o UNITED STATES
~g A['4-rf p
WASHINGTON, D. C. 20555 8
NUCLEAR REGULATORY COMMISSION Q
n March 3, 1993 i
Docket No. 50-423 l
Mr. John F. Opeka Executive Vice President, Nuclear Connecticut Yankee Atomic Power Company Northeast Nuclear Energy Company 1
Post Office Box 270 i
Hartford, Connecticut 06141-0270 i
Dear Mr. Opeka:
\\
SUBJECT:
MILLSTONE NUCLEAR POWER STATION, UNIT 3 - REVIEW 0F FIRST-TEN-YEAR INTERVAL INSERVICE INSPECTION PROGRAM
SUMMARY
REPORT, REVISION 3 AND REQUEST FOR RELIEF
.s By letter dated October 30, 1991 Northeast Nuclear Energy Company (NNECO) l submitted the Millstone Nuclear Power Station, Unit 3, first 10-year interval inservice inspection (ISI) Program Summary Report, Revision 3.
This submittal
. l included requests for relief from ASME Section XI requirements that NNECO has determined to be impractical for its facility. As a result ~of a conference call on April 13, 1992, NNECO submitted additional information regarding the
[
first 10-year ISI program in a letter dated June 1,1992. The Millstone Nuclear Power Station, Unit 3, first 10-year ISI Program Summary Report, j
Revision 2 transmitted by letter dated May 4, 1989, was also used by the staff j
as a reference in this review.
j The NRC staff, with technical assistance from its Contractor, the Idaho National Engineering Laboratory, has reviewed and evaluated the information provided by NNECO in Revision 3 of the first 10-Year ISI Program Summary Report in support of the requests for relief. The staff concludes that the Millstone Nuclear Power Station, Unit 3, first 10-Year-ISI Program Summary J
Report, Revision 3 is unacceptable and not in compliance with-the regulations.
In order to become acceptable, volumetric examination _of 7.5 percent of the welds in the Class 2 Chemical and Volume Control System and High Pressure Safety Injection System should be included in the ISI program.
Regarding NNEC0's requests for relief, the, staff concludes that the requirements of the Code are impractical for certain requests for relief and that relief may be granted for Relief Requests IR-1, IR-2 (in part), IR-6, LIR-12'(in part), IR-13, and IR-18. Pursuant to 10'CFR 50.55a(a)(3)(1), the.-
proposed alternative described in Request-for Relief.IR-9 may be authorized..
Pursuant-to 50.55a(g)(6)(i) such relief is authorized by law and will'not endanger life, property, or the common defense and security, and is otherwise in the public-interest. The relief has been granted giving due consideration l
to the burden upon NNECO that could result if the requirements were imposed on the facility.
For Request for Relief IR-12,'the staff determined that relief I
was not required for the Feed Water System weld.
For Request for Relief _IR-2, j
the staff determined that relief is not required.for Weld #101-104D since 1
040027-l 9303090600 9303o3 h i h b d h fk k b b Y
PDR ADDCK 05000423 g g' l
G PDR l
h
+
Mr. John F. Opeka.-
essentially 100 percent of the weld was examined. Request for Relief IR-17 is denied based on NNECO's use of an out-of-date Code case. Request for Relief IR-15 is denied due to insufficient justification.
Request for Relief IR-16 was withdrawn by NNECO. The staff's evaluation and conclusions are contained in the enclosed Safety Evaluation.
Sincerely, Original signed by John F. Stolz, Director Project Directorate I-4 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation
Enclosure:
As stated cc w/ enclosure:
See next page Distribution:
Docket File EJordan NRC & Local PDRs GHill (2)
TMurley/FMiraglia OPA JPartlow OC/LFDCB ERossi VMcCree, EDO JLieberman LTDoerflein, RI SVarga TKMcLellan i
JCalvo JStolz l
SNorris VRooney OGC i
O A/!
/
o m ct LA:PDI-4 PM:PDI-4k D:bf=4 OGC M SINYi VRooney:cn JStob 8/ d bet
/
N N
2 //7/93' h/6/93
%/l[/93
,J2 /p493
//
OFFICIAL RECORD COPY Document Name:
G:\\R00NEY\\M82054.RLF
Mr. John F. Opeka Millstone Nuclear Power Station Northeast Nuclear Energy Company Unit 3 cc:
Gerald Garfield, Esquire R. M. Kacich, Director Day, Berry and Howard Nuclear Licensing Counselors at Law Northeast Utilities Service Company City Place Post Office Box 270 Hartford, Connecticut 06103-3499 Hartford, Connecticut 06141-0270 W. D. Romberg, Vice President D. O. Nordquist Nuclear, Operations Services Director of Quality Services Northeast Utilities Service Company Northeast Utilities Service Company Post Office Box 270 Post Office Box 270 Hartford, Connecticut 06141-0270 Hartford, Connecticut 06141-0270 Kevin McCarthy, Director Regional Administrator Radiation Control Unit Region I Department of Environmental Protection U.S. Nuclear Regulatory Commission State Office Building 475 Allendale Road Hartford, Connecticut 06106 King of Prussia, Pennsylvania 19406 Allan Johanson, Assistant Director First Selectmen Office of Policy and Management Town of Waterford Policy Development and Planning Division Hall of Records 80 Washington Street 200 Boston Post Road Hartford, Connecticut 06106 Waterford, Connecticut 06385 S. E. Scace, Nuclear Station Director P. D. Swetland, Resident Inspector Millstone Nuclear Power Station Millstone Nuclear Power Station Northeast Nuclear Energy Company c/o U.S. Nuclear Regulatory Commission Post Office Box 128 Post Office Box 513 Waterford, Connecticut 06385 Niantic, Connecticut 06357 C. H. Clement, Nuclear Unit Director M. R. Scully, Executive Director Millstone Unit No. 3 Connecticut Municipal Electric l
Northeast Nuclear Energy Company Energy Cooperative Post Office Box 128 30 Stott Avenue i
Waterford, Connecticut 06385 Norwich, Connecticut 06360 A