OCT 29W Docket No.: S0-482 MEMORANDUM FOR:
B. J. Youngblood, Chief, Licensing Branch No.1, DL FR0ft:
G. E. Edison, Project Manager, Licensing Branch No.1, DL
SUBJECT:
FORTHCOMING MEETING !!!TH VJilSAS GAS AND ELECTRIC ",0ffPANY CONCERNING MATTERS RELATED TO CASELOAD FORECAST FOR THE WOLF CREEK GENERATING STATION, UNIT 1 DATE AND TIME:
Tuesday, Mednesday, and Thursday, November 17, 18, and 19, 1981 9:00 am LOCATION Coffey County Courthouse Burlington, Kansas PURPOSE:
To discuss matters related to caseload forecast for tne Wolf Creek Generating Station, Unit 1 (see attached agenda).
PARTICIPANTS:
NRC Staff, W. Lovelace, J. B. Hopkins, et al Kansas Cas & Electric Company G. Rathbun, et al
,/
/.
G. E. Edison, Project Manager Licensing Branch No. 1 Division 6f Licensing
Attachment:
As stated cc: See next page t
Note: Members of the public wishing to attend should contact G. E. Edison at 301-492-7219 by November 10, 1981 so that arrangements can be made for their attendance.
4 8111300019 811029 PDR ADOCK 05000482
^
.(\\
n/
DL:LB#1 AlV DL:LB#1sfi,..... A
.....!Ly.7 omcr >..............fg...
suam.c >..JHopkins/yt..GEd.ison.......
J.Yo
- d..
.10,/M/,81,,,,,,,,,,10/;;$8.1....,
.10
- 81..
.our)
Nnc ronu ais oo-soi necu oao OFFI'CI AL RECOR D COPY -
usam ini-m.co
E
..~
=
Mr. D. F. Schnell Mr. Glenn L. Koester Vice President - Nuclear Vice President - Nuclear Union Electric Company Kansas Gas and Electric Company P. O. Box 149
,201 North Market Street St. Louis, Missouri 63166 P. O. Box 208 Wichita, Kansas 67201 cc:
Gerald Charnoff, Esq.-
^
Shaw, Pittman, Potts, Trowbridge & Madden Mayor Howard Steffen 1800 M Street, N. W.
Chamois, Missouri 65024 Washiggton, D. C.
20036 Kansas City Power & Light Company Jay Silberg, Esquire ATTN: Mr. D. T. McPhee Shaw, Pittman, Potts & Trowbridge Vice President - Production 1800 M Street, N. W.
1330 Baltimore Avenue Washington, D. C.
20036 Kansas City, Missouri 64141 s
Mr. Donald W. Capone Mr. Nicholas A. Petrick Manager - Nuclear Engineering b
Executive Director, SNUPPS Union Electric Company 5 Choke Cherry Road P. O. Box 149 Rockville, Maryland 20850 St. Louis, Missou'ri 63166 7
Mr. J. E. Birk Ms. Mary Ellen Salva 1
Assistant to the General Counsel Route 1 Box 56 Union Electric Company Burlington, Kansas. 66839 St. Louis, Missouri 63166 Eric A. Eisen, Esq.
Kansans for Sensible Energy Birch, Horton, Bittner & Moore I.*0. Box 3192 1140 Connecticut Avenue, N. W.
Wichita, Kansas 67201 Washington, D. C.
20036 z
Mr. Tom Vandel Ms. Wanda Christy Resident Inspector / Wolf Creek NPS 515 N. 1st Street c/o USNRC Burlington, Kansas 66839 P. 0. Box 1407 Emporia, Kansas 66801 Ms. Marjorie Reilly Energy Chairman of the League Mr. Michael C. Keener of Women Voters of University Wolf Creek Project Director City, M0 State Corporation Commission 7065 Pershing Avenue State of Kansas University City, Missouri 63130 Fourth Floor, State Office Building E
Topeka, Kansas 66612 Mr. Fred Luekey Presiding Judge, Montgomery County Mr. William Hansen Rural Route U. S. Nuclear Regulatory Comission Rhineland, Missouri 65069 1
Resident Inspector Office RR #1 Professor William H. Miller
~'
Steedman, Missouri 65077 Missouri Kansas Section, American Nuclear Societ)
Depart of Nuclear Engineering iT 1026 Engineering Building University of Missouri
~
Columbia, Missouri 65211 o
m w
p..
~
2-Robert G.' Wright Associate' Judge, Eastern District County Court, Callaway County, Missouri Route #1 Fulton, Missouri 65251 Kenneth M. Chackes Chackes and Hoare Attorney for Joint Intervenors 314 N. Broadway St. Louis, Missouri 63102 Mr. Earl Brown School District Superintendent.
P. O. Box 9 Ringdom City, Missouri 65262 Mr. Samuel J. Birk R. R. #1, Box 243 Morrison, Missouri 65061 Mr. Harold Lottman Presiding Judge, Dasconade County Route 1 Owensville, Missouri 65066 A. Scott Cauger, Esq.
Assistant General Counsel for the Missouri Public Service Commission P. O. Box 360 Jefferson City, Missouri 65101 Ms. Barbara Shull Ms. Lenore Loeb League of Woman Voters of Missouri 2138 Woodson Road
' St. Louis, Missouri 63114 u
o e
e O
O b
y e
.j'~
- l..'.
i
~ CASELOAD FORECAST PANEL SITE VISIT MEETING AGENDA 1.
Overview of project construction scheoule including progress and major milestones completed, current problems and any anticipated problem areas that may impact the current projected fuel load date.
2.
Detailed review and current status of design and engineering effort (by major discipline) including any potential problems that may srise from necessary rework.
3.
De' tailed review and current status of procurement activities including valves, pipe, instruments, cable, major components, etc.
4.
Actual and proposed craft work force (by major craft), craft availability, productivity, potential labor negotiations and problems.
5.
Detailed review and current status of all large and small bore pipe hangers, restraints, snubbers, etc., including design, rework, procurement, fabrication, delivery and installation.
6.
Detailed review of project schedule identifying critical path items, near critical items, amount of float for various activities, the curr.ent critical path to fuel lcading,
?
methods of implementation of corrective action for any activities with negative float, and provisions for contingencies.
The estimated project percent complete as of September 30, 1981.
7.
Detailed review and current status of bulk quantities including current estimated quantities, quantities installed to date, quantities scheduled to date, current percent complete for eacli, actual versus forecast installation rates, and basis for figures.
(a) Concrete (CY)
(b) Process Pipe (LF)
Large Bore Pipe (21/2" and larger)
Small Bore Pipe (2" and smaller)
(c) Yard Pipe (LF)
(d) Large Bare Pipe Hangers, Restraints, Snubbers (ea)
- 4 i
l a.. -. _ _ _. - -
,,s.
(
(e) Small Bore Pipe Hangers, Restraints (ea)
(f) Cable Tray (LF)
(g) Total Conduit (LF)
(h) Total Exposed Metal Conduit (LF)
(1) Cable,(LF)
Power Control Security Instrumentation Plant Lighting (j) Termin$tions (ea)
Power Control Security Instrumentation Plant Lighting (k)
Electrical Circuits (ea)
Power Control Security (1) Instrumentation (ea) 8.
Detailed review and current status of preparation of preop and acceptsnce test procedures, integration of preop and acceptance test activities with construction schedule, system turnover schedule, preep and acceptance tests schedule, current and proposed preop and acceptance tests program manpower.
(a) Total number of procedures required for fuel laad.
(b) Number of draft procedures not started.
(c) Number of araft procedures being written.
(d) Number of procedures approved.
(e) Number of procedures in review.
(f) Total number of preep and acceptance tests required for fuel load.
(g) Number of preop and acceptance tests completed.
(h) Number of preop and acceptance tests currently in progress.
l
- (i) Number of systems turned over to start-up.
l 5
(
3-9.
Detailed discussion of potential schedular influence due to changes attributed to NUREG-0737 and other recent licensing requirements.
10.
Discussion of schedular impact, if any, regarding potential deficiencies reported in accordance with 10 CFR 50.5S(e).
11.
Financial comitments to complete the plant.
- 12. Overview of current construction management organization and activities.
13.
Site tour and observation of construction activities.
d b
I i
1 f
4 e
0
. ' a 9
~
MEETING NOTICE DISTRIBUTION C0icketiF11(7 J. Stolz NRC PDR S. Hanauer Local PDR P. Collins TIC g 1915B1 D. Vassallo NSIC D. Ziemann TERA T. Murley Branch File F. Schroeder E. Case K. Kniel D. Eisenhut D. Skovholt R. Purple G. Knighton T. Novak M. Erns t S. Varga R. Baer T. Ippolito E. Adensam R. A. Clark A. Thadani N. Hughes ACRS (16)
R. Tedesco Attorney, OELD J. Youngblood OIE (3)
A. Schwencer OSD (7)
F. Miraglia Project Manager GEdison J. R. Miller Licensing Assistant M. Rushbrook G. Lainas Receptionist D. Crutchfield W. Russell J. LeDoux, I&E J. Olshinki R. Vollmer I&E Headquarters R. Bosnak I&E Region I o
I F. Schauer I&E Region II M'\\
E R. E. Jackson I&E Region II G. Lear I&E Region IV T
W. Johnston I&E Region V $ $
g gi NRC ParticipakTN: h@
S. Pawlicki SI V. Benaroya Z. Rosztoczy
/)
WLovelace
\\A W. Haass
_f 4
D. Muller JHopkins R. Ballard W. Regan V. Moore-R. Mattson P. Check F. Congel
- 0. Parr bec: Applicant & Service List s
F. Rosa W. Butler W. Kreger R. W. Houston W. Gamill L. Rubenstein T. Speis M. Srinivasan B. Grimes S. Schwartz F. Pagano S. Ramos J. Kramer