Text
a.
.[
j g,. -
sw Seabrook, N H 03874
- Telephone (603)474-9521
=
Jh
[
Facsimile (603)474 2987
. Energy Service Corporation Ted C. Feigenbaum Senior Vice President and Chief NuclearOfficer NYN-93039 March 12,1993 United States Nuclear Regulatory Commission Washington, DC 20555 Attention:
Document Control Desk
Reference:
Facility Operating License NPF-86, Docket No. 50-443
Subject:
Monthly Operating Report Gentlemen:
f Enclosed please find Monthly Operating Report 93-02. This report addresses'the operating and shutdown experience relating to Seabrook Station Unit 1 for the month of February,1993 and is submitted in accordance with the requirements of Seabrook Station Technical Specification 6.8.1.5.
t Very truly yours.
J Ted C. Feig. aum Enclosure (s)
I TCF:ALL/ tad cc:
Mr. Thomas T. Martin Regional Administrator United States Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406 Mr. Albert W. De Agazio, Sr. Project Manager.
Project Directorate 14 Division of Reactor Projects i
U.S. Nuclear Regulatory Commission i
Washington, DC-20555 j
Mr. Noel Dudley.
'f NRC Senior Resident inspector P.O. Box 1149 Seabrook, NH 03874 l
--m g
jh
.s 9303190140 930228 g a member of the Northeast Utilities system -
. U.,
PDR ADOCK.05000443 i
- N-
., R PDR
J;
.... _ 7..
.f l
7 b
North Atlantic March 12,1993 -
i 1
I f
I
'l J,
- f i
- r
- ENCLOSURE 1 TO NYN-93039 l
?
-.f-t f
5
.b r
iP tII
'.I i
e t
?
5
- t
(
.n.
' k
' +
I
.E t
g f
r
- ' ~ - - -
J
+ - - -
r"i--*
tY
t- :
l:
(.
OPERATING DATA REPORT'
~
'd
=
DOCKET NO. 50-443 l
UNIT Seabrook 1 DATE 03/12/93 l
COMPLETED BY P. E. Nardone I
TELEPHONE (603T 474-9521'
- j
}
Ext. 4074 OPERATING STATUS.
t 1.
Unit Name:
Seabrook Station Unit 1
]
2.
Reporting Period:
FEBRUARY 1993
~
3.
Licensed Thermal Power (MWt):
3411 4.
Nameplate Rating (Gross MWe):
1197 j
5.
Design Electrical Rating (Net MWe):.
1148
- 6. -Maximum Dependable Capacity (Gross MWe):
1200 i
(f 7.
Maximum Dependable Capacity (Net MWe):
1150
'E 8.
If Changes Occur in Capacity Ratings (Items Number.3 Through 7)
.. i Since Last Report, Give Reasons:
Not Applicable
.s i
9.
Power Level To Which Restricted If Any:
None j
10.
Reasons For Restrictions,- If Any:
Not Applicable t
.j F
This Month Yr.-to-Date Cumulative 4
- 11. Hours In Reporting Period 672.0' 1416.0 55849.0-i
+
- 12. Number Of Hours Reactor Was Critical 672.0 1262.7 20766.1-
- 13. Reactor Reserve Shutdown Hours 0.0' 10.0 953.3
- 14. Hours Generator On-Line 672.0 1243.6 18824.5
- 15. Unit ReserveLShutdown. Hours 0.0 0.0 0.0-
- 16. Gross Thermal Energy Generated (MWH) 2291849 4161956~
60685513
- 17. Gross Elec. Energy Generated (MWH).
805376'
.. 1458099
- 21019737 i
- 18. Net Electrical Energy Generated (MWH) 774612 1401226 20178038 019. Unit. Service-Factor 100.0 87.8' 78.7-
-}
~*20. Unit Availability Factor 100.0 87.8 78.7-i 021. Unit Capacity' Factor (Using MDC Net)~
100.2 86.0 75.0-
- 22. Unit Capacity Factor (Using DER Net) 100.4 86.2' 75.2~
023. Unit Forced Outage Rate 0.0' 12.2' 6.1 -
- 24. Shutdowns Scheduled Over Next 6 Months (Type..Date,'and_ Duration of;Each):
l None Scheduled l
- 25. If Shut _Down At End Of Report' Period. Estimated Date Of Startup :Not Applicable-t
- 1 1
mq ONOTE r. <* Cumulative" values based on-total hours starting. 08/19/90, date Regulari
-l Full Power Operation began.
- 1 1
a 1 of 4 I
o
-]
O
. i k
d IIbf ~
i J
AVERAGE DAILY UNIT POWER LEVEL j
- 1; l
DOCKET NO. 50-443-UNIT Seabrook 1 DATE"03/12/93 COMPLETED BY P. E. Nardone TELEPHONE (603) 474-9521
. Ext. 4074.
J
]
MONTH FEBRUARY. 1993 l
~ !
DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net)
-(MWe-Net):
.!.i 1
1153 17 1153 2
1153 18 1153 3
1153 19 1153 4
1154 20 1153 5
1154 21 1153 1
6 1150 22 1153 7
1152 23 1152 8
1152 24 1152 9
1152 25 1152 10
'1152
.26 1152 11 1152 27.
1152 12 1153 28 1152 13' 1154 114~
'1154
-15 1153 216 -
1154
~ INSTRUCTIONS on_this format.. list the average' daily unit power level:in MWe-Net for each day in; the reporting nonth. -compute'to the nearest.whole megawatt.
2 of_4-y
,sv-g u
y y
e g-
.e+h
-;y UNIT.SHUTDOWiiS AND POWER REDUCTIONS DOCKET'NO. 50-443
.~
_4 UNIT Seabrook 1-4 DATE 03/12/93 REPORT MONTH ~ ' FEBRUARY. 1993 COMPLETED BY. P. E. Nardone! : 4 TELEPHONE'(603) 474-9321-Ext.,4074
.No.
JDate Type -
Duration. Reason 2 Method of Licensee Cause & Corrective l
(Hours)-
Shutting Event Action to Down Reactor 3 Report i Prevent Recurrence Page 1 of 1 NO ENTRIES FOR THIS MONTH.
( 2 3.
~
'F:
' Forced
-Reasons.
Method:
~
S:'.
Scheduled'
- A-Equipment Failure.(Explain) 1-Manual-B-Maintenance oriTest Manual-Scram C-Refueling..
3-Automatic Scram DaRegulatory Restriction
~4-Continued from.
E-Operator Training'&-License' Examination
' previous month F-Administrative.
5-Power Reduction.
i G-Operational l Error.(Explain)
(DurationL=.0)
- H-Other~(Explain)
.9-Other-(Explain) l i'
. 3jof 4 4
waMk'd-mir M
TT4'ut tf1P w 5 4me- -
hM-t 4'WP 9ukn 'Eh TTMB n Y'FGTM V4 Pag gsy,ga 9*py.q q pi-'ep y-yy y-rriegi'~
pgfr
- y w*-y w-ry rve
'W t-~W ig-W PWW"'
rHbw erde4='
(DWW y's WW W its ree wS W w 'F -m i'W' e w n gavgag r
- 499493 awy.syim-.gsfr,&wg W w,
-y g q+ +g e. m g
-ryw.#eyt,-
pi
1 1
m
- \\
DOCKET NO. 501443:
UMIT-Seabrook 1
-1
-DATE.03/12/93 l
COMPLETED BY P.
E. Nardone TELEPHONE (603) 474-9521
-Ext. 4074-REFUELING INFORMATION REQUEST 2
- 1. Name of facility: Seabrook Unit 1
- 12. Scheduled date for next refueling shutdown:
l Refueling Outage 3, 03/26/94
- 3. Scheduled date for restart following refueling:
Refueling Outage 3, 05/20/94
'4. Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?
1
'1
<j No
+
- 5. Scheduled date(s) for submitting licensing action and supporting information:
I N/A
- 6. Important licensing considerations associated with refueling, e.g.,
new or different fuel design or supplier, unreviewed design or performance analysis methods, significant changes in fuel design, new operating procedures:
-~
None i
- 7. The number of' fuel assemblies (a) in the core and (b) in the spent fuel storage pool:
~
(a) In Core:
193
-(b) 136 l
- 8. The present licensed spent fuel pool storage capacity and the size of any increase-in licensed storage capacity-_that has been requestedior is: planned., in number of fuel assemblies:
l Present licensed capacity: 1236 No increase in storage capacity requested or planned.
.9.-The' projected.date of the:last refueling that can be discharged.to:
- the spent fuel pool assuming the present licensed capacity-Licensed capacity of 1236' fuel assemblies-based on two annual and' twelve?
eighteen-month refuelings with-full core offload capability.
The current' licensed capacity'is~ adequate until at least the; year 2010.'
t L
4 of 4-i