduction," PGE states that "The training of current l
holders of NRC Senior Reactor Operator and Reactor Operator licenses may fl be evaluated to determine if they satisfy the requirements of this j
I program." Why is the training of the SR0's being evaluated? SR0's should f
already be cualified to supervise fuel handling / movement evolutions. The R0 licenses must be evaluated to determine what, if any, additional l
training will be required before certification. Will the qualifications of the individual license holders be evaluated? Will any other PGE personnel be evaluated?
i i
i 3.
On page 1.0-2, reference is made to " Appropriate PGE management..." Who is this management? Can this management be delegated to other l
3 l
individuals?
l 4.
On pages 2.1-1 and 3.1-1, reference is made to " individual lecture" What is individual lecture?
l 5.
How much of the training described on pages 2.1-1 and 3.1-1 will be i
l lecture and how much will be self-study?
l i
I l
i l
i I
?
I
1 i
!) 4 4 '
1 i
l 6.
If the fundamentals listed on page 2.1-1 are those " typically" in the j
l fundamentals training program and given that using a SAT-based training program will allow adjustments to the program as appropriate for the 3
currer.t status, will any cf th: tcpics listed be considered part of a core l
program that all certified fuel handlers will receive?
li 7.
On page 2.2-1, reference is made to a period of on-shift watches under l
inst ruct i nn.
What is the rninimum numhar of on-shift watches required for j
qualification?
i i
8.
On page 2.3-1, " appropriate PGE management" is defined as the " General Manager, Trojan Plant." Can this authority be delegated? If so, to whom?
l 9.
On page 3.1-1, PGE states that the actual content of the retraining program shall be determined by appropriate PGE management.
Is the content of the retraining program determined and presented over a 24-month basis 1
or is the content determined and presented on a continuing basis? What is i
)
the basis for the actual content of the retraining program?
t J
10.
Section 3.2.2. " Missed Training." states that any missed training will be l
made up.
How long does an individual have to make up the missed training?
- 11. Section 3.2.2, " Missed Training," states that if missed training is not completed, the individual is suspended until completion of retraining.
i l
Does this remedial training require any additional qualification or watch l
standing?
- 12. The retraining program requires a comprehensive final examination. Will i
any examinations be administered during the retraining cycle to determine j
training deficiencies?
i i
k 1
i 1
i l
I
)
i i
f
..m.
..-.,,-n-.
_3_
- 13. Section 3.4.2, " Waiver of Maintenance of Qualification Requirements,"
states that an individual will not be exempted from the written examinations based on the fact that the individual helped in exam preparation. Daes this mean that exemptions can be granted for other reasons? If so, what are these reasons?
- 14. Section 4.0, " Program Evaluation," requires " routine assessments
- of the effectiveness and accuracy of trainina. How often will an assessment of i
the program be made?
- 15. Will the written examination be open reference or closed reference?
Will certified fuel handlers be evaluated in the area of integrated operations?
16.
What will the operating exam described in Appendix B evaluate? As Appendix B is currently written, it is not clear what the exam will do.
i
)
)
i 4
)
1 l
4 i
a 1
d 1
i
--