Advises That Info on Four of 56 Listed Licensing Review Group-II Issues,Per ,Will Be Incorporated Into OL Application
ML20033D270
Person / Time
Site: Clinton Constellation icon.png
Issue date: 12/03/1981
From: Wuller G
ILLINOIS POWER CO.
To: John Miller
Office of Nuclear Reactor Regulation
References
U-0343, U-343, NUDOCS 8112070470
Download: ML20033D270 (1)


Text

-

U-0343 ILLIN0/S POWER 00MPANY ffy g39_g3z32_g3y_g 500 SOUTH 27TH STREET, DECATUR. ILLINOIS 62525 December 3, 1981 1

Mr. James R. Miller, Chief i

E / '(b Standardizai. ion & Special Projects Branch Y

/

k 50)

Division of Licensing b [$ s Office of Nuclear Reactor Regulation s

ke/ @ [ ;-

U. S. Nuclear Regulatory Commission

. b 4

Washington, D. C.

20555

/

Dear Mr. Miller:

O>

s' / -

^

Clinton Power Station Unit 1 O'/ /1@M Docket No. 50-461 l

By the lotter dated December 2,1981, Mr. Dale Holtzscher, l

Chairman el the LRG-II Working Group provided Mr. Howard Faulkner, NRR Project Manager for LRG-II, with position papers on 4 of the 56 presently identified LRG-II issues.

As you know, Illinois Power Company is a member of the LRG-II.

We would like to advise you, in accordance with the practices developed by NRR and the LRG-II, that Illinois Power Company hereby incorporates the information provided in Mr. Holtzscher's December 3, 1991 letter into the Clinton Power Station OL application.

l For specificity, this December 2, 1981, lettet movides information on the LRG-II issues identified in the following manner.

3-RSB 3-ICSB 1-CPB 1-ASB-When subsequent LRG-II position papers are developed and provided to NRR, we intend to incorporate them in similar fasion.

Sincerely, G. E. Wuller Supervisor - Licensing _

Nuclear' Station Engineering DLH/cm cc:

J. H. Williams, NRC Clinton Project _. Manager H. H..Livermore, NRC Resilent Inspector.

H. F. Faulkner, NRC-LRG-II Project Manager si12070470 Oli PDR ADOCK 0500