APPENDIX A l
Omaha Public Power District Docket:
50-285 Fort Calhoun Station License:
OPR-40 During an NRC inspection conducted January 16 through February 28, 1990, a violation of NRC requirements was identified.
In accordance with the " General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2, f
Appendix C (1989) (Enforcement Policy), the violation is listed below:
Failure to Take Corrective Actions f
Criterion XVI of Appendix B to 10 CFR Part 50 and Section A.17 of the licensee's approved QA Program. Updated Safety Analysis Report, require that measures be established to assure that conditions adverse to quality be promptly identified and corrected.
Contrary to the above, the corrective measures initiated by the licensee i
failed to:
1.
Identify in Safety Analysis for Operability 89-10 the potential for degradation of the raw water (RW) pump discharge check valves that could have resulted in the operation of the RW system outside of its design basis following the failure of the RW Pump AC-10A discharge check valve (Valve RW-125) on June 24, 1989, i
2.
Provide for backflow testing of the RW pump discharge check valves to determine that further degradation had not occurred from the first quarter of January 1989 until January 1990.
l l
This is a Severity Level IV violation.
(Supplement I) (285/9002-04)
Pursuant to the provisions of 10 CFR Part 2.201, the Omaha Public Power District is hereby required to submit to this of fice, within 30 days of the date of the letter transmitting this Notice, a written statement or explanation in reply, including for each violation:
(1) the reason for the l
violation if admitted, (2) the corrective steps that have been taken and the
~
results achieved. (3) the corrective steps that will be taken to avoid further violations, and (4) the date when full compliance will be achieved. Where good cause is shown, consideration will be given to extending the response i
time.
l Dated at Arlington, lexas, this[q dday of p @ 1990 l