Forwards Suppl 2 to NRC Info Notice 89-059, Suppliers of Potentially Misrepresented Fasteners. Suppl Clarifies That Phoell Mfg Co May Not Have Been Supplier of nonsafety-related Fastener
ML20033E213
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 03/05/1990
From: Berlinger C
Office of Nuclear Reactor Regulation
To: Frederickson W
PHOELL MANUFACTURING CO.
References
IEIN-89-059, IEIN-89-59, NUDOCS 9003090388
Download: ML20033E213 (1)


Text

p f.

March.5, 1990 33 L

ne Mr. Walter. Frederickson i;

-Phoell Manufacturing Company 1313 Chestnut Avenue North Minneapolis, Minnesota 55403 g

Dear Mr. Frederickson:

Northern State Power Company's (NSP) letter of January 30, 1990, to Charles E.

Rossi clarified their January 29, 1988, response to NRC Bulletin 87-02, "Fas-tener Testing to Determine Conformance With Applicable Material Specifica-tions."' This clarification indicated that Phoell Manufacturing Company may not, in fact, have been the supplier of the non-safety-related fastener which they had previously reported as not meeting the specified carbon content for the applicable material specification.

i We have reviewed the information p' Suppliers of Potentially Misrepresentedrese j

to NRC Information Notice 89-59, j

Fasteners," is warranted.

A copy of this supplement'is attached for your information.

1 Original Signed By j

Carl fl. Berlmger i

Carl H. Berlinger, Chief Generic Communications Branch J

Division of Operational Events Assessment Office of Nuclear Reactor Regulation i

Enclosure:

NRC Information Notice 89-59, Supplement 2 1

' DISTRIBUTION w/enclosu_re FJMiraglia, NRR CERossi, NRR CHBerlinger, NRR RJKiessel, NRR

-JAcalvo, NRR PBaranowsky, NRR l

BKGrimes, NRR EWBrach, NRR GCCwalina, NRR l

L PDR-SCentrappleg"ia DCB L

00EA'R/F OGCB R/F

.RKiessel R/F l

ument Name:

LETTER TQ PHOELL MANUFACTURING

)

pg

,,9 j

1-OG A:NRR C/0GCB:00EA:NRR-A i

.RJKiessel CHBerlinger

\\

1 02/2 7/90 03/5/90 9003090388 900305

?

PDR ADOCK 05000202 #

G pnu y J

4-Enclosuro q

}l

~

1

' ~

l' UNITED STATES.

NUCLEAR REGULATORY COMMIS$10N

^

OFFICE OF NUCLEAR REACTOR REGULATION WASHINGTON, D.C.

20555 1

March 7, 1990

~

HRC INFORMATION NOTICE NO. 89-59, SUPPLEMENT 2: SUPPLIERS OF POTENTIALLY NISREPRESENTED FASTENERS i

J Addressees:

All holders of operating licenses or construction permits for nuclear power reactors

Purpose:

This information notice supplement is intended to inform addressees that the -

NRC has been notified by its original source, the Northern States Power Company (NSP),thatitcannotbedeterminedthatPhoellManufacturingdid,infact, o'

supply suspect fasteners.

It is expected that recipients will review the information for applicability to their facilities and consider actions, as a)propriate, to avoid similar problems.- However, suggestions contained in

-tiis information notice do not constitute NRC requirements; therefore, no

specific action or written response is required.

Background

NRC Information Notice (IN)'89-59, " Suppliers of Potentially Misrepresented l

Fasteners," was issued August 16,.1989, to provide addressees with the names L

- and addresses, if known, of companies suspected of supplying fasteners to the nuclear industry that may have been misrepresented, that is, marked as having a material content and composition different from the actual content. The names and addresses were taken from the data that the licensees-provided in L

response to NRC Bulletin 87-02, " Fastener Testing to Determine Conformance i

With Applicable Material Specifications."

Phoell Manufacturing was named in IN 89-59 as a result of test data that NSP supplied in response to NRC Bulletin 87-02. However, in a letter to the NRC dated January 30, 1990 NSP indicated that it is possible that Phoell Manu-facturing did not supply the non-safety-related fastener, which showed a lower-than-specified carbon content. NSP stated that their maintenance group consistently bought bolts of that size from Phoell Manufacturing. However, because it was a non-safety-related bolt, the bolt in question could have been left over from construction projects that had received materials from L

other suppliers.

-9003010293-

a IN 89-59, Supplement 2 1990

^

March 7,f 2

'^

Page 2 o i

4 { ~j -.

[

Discussion:

t Over the )ast'several years, various industries, associations, and ' Federal.

5 agencies 1 ave identified misrepresented fasteners among fasteners they have "c.

L' procured.

Because of the potential safety significance of using misrepre-sented fasteners, the NRC, in cooperation with'other Federal agencies, has

'been actively trying to. identify suspected suppliers or manufacturers of mis-i represented fasteners.

Because of. the potential adverse effect of releasing incorrect information about suppliers or manufacturers of com)onents, it is imperative that the information be correct.

In instances suc1 as this, the

'NRC relies on the licensees to provide' correct information.

7 This information notice requires no specific action or written response. Jf

)

4 you have any questions about the information in this notice, please contact the technical contact listed below or the appropriate NRR project manager.

~

[

Charles E.

ossi, D rector Division of Operational Events Assessment Office of Nuclear Reactor Regulation l

Technical

Contact:

Richard J. Kiessel, NRR (301)492-1154

Attachment:

List 'of Recently Issued NRC Information Notices A

Attachment

,.s IN 89-59, Supplement 2 1990-

. March 7,f 1 Page 1 o

,m n LIST OF RECENTLY ISSUED NRC INFORMATION NOTICES Information Date of flotice No.-

Subject-Issuance-Issued to "

90-16 Compliance with New 3/7/90

.All materials licensees.

Decommissioning Rule 90-15 Reciprocity:

Notification 3/7/90 All holders of HRC of Agreement State Radiation materials licenses.

Control Directors Before which authorize use-Beginning Work in Agreement of radioactive States material at temporary

-job sites.

}

90 Accidental Disposal of 3/6/90-All U.S. NRC byproduct Radioactive Materials material licensees.

t 90-13 Importance of Review and 3/5/90 All holders of Ots Analysis of Safeguards or cps for nuclear.

Event Logs power reactors.

90-12 Honitoring or Interruption 2/28/90 All holders of-OLs of Plant Comunications or cps for nuclear power reactors.

90-11 Maintenance Deficiency 2/28/90 All holders of OLs-Associated with Solenoid-

'or cps for nuclear.

4 Operated Valves power reactors.

90 Primary Water Stress 2/23/90 All holders of OLs Corrosion Cracking (PWSCC) or cps for PWRs.

of Inconel 600 m

L

.90-09 Extended Interim Storage of-2/5/90

-All holders of NRC Low-Level Radioactive Waste materials licenses.

- by Fuel Cycle and Materials Licensees

. 30, Target Rock Two-Stage SRV 2/2/90 All holders of OLs Supp. 1.

Setpoint Drift Update or cps for nuclear power reactors.

OL = Operating License CP = Construction Permit i